SCHEDULE 25Waste and extractive waste
PART 2Requirements of authorities
Requirements applying to planning authorities4
1
Nothing in paragraph 1 or 2 of this Part requires a planning authority to deal with a matter which an appropriate authority or a regulator has power to deal with.
2
A planning authority must not grant planning permission or development consent for a landfill unless it has taken the requirements of paragraph 1.1 of Annex 1 to the Landfill Directive into consideration.
3
A mineral planning authority must not grant planning permission for a mining waste facility to which Article 7 of the Mining Waste Directive applies unless it is satisfied thatâ
a
the operator of that facility will meet the requirements of Article 11(2)(a) of that Directive; and
b
the management of waste at that facility will not conflict directly or otherwise interfere with the implementation of the plan or plans referred to in Article 7(3)(b) of that Directive.