Modifications etc. (not altering text)
C1Pt. 1 (ss. 1-46) restricted by Channel Tunnel Act 1987 (c. 53, SIF 102), ss. 31(1), 45, Sch. 7 Pt. VI para. 2
C2Pt. 1 (ss. 1-46) modified (1.4.1991) by National Health Service and Community Care Act 1990 (c. 19, SIF 113:2), s. 60(2), Sch. 8 para. 18(1)
C3Pt. 1 (ss. 1-46) modified (17.7.1992) by S.I. 1992/1732, art. 4(1)
C4Pt. 1 (ss. 1-46) excluded (18. 12. 1996) by 1996 c. 61, s. 38, Sch. 10 para.7PPt. I (ss. 1-46) excluded (26.3.2001) by S.I. 2001/1149, art. 4(5) (subject to art. 1(3))
C5Pt. 1 (ss. 1-46) excluded (22.7.2008) by Crossrail Act 2008 (c. 18), Sch. 14 para. 8
C6Pt. 1 (ss. 1-46) excluded (24.9.2014) by The Thames Water Utilities Limited (Thames Tideway Tunnel) Order 2014 (S.I. 2014/2384), art. 1, Sch. 19 Pt. 1 para. 3
C7Pt. 1 (ss. 1-46) excluded (23.2.2017) by High Speed Rail (London - West Midlands) Act 2017 (c. 7), s. 70(1), Sch. 22 para. 1
C8Pt. 1 excluded (11.2.2021) by High Speed Rail (West Midlands - Crewe) Act 2021 (c. 2), s. 64(1), Sch. 22 para. 1(1)(a) (with Sch. 22 para. 1(2)(3))
C9Pt. 1 excluded (4.10.2024) by The National Grid (Bramford to Twinstead Reinforcement) Order 2024 (S.I. 2024/958), art. 1, Sch. 15 para. 4 (with art. 40, Sch. 14)
Textual Amendments
F1S. 16 cross-heading substituted (1.10.2023 except in relation to W., 6.4.2024 for W.) by Building Safety Act 2022 (c. 30), s. 170(4)(b)(c), Sch. 5 para. 19; S.I. 2023/993, reg. 2(n)(ix); S.I. 2024/207, reg. 2(d)(xi), Sch. (with regs. 3, 4, 8-12)
F2(1). . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
F2(2). . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
(3)Any question arising under subsection [F3(4) below] between a [F4building control authority] and the person by whom, or on whose behalf, [F5plans are deposited] [F5an application for building control approval is made] as to [F6whether a proposed drain shall be required to connect with a sewer] may on the application of that person be determined by [F7the appropriate court or tribunal].
(4)[F8Where [F9plans of a building or of an extension of a building are, in accordance with building regulations, deposited with] [F9an application for building control approval in respect of a building or an extension of a building is made to] a [F4building control authority], the [F4building control authority], or on appeal [F10the appropriate court or tribunal], may require a proposed drain to connect with a sewer where]—
(a)that sewer is within one hundred feet of the site of the building or, in the case of an extension, the site either of the extension or of the original building, and is at a level that makes it reasonably practicable to construct a drain to communicate with it, and, if it is not a public sewer, is a sewer that the person constructing the drain is entitled to use, and
(b)the intervening land is land through which that person is entitled to construct a drain.
(5)Notwithstanding paragraph (a) of subsection (4) above, a drain may be required to be made to connect with a sewer that is not within the distance mentioned in that paragraph, but is otherwise such a sewer as is therein mentioned, if the authority undertake to bear so much of the expenses reasonably incurred in constructing, and in maintaining and repairing, the drain as may be attributable to the fact that the distance of the sewer exceeds the distance so mentioned.
(6)If any question arises as to the amount of a payment to be made to a person under subsection (5) above, that question may on his application be determined by [F11the appropriate court or tribunal], or he may require it to be referred to arbitration.
[F12(7)This section does not apply to works in connection with which approval is required in accordance with Schedule 3 to the Flood and Water Management Act 2010 (sustainable drainage).]
Textual Amendments
F2S. 21(1)(2) repealed (1.4.2002) by S.I. 2001/3335, reg. 3(1) (with reg. 4)
F3Words in s. 21(3) substituted (1.4.2002) by S.I. 2001/3335, reg. 3(2)(a) (with reg. 4)
F4Words in s. 21 substituted (1.10.2023 except in relation to W., 6.4.2024 for W.) by Building Safety Act 2022 (c. 30), s. 170(4)(b)(c), Sch. 5 para. 23(2); S.I. 2023/993, reg. 2(n)(xi) (with reg. 4); S.I. 2024/207, reg. 2(d)(xi), Sch. (with regs. 3, 4, 8-12)
F5Words in s. 21(3) substituted (1.10.2023 except in relation to W.) by Building Safety Act 2022 (c. 30), s. 170(4)(b)(c), Sch. 5 para. 23(3); S.I. 2023/993, reg. 2(n)(xi) (with reg. 3)
F6S. 21(3)(a)(b) substituted for words (1.4.2002) by S.I. 2001/3335, reg. 3(2)(b) (with reg. 4)
F7Words in s. 21(3) substituted (1.10.2023 except in relation to W., 6.4.2024 for W.) by Building Safety Act 2022 (c. 30), s. 170(4)(b)(c), Sch. 6 para. 9(b); S.I. 2023/993, reg. 2(o)(i) (with reg. 6); S.I. 2024/207, reg. 2(d)(xii) (with regs. 3, 4, 8-12)
F8Words in s. 21(4) substituted (1.4.2002) by S.I. 2001/3335, reg. 3(3) (with reg. 4)
F9Words in s. 21(4) substituted (1.10.2023 except in relation to W.) by Building Safety Act 2022 (c. 30), s. 170(4)(b)(c), Sch. 5 para. 23(4); S.I. 2023/993, reg. 2(n)(xi) (with reg. 3)
F10Words in s. 21(4) substituted (1.10.2023 except in relation to W., 6.4.2024 for W.) by Building Safety Act 2022 (c. 30), s. 170(4)(b)(c), Sch. 6 para. 9(b); S.I. 2023/993, reg. 2(o)(i) (with reg. 6); S.I. 2024/207, reg. 2(d)(xii) (with regs. 3, 4, 8-12)
F11Words in s. 21(6) substituted (1.10.2023 except in relation to W., 6.4.2024 for W.) by Building Safety Act 2022 (c. 30), s. 170(4)(b)(c), Sch. 6 para. 9(b); S.I. 2023/993, reg. 2(o)(i) (with reg. 6); S.I. 2024/207, reg. 2(d)(xii) (with regs. 3, 4, 8-12)
F12S. 21(7) added (2.5.2018 for W. for specified purposes, 7.1.2019 for W. in so far as not already in force) by Flood and Water Management Act 2010 (c. 29), s. 49(3), Sch. 3 para. 26(1) (with s. 49(1)(6)); S.I. 2018/557, arts. 2(b), 3(b)
Modifications etc. (not altering text)
C10Ss. 21, 22, 23 extended by S.I. 1987/798, regs. 2(1), 4