[F1Higher-risk buildings in EnglandE+W

Textual Amendments

F1Ss. 30C-30I and cross-heading inserted (28.4.2022 for specified purposes, 6.4.2023 for specified purposes) by Building Safety Act 2022 (c. 30), ss. 112(2), 170(2) (with s. 164); S.I. 2023/362, reg. 3(1)(z10)(ii)

30HSpecific performance of implied termsE+W

In proceedings relating to a breach of a covenant in section 30C(2) or (3) (implied building safety terms), the court may order specific performance of the covenant—

(a)notwithstanding any equitable rule restricting the scope of the remedy, whether on the basis of a lack of mutuality or otherwise, and

(b)in the case of a breach of a covenant in section 30C(2) or (3)(b) or (c), whether or not the breach relates to a part of the higher-risk building let to the tenant.]