xmlns:atom="http://www.w3.org/2005/Atom"

SCHEDULEBritish Railways (No. 2)

Part IIILand

Purchase of specific new rights over land

14(1)The Board may, in addition to such new rights as they may purchase under section 13 (Purchase of new rights over land) of this Order, purchase compulsorily such new rights as they require in or over the land numbered on the deposited plan 19 in the Clackmannan District within the line marked “Limit of land to be used” for the purpose of providing means of access—

(a)in connection with the construction and maintenance of the works; and

(b)following completion of the works, for pedestrians proceeding to and from the station authorised by section 7 (Station works at Alloa) of this Order.

(2)For the avoidance of doubt, nothing in this section shall be taken as conferring a power to carry out works.