Search Legislation

Environmental Protection Act 1990

 Help about what version

What Version

 Help about advanced features

Advanced Features

 Help about opening options

Opening OptionsExpand opening options

Changes over time for: Cross Heading: Period within which applications under Act to be determined

 Help about opening options

Alternative versions:

Changes to legislation:

Environmental Protection Act 1990, Cross Heading: Period within which applications under Act to be determined is up to date with all changes known to be in force on or before 15 June 2025. There are changes that may be brought into force at a future date. Changes that have been made appear in the content and are referenced with annotations. Help about Changes to Legislation

Period within which applications under Act to be determinedU.K.

Textual Amendments

F1Sch. 5 repealed (27.8.1993) by 1993 c. 12, ss. 50, 51(2), Sch. 6 Pt.I (with ss. 42, 46)

11(1)In section 1 of the 1960 Act (registration for users of radioactive material), after subsection (3) there shall be inserted the following subsection—

(3A)An application for registration under this section which is duly made to the chief inspector may be treated by the applicant as having been refused if it is not determined within the prescribed period for determinations or within such longer period as may be agreed with the applicant.

(2)In section 3 of that Act (registration for mobile apparatus), after the subsection (4A) inserted by paragraph 6(2) above there shall be inserted the following subsection—

(4B)An application for registration under this section which is duly made to the chief inspector may be treated by the applicant as having been refused if it is not determined within the prescribed period for determinations or within such longer period as may be agreed with the applicant.

(3)In section 8 of that Act (supplementary provisions relating to authorisations) after the subsection (3A) inserted by paragraph 4(2) above there shall be inserted the following subsection—

(3B)An application for an authorisation under section six or section seven of this Act (other than an application to which subsection (1) of this section applies) which is duly made to the chief inspector may be treated by the applicant as having been refused if it is not determined within the prescribed period for determinations or such longer period as may be agreed with the applicant.

(4)In section 19 of that Act (interpretation)—

(a)in subsection (1), after the definition of “prescribed”, there shall be inserted the following definition—

the prescribed period for determinations”, in relation to any applications under this Act, means, subject to subsection (1A) below, the period of four months beginning with the day on which the application was received;and

(b)after subsection (1), there shall be inserted the following subsection—

(1A)The Secretary of State may by order substitute for the period for the time being specified in the last preceding subsection as the prescribed period for determinations such other period as he considers appropriate.

Back to top

Options/Help

You have chosen to open The Whole Act

The Whole Act you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

You have chosen to open The Whole Act as a PDF

The Whole Act you have selected contains over 200 provisions and might take some time to download.

Would you like to continue?

You have chosen to open the Whole Act

The Whole Act you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

You have chosen to open the Whole Act without Schedules

The Whole Act without Schedules you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

You have chosen to open Schedules only

The Schedules you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?