Savings3.
The 2019 Regulations continue to apply as they did immediately before 13 December 2022 in respect of any application made before that date—
(a)
for consent under section 36 of the Electricity Act 1989 (consent for construction etc. of generating stations) to construct, extend or operate a generating station,
(b)
under section 36C(1) of the Electricity Act 1989 (variation of consents under section 36) for variation of a consent granted under section 36 of that Act,
(c)
for consent under section 37 of the Electricity Act 1989 (consent required for overhead lines) to install or keep installed an electric line above ground.