PART 6N.I.Banding and Grandfathering

[F1Qualifying new hydro stationsN.I.

27B.(1) This Article applies to a generating station which is a qualifying new hydro station.

(2) The amount of electricity to be stated in each NIROC which is issued in respect of electricity generated by a generating station to which this Article applies is—

(a)in relation to a qualifying new hydro station which has not had a declared net capacity in excess of 20 kilowatts at any time after 31st March 2010, ¼ megawatt hour;

(b)in relation to a qualifying new hydro station which has had a declared net capacity in excess of 20 kilowatts but not in excess 250 kilowatts at any time after 31st March 2010, ⅓ megawatt hour;

(c)[F2in relation to a qualifying new hydro station which has had a declared net capacity in excess of 250 kilowatts but not in excess of 1 megawatt at any time after 31st March 2010, ½ megawatt hour;

(d)in relation to a qualifying new hydro station which has had a declared net capacity in excess of 1 megawatt but not in excess of 5 megawatts at any time after 31st March 2010, 1 megawatt hour.]]