Part IIE+W Supervision of Building Work etc. otherwise than by [F1Local Authorities] [F1BUILDING CONTROL AUTHORITIES]

Textual Amendments

F1Words in Pt. 2 heading substituted (1.10.2023 except in relation to W., 6.4.2024 for W.) by Building Safety Act 2022 (c. 30), s. 170(4)(b)(c), Sch. 5 para. 39; S.I. 2023/993, reg. 2(n)(xii) (with reg. 4); S.I. 2024/207, reg. 2(d)(xi), Sch. (with regs. 3, 4, 8-12)

Supervision of plans and work by approved inspectorsE+W

[F253ERestriction on functions of registered building control approversE+W

(1)This section applies where—

(a)a new initial notice is given in accordance with section 53(7)(a) (change of registered building control approver in certain cases), and

(b)the notice is accepted by the local authority.

(2)During the period in respect of which—

(a)the notice is in force, but

(b)a transfer certificate and a transfer report have not been accepted by the local authority,

the registered building control approver may not exercise the relevant functions.

(3)In this section the “relevant functions” are the functions of a registered building control approver under, or under regulations made under—

(a)section 50 (plans certificates);

(b)section 51 (final certificates);

(c)section 51A (amendment notices).]

Textual Amendments

F2Ss. 53B-53E inserted (6.4.2023 for specified purposes except in relation to W., 5.9.2023 for W. for specified purposes) by Building Safety Act 2022 (c. 30), ss. 51(2), 170(4)(b)(c); S.I. 2023/362, reg. 3(1)(v); S.I. 2023/914, reg. 2(b)(xii)