SCHEDULEFEES
Fees for variation applications
3.
(1)
Subject to sub-paragraph (2), where a variation application is made, the fee payable in respect of the variation application is as specified in Table 3.
(2)
Where the subject matter of the variation application is two or more of the matters specified in Table 3, the fee to be paid is the higher or the highest of the relevant fees.
Variation application | Fee payable |
---|---|
1. A variation application which is not for EIA development and which, if granted, would increase the capacity of the generating station such that the increased capacity would— | |
| £5,850 |
| £22,500 |
| £63,000 |
| £90,000 |
| £135,000 |
| £164,400 |
| £200,500 |
| £200,500 + £15,000 for each additional 500 megawatts above 1 gigawatt |
2. A variation application which is for EIA development and which, if granted, would increase the capacity of the generating station such that the increased capacity would— | |
| £6,300 |
| £31,500 |
| £112,500 |
| £162,000 |
| £252,000 |
| £310,000 |
| £367,000 |
| £367,000 + £30,000 for each additional 500 megawatts above 1 gigawatt |
3. A variation application which is not for EIA development and which, if granted, would not increase the capacity of the generating station, where the generating station has a capacity— | |
| £5,740 |
| £22,500 |
4. A variation application which is for EIA development and which, if granted, would not increase the capacity of the generating station, where the generating station has a capacity— | |
| £6,300 |
| £31,500 |
| £112,500 |
| £162,000 |
| £252,000 |
| £310,000 |
| £367,000 |
| £367,000 + £30,000 for each additional 500 megawatts above 1 gigawatt |