2.—(1) The Act is amended as follows.

(2) After section 14(1)(n) (nationally significant infrastructure projects: general)(1), insert—

(na)the construction or alteration of a desalination plant;.

(3) In section 27 (dams and reservoirs)—

(a)for subsection (1)(c), substitute—

(c)it is expected that—

(i)the volume of water to be held back by the dam or stored in the reservoir will exceed 30 million cubic metres, or

(ii)the deployable output of the dam or reservoir will exceed 80 million litres per day.;

(b)for subsection (2)(c), substitute—

(c)it is expected that—

(i)the additional volume of water to be held back by the dam or stored in the reservoir as a result of the alteration will exceed 30 million cubic metres, or

(ii)the additional deployable output of the dam or reservoir as a result of the alteration will exceed 80 million litres per day..

(4) For section 28(1)(b) (transfer of water resources), substitute—

(b)it is expected that—

(i)the deployable output of the facility to be constructed as a result of the development will exceed 80 million litres per day, or

(ii)the additional deployable output of the facility to be altered as a result of the development will exceed 80 million litres per day,.

(5) After section 28 insert—

28A    Desalination plants

(1) The construction of a desalination plant is within section 14(1)(na) only if—

(a)the desalination plant (when constructed) will be in England or in waters adjacent to England up to the seaward limits of the territorial sea,

(b)the construction will be carried out by one or more water undertakers, and

(c)the deployable output of the desalination plant is expected to exceed 80 million litres per day.

(2) The alteration of a desalination plant is within section 14(1)(na) only if—

(a)the desalination plant is in England or in waters adjacent to England up to the seaward limits of the territorial sea,

(b)the alteration will be carried out by one or more water undertakers, and

(c)the additional deployable output of the desalination plant as a result of the alteration is expected to exceed 80 million litres per day.

(3) “Water undertaker” means a company appointed as a water undertaker under the Water Industry Act 1991..

(6) In section 235(1) (interpretation)(2) insert in the appropriate place—

“deployable output” means, in relation to a given facility, the annual average volume of water that can be produced per day from that facility under drought conditions, having regard in particular (where applicable) to—

(a)

the hydrological yield of the facility;

(b)

the quantity of water licensed for abstraction;

(c)

the state of the local environment;

(d)

the properties of any—

(i)

pumping plant;

(ii)

well;

(iii)

aquifer;

(iv)

raw water main;

(v)

aqueduct;

(vi)

transfer main;

(vii)

output main;

(e)

any water treatment processes;

(f)

any requirements relating to water quality;

“desalination plant” means a facility for the extraction of mineral components from saline water;

“drought conditions” means conditions resulting from a shortage of precipitation that has a 0.5% chance of occurring within a 12 month period;.

(1)

Section 14(1) was amended by S.I. 2012/1645 and 2015/949.

(2)

Section 235(1) was amended by the Localism Act 2011, Schedule 13, Part 1, paragraph 69.

Back to top

Options/Help

Print Options

Close

Legislation is available in different versions:

Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.

Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.

Close

Opening Options

Different options to open legislation in order to view more content on screen at once

Close

Explanatory Memorandum

Explanatory Memorandum sets out a brief statement of the purpose of a Statutory Instrument and provides information about its policy objective and policy implications. They aim to make the Statutory Instrument accessible to readers who are not legally qualified and accompany any Statutory Instrument or Draft Statutory Instrument laid before Parliament from June 2004 onwards.

Close

More Resources

Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as enacted version that was used for the print copy
  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • correction slips
  • links to related legislation and further information resources
Close

More Resources

Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as made version that was used for the print copy
  • correction slips

Click 'View More' or select 'More Resources' tab for additional information including:

  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • links to related legislation and further information resources