7. After article 22B (common agricultural policy requirements) insert—
22C.—(1) This article applies to a generating station which—
(a)is first commissioned after 31st March 2014;
(b)has a total installed capacity of more than 15 megawatts;
(c)generates electricity from relevant biomass.
(2) No SROCs are to be issued in respect of any electricity generated in any month by a generating station to which this article applies—
(a)unless the generating station is a qualifying combined heat and power station;
(b)if the generating station has not been a qualifying combined heat and power station during the whole or part of 5 or more obligation periods.
(3) In this article “relevant biomass” means biomass which is composed wholly or partly from wood which is not an energy crop.”.