Search Legislation

The Gas (Northern Ireland) Order 1996

 Help about what version

What Version

  • Latest available (Revised)
  • Original (As made)
 Help about advanced features

Advanced Features

More Resources

Changes over time for: Section 10AA

 Help about opening options

Changes to legislation:

The Gas (Northern Ireland) Order 1996, Section 10AA is up to date with all changes known to be in force on or before 25 April 2024. There are changes that may be brought into force at a future date. Changes that have been made appear in the content and are referenced with annotations. Help about Changes to Legislation

Close

Changes to Legislation

Revised legislation carried on this site may not be fully up to date. Changes and effects are recorded by our editorial team in lists which can be found in the ‘Changes to Legislation’ area. Where those effects have yet to be applied to the text of the legislation by the editorial team they are also listed alongside the legislation in the affected provisions. Use the ‘more’ link to open the changes and effects relevant to the provision you are viewing.

View outstanding changes

Changes and effects yet to be applied to Article 10AA:

Changes and effects yet to be applied to the whole Order associated Parts and Chapters:

Whole provisions yet to be inserted into this Order (including any effects on those provisions):

  • art. 18(1A)(aa) inserted by S.I. 2019/93, Sch. 1 para. 7(2)(b) (as substituted) by S.I. 2019/1245 reg. 24 (This amendment not applied to legislation.gov.uk. The affecting statutory instrument has no legal effect. It was made under a procedure which meant that it ceased to have effect 28 days after signing unless it was debated and approved in Parliament within that time. It was not debated and approved within 28 days, so it has expired with no effect.)

[F1Licensing and energy efficiencyN.I.

10AA.(1) Subject to paragraph (5), where a customer of the holder of a licence granted under Article 8(1)(c) takes a supply of gas through a smart meter, the conditions included in that licence must require the holder of the licence to ensure that—

(a)the meter complies with standards corresponding to those set out in Article 9(2)(a) and 10(2) of the Energy Efficiency Directive and where the customer so requests, Article 9(2)(c) of that Directive;

(b)the customer is provided with the information specified in Article 9(2)(a) and 10(2) of the Energy Efficiency Directive;

(c)the customer is provided with the information specified in Article 10(2)(b) of the Energy Efficiency Directive in the manner mentioned in that provision;

(d)where the customer so requests, the customer or another person acting on the customer's behalf is provided with the information specified in Article 9(2)(d) of the Energy Efficiency Directive in the manner mentioned in that provision;

(e)the meter is physically secure and any information provided by it is held in a manner that complies with the requirements of any relevant legislation relating to data protection; and

(f)advice and information specified in Article 9(2)(e) of the Energy Efficiency Directive is provided to the customer.

(2) For the purposes of paragraph (1)(b) and (c), the reference to Article 10(2) of the Energy Efficiency Directive is to be read as a reference to that Article with the modifications that—

(a)the words “installed in accordance with Directives 2009/72/EC and 2009/73/EC” are to be omitted; and

(b)the reference to “Member States” is to be read as a reference to “the Authority”.

(3) Where a customer of the holder of a licence under Article 8(1)(c) does not take a supply of gas through a smart meter, the conditions included in that licence must require the holder of the licence to ensure that any bill or statement of account provided to the customer is accurate and based on actual consumption and that the information specified in paragraph 1.1 of Annex VII to the Energy Efficiency Directive is provided to the customer in the manner specified in that provision.

(4) The conditions included in a licence under Article 8(1)(c) must require the holder of the licence to ensure that—

(a)where a customer so requests, the information specified in Article 10(3)(a) of the Energy Efficiency Directive is provided to an energy service provider designated by the customer;

(b)any bill or statement of account sent to the customer—

(i)contains the information specified in Article 10(3)(c) of and paragraph 1.2 and 1.3 of Annex VII to the Energy Efficiency Directive;

(ii)complies with any guidance issued and published by the Authority; and

(iii)where the customer so requests, is provided in an electronic format;

(c)where a customer so requests, the information specified in Article 10(3)(b) of the Energy Efficiency Directive is provided to the customer;

(d)any customer taking a supply of gas from the licence holder is provided with the information specified in paragraph 1.3 of Annex VII to the Energy Efficiency Directive in contract documentation;

(e)any information provided to a customer in accordance with conditions included under this paragraph is provided in a timely manner and in an easily understandable format enabling customers to compare deals on a like-for-like basis;

(f)a charge is not made in respect of any bill or statement of account sent to a customer or in respect of any information provided to the customer (whether in the bill or statement of account or otherwise).

(5) The duty on the Authority in paragraph (1) to include conditions in a licence only has effect where the Department—

(a)has determined that it is technically possible, financially reasonable and proportionate in relation to the potential energy savings to implement a programme for the widespread provision of smart meters; and

(b)notifies the Authority in writing to that effect.

(6) In this Article—

(a)the Energy Efficiency Directive” means the European Parliament and Council Directive 2012/27/EU on energy efficiency, amending Directives 2009/125/EC and 2010/30/EU and repealing Directives 2004/8/EC and 2006/32/EC;

(b)smart meter” means—

(i)a gas meter which can send and receive information using an electronic communications network; or

(ii)a gas meter and a device which is associated with or ancillary to that meter and which enables information to be sent and received by the meter using an electronic communication network;

(c)electronic communications network” has the same meaning as in section 32 of the Communications Act 2003; and

(d)other expressions which are also used in the Energy Efficiency Directive have the same meaning as in that Directive.]

Back to top

Options/Help

Print Options

Close

Legislation is available in different versions:

Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.

Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.

Close

See additional information alongside the content

Geographical Extent: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.

Show Timeline of Changes: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.

Close

Opening Options

Different options to open legislation in order to view more content on screen at once

Close

More Resources

Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as enacted version that was used for the print copy
  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • correction slips
  • links to related legislation and further information resources
Close

Timeline of Changes

This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.