PART 6Banding and grandfathering

The amount of electricity to be stated in each SROC27

1

Each SROC is to state the amount of electricity in respect of which it has been issued.

F12

The amount of electricity to be stated in each SROC depends on—

a

the way in which the electricity in respect of which it is to be issued has been generated; and

b

the type of generating capacity used to generate the electricity in respect of which the SROC is to be issued.

3

Subject to articles 28 to 32, the amount of electricity to be stated in each SROC is to be determined in accordance with paragraphs (4) to (10).

4

Each SROC to be issued in respect of electricity generated—

a

using pre–2013 capacity; and

b

in a way described in the first column of Part 2 of Schedule 2,

must state the amount of electricity which corresponds to that description in the second column of that Part of that Schedule.

5

Each SROC to be issued in respect of electricity generated—

a

using 2013/14 capacity; and

b

in a way described in the first column of Part 2A of Schedule 2,

must state the amount of electricity which corresponds to that description in the second column of that Part of that Schedule.

6

Each SROC to be issued in respect of electricity generated—

a

using 2014/15 capacity; and

b

in a way described in the first column of Part 2A of Schedule 2,

must state the amount of electricity which corresponds to that description in the third column of that Part of that Schedule.

7

Each SROC to be issued in respect of electricity generated—

a

using 2015/16 capacity; and

b

in a way described in the first column of Part 2A of Schedule 2,

must state the amount of electricity which corresponds to that description in the fourth column of that Part of that Schedule.

8

Each SROC to be issued in respect of electricity generated—

a

using post-2016 capacity; and

b

in a way described in the first column of Part 2A of Schedule 2,

must state the amount of electricity which corresponds to that description in the fifth column of that Part of that Schedule.

9

The amount of electricity to be stated in each SROC to be issued in respect of electricity generated—

a

using pre–2013 capacity; and

b

in a way which is not described in the first column of Part 2 of Schedule 2,

is one megawatt hour.

10

The amount of electricity to be stated in each SROC to be issued in respect of electricity generated—

a

using 2013/14 capacity, 2014/15 capacity, 2015/16 capacity or post-2016 capacity; and

b

in a way which is not described in the first column of Part 2A of Schedule 2,

is one megawatt hour.