Amendment of the Electricity (Applications for Consent) Regulations 19902.
(1)
(2)
“TABLE
Subject matter of application for consent
Fee
1. Overhead line with a total distance not exceeding 15 kilometres which is not EIA development
£180
2. Overhead line with a total distance not exceeding 15 kilometres which is EIA development
£2,400
3. Overhead line with a total distance—
- (a)
exceeding 15 kilometres but not exceeding 50 kilometres
£18,000
- (a)
exceeding 50 kilometres but not exceeding 100 kilometres
£30,000
- (a)
exceeding 100 kilometres
£60,000
4. Construction or construction and operation of a generating station of capacity—
- (a)
not exceeding 10 megawatts
£6,000
- (a)
exceeding 10 megawatts but not exceeding 100 megawatts
£18,000
- (a)
exceeding 100 megawatts but not exceeding 200 megawatts
£24,000
- (a)
exceeding 200 megawatts but not exceeding 500 megawatts
£36,000
- (a)
exceeding 500 megawatts
£60,000
5. Extension or extension and operation of a generating station resulting in increase in capacity—
- (a)
not exceeding 10 megawatts
£6,000
- (a)
exceeding 10 megawatts but not exceeding 100 megawatts
£18,000
- (a)
exceeding 100 megawatts but not exceeding 200 megawatts
£24,000
- (a)
exceeding 200 megawatts but not exceeding 500 megawatts
£36,000
- (a)
exceeding 500 megawatts
£60,000
6. Extension of a nuclear generating station by retrofitting of emission control equipment
£6,000
7. Any other extension of a generating station
£1,200
8. Operation only or change to manner of operation of a generating station
£1,200”