13—(1) Registration under section 10 of a structure or area which is to be treated as a controlled reservoir by virtue of regulations made under subsection (3) of section 2 must, subject to subsection (2), take place not later than 28 days after the day on which notice of the making of the regulations is served by the Department under subsection (4) of that section.

(2) The Department may, in relation to information or a document where it considers it appropriate to do so, extend the period of 28 days specified in subsection (1) to such other period as it may, by notice served on the reservoir manager, specify; and different periods may be specified in relation to different information or documents.