Determination of reportable emissions or aviation emissions by regulator

This section has no associated Explanatory Memorandum

45.—(1) The regulator must make a determination of emissions of an installation or an aircraft operator in either of the following circumstances—

(a)if the operator of the installation fails to submit a report of the installation’s reportable emissions in accordance with a condition of a permit included under paragraph 4(2)(b) of Schedule 6 or paragraph 11(2)(b) of Schedule 7;

(b)if the aircraft operator fails to submit a report of aviation emissions in accordance with article 33.

(2) Where a verifier states in a verification report under the Verification Regulation 2018 that there are non-material misstatements in the annual emissions report of the operator of an installation or of an aircraft operator that have not been corrected by the operator or the aircraft operator before the verification report is issued—

(a)the regulator must—

(i)assess the misstatements;

(ii)if the regulator considers it appropriate, make a determination of emissions of the installation or the aircraft operator; and

(iii)give notice to the operator or the aircraft operator as to whether or not corrections are required to the annual emissions report and, if corrections are required, set out the corrections in the notice; and

(b)the operator or the aircraft operator must make the information referred to in sub-paragraph (a)(iii) available to the verifier.

(3) The regulator may make a determination of emissions of an installation or of an aircraft operator in any of the following circumstances—

(a)if the operator of the installation fails to satisfy the regulator in accordance with a condition of a permit included under paragraph 4(2)(c) of Schedule 6 (as to sustainability criteria in respect of the use of bioliquids);

(b)if the operator of the installation fails to submit a report in accordance with paragraph 11(4)(b) of Schedule 6;

(c)if the operator of the installation fails to submit a report in accordance with paragraph 12(5)(b) of Schedule 6;

(d)if the regulator considers that the determination of emissions is necessary for the purpose of imposing, or considering whether to impose, a civil penalty under article 47.

(4) In making a determination under paragraph (3)(a), the regulator may substitute an emission factor of greater than zero for the factor reported in respect of the bioliquids concerned.

(5) A regulator who makes a determination of emissions must give notice of the determination to the operator, the aircraft operator or the person on whom the civil penalty may be imposed.

(6) A notice of a determination of emissions determines for the purposes of this Order (including for calculating a civil penalty under article 47) the installation’s reportable emissions or the aviation operator’s aviation emissions for the period to which the determination relates.

(7) Where, after making a determination of emissions (including a rectified determination of emissions, or a further rectified determination of emissions, made under this paragraph), the regulator considers that there is an error in the determination, the regulator must—

(a)withdraw any notice of the determination given under paragraph (5);

(b)make a rectified determination of the emissions; and

(c)give notice of the rectified determination in accordance with paragraph (5),

and paragraph (6) applies to a notice of the rectified determination as it does to the notice of the previous determination.

(8) For the purposes of this article, emissions must be determined on the basis of a set of assumptions designed to ensure that no under-estimation occurs.

Back to top

Options/Help

Print Options

You have chosen to open The Whole Instrument

The Whole Instrument you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

You have chosen to open The Whole Instrument as a PDF

The Whole Instrument you have selected contains over 200 provisions and might take some time to download.

Would you like to continue?

You have chosen to open the Whole Instrument

The Whole Instrument you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

Close

Legislation is available in different versions:

Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.

Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.

Close

Opening Options

Different options to open legislation in order to view more content on screen at once

Close

Draft Explanatory Memorandum

Draft Explanatory Memorandum sets out a brief statement of the purpose of a Draft Statutory Instrument and provides information about its policy objective and policy implications. They aim to make the Draft Statutory Instrument accessible to readers who are not legally qualified and accompany any Statutory Instrument or Draft Statutory Instrument laid before Parliament from June 2004 onwards.

Close

More Resources

Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as enacted version that was used for the print copy
  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • correction slips
  • links to related legislation and further information resources
Close

Impact Assessments

Impact Assessments generally accompany all UK Government interventions of a regulatory nature that affect the private sector, civil society organisations and public services. They apply regardless of whether the regulation originates from a domestic or international source and can accompany primary (Acts etc) and secondary legislation (SIs). An Impact Assessment allows those with an interest in the policy area to understand:

  • Why the government is proposing to intervene;
  • The main options the government is considering, and which one is preferred;
  • How and to what extent new policies may impact on them; and,
  • The estimated costs and benefits of proposed measures.
Close

More Resources

Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as made version that was used for the print copy
  • correction slips

Click 'View More' or select 'More Resources' tab for additional information including:

  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • links to related legislation and further information resources