47.—(1) A person who wishes to benefit from charitable relief must submit a claim for charitable relief to the collecting authority.
(2) A claim for charitable relief must—
(a)be received by the collecting authority before the commencement of the chargeable development to which it relates;
(b)be submitted in writing on a form published by the Secretary of State (or a form to substantially the same effect);
(c)include the particulars specified or referred to in the form; and
(d)where there is more than one material interest in the relevant land, be accompanied by an apportionment assessment.
(3) A claim for charitable relief will lapse where the chargeable development to which it relates is commenced before the collecting authority has notified the claimant of its decision on the claim.
(4) Where a claim is accompanied by an apportionment assessment the collecting authority may either—
(a)accept the claimant’s assessment; or
(b)substitute its own assessment.
(5) As soon as practicable after receiving a valid claim, the collecting authority must notify the claimant in writing of—
(a)its decision on the claim and the reasons for the decision; and
(b)where relief is granted, the amount of relief granted.
(6) A claim for charitable relief is valid if it complies with the requirements of paragraph (2).
(7) A person who is granted charitable relief ceases to eligible for that relief if a commencement notice is not submitted to the collecting authority on or before the day the chargeable development is commenced.
(8) Paragraph (9) applies where a charging authority issues a statement (in accordance with regulation 46(3)(a)) giving notice that discretionary charitable relief will no longer be available in its area.
(9) Any claim for discretionary charitable relief received by the collecting authority on or before the day mentioned in regulation 46(3)(a)) in respect of a chargeable development situated in the charging authority’s area must be considered by the collecting authority.
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Draft Explanatory Memorandum sets out a brief statement of the purpose of a Draft Statutory Instrument and provides information about its policy objective and policy implications. They aim to make the Draft Statutory Instrument accessible to readers who are not legally qualified and accompany any Statutory Instrument or Draft Statutory Instrument laid before Parliament from June 2004 onwards.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
Impact Assessments generally accompany all UK Government interventions of a regulatory nature that affect the private sector, civil society organisations and public services. They apply regardless of whether the regulation originates from a domestic or international source and can accompany primary (Acts etc) and secondary legislation (SIs). An Impact Assessment allows those with an interest in the policy area to understand: