44.—(1) Subject to paragraph (2), on receipt of a completion certificate the verifier shall proceed forthwith to consider the completion certificate and shall within the period of 14 days beginning with the date of receipt notify the person who submitted the certificate of its acceptance or rejection.
(2) In relation to a completion certificate submitted under section 17(4) of the Act, on receipt thereof the verifier shall proceed to consider the completion certificate in accordance with the provisions of regulation 9(1)(ii).
(3) Where a verifier accepts a completion certificate the verifier must send an acceptance in such form as the verifier thinks fit to the person who submitted the certificate.
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: