1.—(1) The fee payable under regulation 3 for an application relating to a category of development in column 1 of the relevant table contained in Part 3 of this schedule is the fee calculated in accordance with the appropriate entry in column 2 of that table and paragraphs 1 to 11.
(2) The relevant table is—
(a)table 1 in relation to an application for—
(i)planning permission, or
(ii)approval, consent or agreement required by a condition imposed on a grant of planning permission in principle,
(b)table 2 in relation to an application for planning permission in principle,
(c)table 3 in relation to an application for a certificate of lawful use or development under section 150 or for a certificate of proposed use or development under section 151 of the 1997 Act,
(d)table 4 in relation to an application for a determination as to whether the planning authority’s prior approval is required in relation to development under schedule 1 of the General Permitted Development Order.
2. In this schedule—
(a)any reference to a category of development is a reference to one of the categories of development specified in column 1 of the relevant table, and
(b)in the case of an application for approval, consent or agreement required by a condition imposed on a grant of planning permission in principle, references to the category of development to which an application relates are to be construed as references to the category of development authorised by the relevant planning permission in principle.
3. Where, in respect of any category of development the fee must be calculated by reference to—
(a)the site area—
(i)that area is to be taken as consisting of the area of land to which the application relates, and
(ii)where the area is not an exact multiple of the unit of measurement specified in respect of the relevant category of development, the fraction of a unit remaining after division of the total area by the unit of measurement is to be treated as a complete unit, and
(b)the gross floor space—
(i)the area of gross floor space is to be ascertained by external measurement of the floor space, whether or not it is to be bounded wholly or partly by external walls of a building, and
(ii)where the floor is to be measured by units of 100 square metres any floor space remaining after division of the gross floor space by 100 square metres is to be treated as 100 square metres.
4. Where an application relates to development which is within more than one of the categories of development—
(a)an amount is to be calculated in respect of each category of development, and
(b)the highest amount so calculated is the fee payable in respect of the application.
5. In table 1 “glasshouse and polytunnel” means a building which—
(a)has not less than three-quarters of its total external area comprised of glass or other translucent material,
(b)is designed for the production of flowers, fruit, vegetables, herb or other horticultural produce, and
(c)is used, or is to be used, solely for the purposes of agriculture.
6. Where the application is for the approval, consent, or agreement required by a condition imposed on a grant of permission in principle and—
(a)the planning permission in principle was granted before 1 April 2022, and
(b)the application relates to development within categories 1, 4, 17, or 21 of table 1,
the fee payable under regulation 3 is subject to a maximum of £125,000.
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Policy Note sets out a brief statement of the purpose of a Scottish Statutory Instrument and provides information about its policy objective and policy implications. They aim to make the Scottish Statutory Instrument accessible to readers who are not legally qualified and accompany any Scottish Statutory Instrument or Draft Scottish Statutory Instrument laid before the Scottish Parliament from July 2012 onwards. Prior to this date these type of notes existed as ‘Executive Notes’ and accompanied Scottish Statutory Instruments from July 2005 until July 2012.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: