Planning Act (Northern Ireland) 2011

IntroductoryN.I.

Expressions used in connection with enforcementN.I.

131—(1) For the purposes of this Act—

(a)carrying out development without the planning permission required; or

(b)failing to comply with any condition or limitation subject to which planning permission has been granted,

constitutes a breach of planning control.

(2) For the purposes of this Act—

(a)the issue of an enforcement notice; or

(b)the service of a breach of condition notice,

constitutes taking enforcement action.

Modifications etc. (not altering text)

C2Pt. 5 (except ss. 157-163) applied with modification(s) (1.4.2015) by The Planning General Regulations (Northern Ireland) 2015 (S.R. 2015/39), regs. 1(1), 2 (with regs. 3-10)

Commencement Information

I1S. 131 in operation at 13.2.2015 for specified purposes by S.R. 2015/49, art. 2, Sch. 1

I2S. 131 in operation at 1.4.2015 in so far as not already in operation by S.R. 2015/49, art. 3, Sch. 1 (with Sch. 2) (as amended (16.3.2016) by S.R. 2016/159, art. 2)

Time limitsN.I.

132—(1) Where there has been a breach of planning control consisting in the carrying out without planning permission of building, engineering, mining or other operations in, on, over or under land, no enforcement action may be taken after the end of the period of 5 years beginning with the date on which the operations were substantially completed.

(2) Where there has been a breach of planning control consisting in the change of use of any building to use as a single dwelling-house, no enforcement action may be taken after the end of the period of 5 years beginning with the date of the breach.

(3) In the case of any other breach of planning control, no enforcement action may be taken after the end of the period of 5 years beginning with the date of the breach.

(4) The preceding subsections do not prevent—

(a)the service of a breach of condition notice in respect of any breach of planning control if an enforcement notice in respect of the breach is in effect; or

(b)taking further enforcement action in respect of any breach of planning control if, during the period of 5 years ending with that action being taken, the council or the Department has taken or purported to take enforcement action in respect of that breach.

Modifications etc. (not altering text)

Commencement Information

I3S. 132 in operation at 13.2.2015 for specified purposes by S.R. 2015/49, art. 2, Sch. 1

I4S. 132 in operation at 1.4.2015 in so far as not already in operation by S.R. 2015/49, art. 3, Sch. 1 (with Sch. 2) (as amended (16.3.2016) by S.R. 2016/159, art. 2)