Changes over time for: Cross Heading: Adoption of water mains and service pipes

 Help about opening options

Alternative versions:

Status:

This version of this cross heading contains provisions that are prospective. Help about Status

Close

Status

The term provision is used to describe a definable element in a piece of legislation that has legislative effect – such as a Part, Chapter or section. A version of a provision is prospective either:

  1. where the provision (Part, Chapter or section) has never come into force or;
  2. where the text of the provision is subject to change, but no date has yet been appointed by the appropriate person or body for those changes to come into force.

Commencement Orders listed in the ‘Changes to Legislation’ box as not yet applied may bring this prospective version into force.

Changes to legislation:

The Water and Sewerage Services (Northern Ireland) Order 2006, Cross Heading: Adoption of water mains and service pipes is up to date with all changes known to be in force on or before 19 April 2024. There are changes that may be brought into force at a future date. Changes that have been made appear in the content and are referenced with annotations. Help about Changes to Legislation

Close

Changes to Legislation

Revised legislation carried on this site may not be fully up to date. Changes and effects are recorded by our editorial team in lists which can be found in the ‘Changes to Legislation’ area. Where those effects have yet to be applied to the text of the legislation by the editorial team they are also listed alongside the legislation in the affected provisions. Use the ‘more’ link to open the changes and effects relevant to the provision you are viewing.

View outstanding changes

Changes and effects yet to be applied to the whole Order associated Parts and Chapters:

Whole provisions yet to be inserted into this Order (including any effects on those provisions):

Adoption of water mains and service pipesN.I.

Prospective

Agreements to adopt water main or service pipe at a future dateN.I.

86.—(1) Subject to paragraphs (2) and (10), a water undertaker may agree with any person constructing or proposing to construct—

(a)any water main; or

(b)any service pipe,

that, if the water main or service pipe is constructed in accordance with the terms of the agreement, the undertaker will, upon completion of the work, at some specified date or on the happening of some future event, declare the water main or (as the case may be) so much of the service pipe as the undertaker could otherwise, by virtue of Articles 79 to 85, be required to lay, to be vested in that undertaker.

(2) Paragraph (1) shall not apply in the case of water mains or service pipes which are to be used (in whole or in part) for the purpose of supplying water other than for domestic purposes, but—

(a)nothing in this Article shall prevent a water undertaker from agreeing apart from this Article to declare any such water main or service pipe (or a part of it, as specified in the agreement) to be vested in the undertaker; and

(b)such a declaration shall take effect as a declaration made under this Chapter.

(3) A person constructing or proposing to construct a water main or a service pipe to which paragraph (1) applies may make an application in writing to a water undertaker requesting the undertaker to make an agreement under this Article.

(4) An application under paragraph (3) shall be accompanied and supplemented by all such information as the undertaker may reasonably require; but subject to paragraph (5) and without prejudice to the effect (if any) of any other contravention of the requirements of this Article in relation to such an application, a failure to provide information in pursuance of the obligation to supplement such an application shall not invalidate the application.

(5) Where—

(a)a person who has made an application to a water undertaker under paragraph (3) has failed to comply with his obligation under this Article to supplement that application with information required by the undertaker; and

(b)that requirement was made by the undertaker at such a time before the end of the period within which the undertaker is required, by virtue of Article 87, to respond to the application as gave that person a reasonable opportunity to provide the required information within that period,

the undertaker may delay its response to the application until a reasonable time after the required information is provided.

(6) In deciding whether or on what terms to grant an application under paragraph (3), a water undertaker shall have regard in particular to any effect or potential effect on the quality of water supplies and to any increased danger to life or health which it considers may result.

(7) The terms of an agreement under paragraph (1) relating to a water main may, in particular, include terms—

(a)for the provision (at the expense of the person constructing or proposing to construct the water main) by—

(i)that person; or

(ii)the water undertaker,

of such associated infrastructure at or downstream of the point of connection with the undertaker's supply system as it is necessary to provide in consequence of incorporating the new water main into that system;

(b)providing that, if the water main and the associated infrastructure are constructed in accordance with the terms of the agreement, the undertaker will, in addition to declaring the water main to be vested in it, declare the associated infrastructure to be so vested;

(c)where the undertaker considers that the proposed main is, or is likely to be, needed for the provision of water supply services in addition to those for which the person is proposing to construct the main—

(i)requiring that person to construct the main in a manner differing, as regards material or size of pipes, depth or otherwise, from the manner in which that person proposes, or could otherwise be required by the undertaker, to construct it; and

(ii)providing for the repayment by the undertaker of any extra expense reasonably incurred by that person in complying with that requirement;

(d)for the connection of the new water main to the undertaker's existing supply system at the point or points specified in the agreement;

(e)for any service pipes which the person constructing or proposing to construct the new water main proposes to connect to that main to be constructed in accordance with the terms of the agreement and, subject to that, to be vested in the undertaker at the same time as the main.

(8) The terms of an agreement under paragraph (1) relating to a service pipe may, in particular, include terms—

(a)for the connection of the new service pipe to the undertaker's existing supply system at the point or points specified in the agreement;

(b)for such requirements of the kind referred to in Article 82(2) as may be applicable to be complied with before connection takes place.

(9) An agreement made under this Article by a water undertaker shall be enforceable against the undertaker by the owner or occupier for the time being of any premises connected or to be connected with the water main or service pipe to which it relates.

(10) A water undertaker shall not make an agreement under this Article with respect to a water main or a service pipe situated within the area of another water undertaker, until either—

(a)that other undertaker has consented in writing to the making of the agreement; or

(b)the Authority, on an application made to it, has dispensed with the necessity for such consent, either unconditionally or subject to such conditions as the Authority may think fit to impose.

Prospective

Appeals with respect to adoptionN.I.

87.—(1) Subject to Article 86(5), a person constructing or proposing to construct a water main or service pipe may appeal to the Authority where the water undertaker—

(a)has refused an application under Article 86;

(b)has offered to grant such an application on terms to which that person objects; or

(c)has failed, before the end of two months from the making of such an application, either to refuse the application or to give notice to the applicant of the terms on which it is prepared to grant the application.

(2) On the hearing of an appeal under this Article, the Authority may—

(a)uphold the refusal of the undertaker to grant the application or to modify the terms offered; or

(b)on behalf of the undertaker, refuse the application or enter into any agreement into which the undertaker might have entered on the application.

(3) Where the Authority makes an agreement under paragraph (2)(b) on behalf of a water undertaker, it may do so on such terms as it considers reasonable or, as the case may be, on the terms offered by the undertaker subject to such modifications as it considers appropriate for ensuring that the terms of the agreement are reasonable.

(4) An agreement entered into on behalf of a water undertaker under paragraph (2)(b) shall be deemed, for the purposes of this Order, to have been entered into under Article 86.

(5) In deciding on an appeal under this Article, the Authority may include such incidental, supplemental and consequential provision (including provision requiring either party to pay a sum in respect of the costs or expenses incurred by the Authority) as it thinks fit, and any such provision as to costs or expenses shall be enforceable as if it were a money judgment within the meaning of the Judgments (Enforcement) (Northern Ireland) Order 1981(NI 6).

Prospective

Financial conditions of complianceN.I.

88.—(1) This Article applies where an agreement is, or is to be, entered into under Article 86 in relation to a water main (“the adopted main”) by, or on behalf of, a water undertaker and a person constructing or proposing to construct that water main.

(2) Where this Article applies, the water undertaker may, as a condition of the undertaker's compliance with the agreement, require that person to pay to it the reasonable costs incurred by it in connection with the adopted main as determined in accordance with the undertaker's charges scheme.

(3) For the purposes of any payment required to be made by virtue of paragraph (2), the water undertaker may require the person to provide such security as it may reasonably request, and the provisions of paragraphs (4) and (5) of Article 77 shall apply to any security so required as they apply to security required under that Article.

(4) Where this Article applies, the water undertaker shall pay to the person referred to in paragraph (1), upon declaring the water main to be vested in the undertaker—

(a)such sum as may be determined in accordance with the charges scheme of the undertaker; or

(b)if no such provision has been made in the charging scheme, such sum as the undertaker may with the approval of the Authority determine.

(5) Except in a case to which paragraph (4)(b) applies, any dispute between the water undertaker and the other person as to the payments required to be made or the security required to be provided by virtue of this Article may be referred to the Authority for determination under Article 61 by either party to the dispute.

Prohibition on connection without adoptionN.I.

89.—(1) Where a person (other than a water undertaker) constructs a water main or service pipe which is to be used, in whole or in part, for supplying water for domestic or food production purposes, no water undertaker may permit that water main or service pipe to become connected with its supply system unless it vests (to the relevant extent) in a water undertaker.

(2) In paragraph (1), “the relevant extent” means the extent specified in the agreement for the vesting in the undertaker of the water main or service pipe in question.

(3) The prohibition imposed on a water undertaker by paragraph (1) shall be enforceable under Article 30 by the Authority.

Commencement Information

I1Art. 89 wholly in operation at 1.4.2007, see art. 1(2) and S.R. 2007/194, art. 2(2), Sch. 1 Pt. II (subject to art. 3, Sch. 2)

Articles 86 to 89: supplementaryN.I.

90.—(1) For the purposes of Articles 86 to 89, the definition of “water main” in Article 2(2) shall be treated as if the words “not being a pipe for the time being vested in a person other than the undertaker” were omitted.

(2) In Article 86, references to so much of the service pipe as the undertaker could otherwise, by virtue of Articles 79 to 85, be required to lay shall be construed disregarding Article 80(8).

(3) In this Order, references to vesting or the making of a declaration of vesting with respect to a service pipe refer to so much of the service pipe as is specified for those purposes in the relevant vesting agreement.

Commencement Information

I2Art. 90 partly in operation; art. 90 not in operation at date of making see art. 1(2); art. 90 in operation for certain purposes at 1.4.2007 by S.R. 2007/194, art. 2(2), Sch. 1 Pt. II (subject to art. 3, Sch. 2)

Back to top

Options/Help

Print Options

You have chosen to open The Whole Order

The Whole Order you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

You have chosen to open The Whole Order as a PDF

The Whole Order you have selected contains over 200 provisions and might take some time to download.

Would you like to continue?

You have chosen to open The Whole Order without Schedules

The Whole Order without Schedules you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

You have chosen to open The Whole Order without Schedules as a PDF

The Whole Order without Schedules you have selected contains over 200 provisions and might take some time to download.

Would you like to continue?

You have chosen to open the Whole Order

The Whole Order you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

You have chosen to open the Whole Order without Schedules

The Whole Order without Schedules you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

Close

Legislation is available in different versions:

Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.

Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.

Close

See additional information alongside the content

Geographical Extent: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.

Show Timeline of Changes: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.

Close

Opening Options

Different options to open legislation in order to view more content on screen at once

Close

Explanatory Memorandum

Explanatory Memorandum sets out a brief statement of the purpose of a Northern Ireland Order in Council and provides information about its policy objective and policy implications. They aim to make the Order accessible to readers who are not legally qualified and accompany any Northern Ireland Order in Council made since 2002.

Close

More Resources

Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as enacted version that was used for the print copy
  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • correction slips
  • links to related legislation and further information resources
Close

Timeline of Changes

This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.

Close

More Resources

Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as made version that was used for the print copy
  • correction slips

Click 'View More' or select 'More Resources' tab for additional information including:

  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • links to related legislation and further information resources