Search Legislation

The London Gateway Port Harbour Empowerment Order 2008

Changes to legislation:

There are outstanding changes not yet made by the legislation.gov.uk editorial team to The London Gateway Port Harbour Empowerment Order 2008. Those changes will be listed when you open the content using the Table of Contents below. Any changes that have already been made by the team appear in the content and are referenced with annotations. Help about Changes to Legislation

Close

Changes to Legislation

Revised legislation carried on this site may not be fully up to date. Changes and effects are recorded by our editorial team in lists which can be found in the ‘Changes to Legislation’ area. Where those effects have yet to be applied to the text of the legislation by the editorial team they are also listed alongside the affected provisions when you open the content using the Table of Contents below.

View outstanding changes

Changes and effects yet to be applied to :

  1. Introductory Text

  2. PART 1

    1. 1.Citation and commencement

    2. 2.Interpretation

    3. 3.Incorporation of the Harbours, Docks and Piers Clauses Act 1847

    4. 4.Byelaws

    5. 5.Application of the Local Government Act 1972

    6. 6.Application of the New Roads and Street Works Act 1991

    7. 7.Incorporation of the Railways Clauses Consolidation Act 1845

  3. PART 2

    1. 8.Jurisdiction of the Harbour Authority

    2. 9.Agreements entered into by the Company, etc.

  4. PART 3

    1. 10.Power to construct, etc., works

    2. 11.Power to construct, etc., pontoons and jetties

    3. 12.Further mitigation and compensation works

    4. 13.Power to dredge

    5. 14.Power to deviate

    6. 15.Fine for obstructing works

    7. 16.Tidal works not to be constructed without approval of the Secretary of State

    8. 17.Provision against danger to navigation

    9. 18.Lights on tidal works, etc.

    10. 19.Stopping up, diversion, provision and upgrading of footpaths and bridleways

    11. 20.Power to alter layout of streets, etc.

    12. 21.Power to execute street works

    13. 22.Temporary stopping up of streets

    14. 23.Agreements with street authorities

    15. 24.Construction of bridges

    16. 25.Level crossings

    17. 26.Application of permitted development rights

    18. 27.Defence to proceedings in respect of statutory nuisance

  5. PART 4

    1. 28.Power to acquire land

    2. 29.Application of Part 1 of the Compulsory Purchase Act 1965

    3. 30.Application of the Compulsory Purchase (Vesting Declarations) Act 1981

    4. 31.Disregard of certain interests and improvements

    5. 32.Extinction of private rights of way

    6. 33.Time limit for exercise of powers of acquisition

  6. PART 5

    1. 34.Duty of the Harbour Authority

    2. 35.Power to make charges

    3. 36.Power to enter vessels

    4. 37.Recovery and enforcement of charges

    5. 38.Time when charges are payable and their recovery

    6. 39.Security for charges

    7. 40.Disputes concerning rates

    8. 41.Objection and arbitration in relation to charges

    9. 42.Power to appropriate berths, etc.

    10. 43.Power to remove goods

    11. 44.Power to operate and use railways

    12. 45.Saving for regulated rights, etc.

    13. 46.Powers of disposal

    14. 47.Conservation

    15. 48.Obstruction of officers

    16. 49.Arrangements with Her Majesty’s Revenue and Customs

    17. 50.Agreements with Network Rail

    18. 51.Power to establish a police force

    19. 52.Incorporation of Police and Criminal Evidence Act 1984

    20. 53.Refusal of a landing place, etc.

    21. 54.Power to discharge surface water into the river

    22. 55.Harbour Authority not to be a local lighthouse authority

    23. 56.Harbour Authority not to be a port health authority

  7. PART 6

    1. 57.Crown rights

    2. 58.For the protection of the local highway authority

    3. 59.For the protection of Thurrock Borough Council and others

    4. 60.For the protection of Network Rail

    5. 61.For the protection of the Port of London Authority

    6. 62.For the protection of the Trinity House Lighthouse Service

    7. 63.For the protection of the Environment Agency

    8. 64.For the protection of National Grid Gas plc and other statutory undertakers

  8. PART 7

    1. 65.No double recovery

    2. 66.Arbitration

    3. 67.Defence of due diligence

    4. 68.Local inquiries

    5. 69.Certification of plans, etc.

  9. Signature

  10. SCHEDULES

    1. SCHEDULE 1

      WORKS

      1. 1.In this Schedule— (a) “Chainage Reference” means the relevant chainage...

      2. 2.The works referred to in article 10(1) are— Work No....

    2. SCHEDULE 2

      RESTRICTIONS ON WORKS

      1. 1.In this Schedule, “building” does not include any form of...

      2. Containers and associated equipment

        1. 2.Within the port premises, containers may not be stacked above...

        2. 3.Within the port premises, gantry cranes used for stacking or...

        3. 4.Quayside container cranes may only be used in the area...

        4. 5.Quayside equipment other than container cranes, such as general cargo...

      3. Other height restrictions

        1. 6.Subject to paragraph 10, in the area washed in yellow...

        2. 7.In the area washed in blue on the planning restrictions...

        3. 8.Material dredged pursuant to article 13 (power to dredge) may...

        4. 9.Within the port premises, internal harbour security fencing shall not...

      4. Railways

        1. 10.In the area cross-hatched on the planning restrictions plan, railway...

        2. 11.Only in the area cross-hatched on the planning restrictions plan...

      5. Other construction restrictions

        1. 12.No flood lighting columns shall be constructed within 50 metres...

        2. 13.No more than five entry and exit complexes with associated...

        3. 14.No more than one multi-storey car storage facility is permitted...

        4. 15.No more than one multi-storey car park is permitted with...

      6. Activities permitted for construction or operational purposes only

        1. 16.Once constructed— (a) no part of the water frontage of...

        2. 17.Construction plant, concrete batching plant, temporary grading, washing and weighing...

        3. 18.Storage of fuels including diesel, petroleum or liquid petroleum gas...

        4. 19.The underground storage and pumping of storm, surface and waste...

        5. 20.The construction and operation of electricity sub-stations is only permitted...

        6. 21.No signage is permitted within the port premises other than...

        7. 22.No relocation, reconstruction or improvement of the existing bitumen and...

        8. 23.Subject to paragraph 24, the area of jurisdiction shall not...

        9. 24.Paragraph 23 shall not preclude— (a) the permanent use of...

      7. Application of Town and Country Planning legislation

        1. 25.The provisions of this Schedule shall be deemed to be...

    3. SCHEDULE 3

      DREDGING WORKS

      1. 1.In this Schedule— (a) “Coordinates Reference” means the relevant coordinates...

      2. 2.The works referred to in article 13(1) are as follows—...

    4. SCHEDULE 4

      STOPPING UP OF FOOTPATHS AND BRIDLEWAY AND NEW PUBLIC RIGHTS OF WAY TO BE SUBSTITUTED

    5. SCHEDULE 5

      APPLICATION OF PERMITTED DEVELOPMENT RIGHTS

      1. PART 1 GENERAL PERMITTED DEVELOPMENT

        1. 1.(1) In their application to any development authorised by this...

        2. 2.(1) Any change of use of the port premises to...

      2. PART 2 HABITATS REGULATIONS

        1. 3.Subject to paragraph 4, regulation 60(1) of the Habitats Regulations...

        2. 4.If and to the extent that any development authorised by...

    6. SCHEDULE 6

      FOR THE PROTECTION OF THURROCK BOROUGH COUNCIL AND OTHERS

      1. General

        1. 1.The following provisions of this Schedule shall have effect for...

        2. 2.(1) In this Schedule— “the A13 Lakeside Link” means that...

      2. The authorised works in combination with the related development

        1. 3.In circumstances where the related development is materially implemented and...

        2. 4.None of the B1(b), B1(c), B2 or B8 uses or...

        3. 5.(1) This paragraph shall apply unless the Highways Agency acting...

        4. 6.No more than the following combinations of B1(b), B1(c), B2...

        5. 7.No more than the following combinations of B1(b), B1(c), B2...

        6. 8.No more than the following combinations of B1(b), B1(c), B2...

        7. 9.No more than 100,000m2 of the B1(b), B1(c), B2 and...

        8. 10.No more than the following combinations of B1(b), B1(c), B2...

        9. 11.No more than 157,000m2 of B1(b), B1(c), B2 and B8...

        10. 12.No more than 167,000m2 of B1(b), B1(c), B2 and B8...

        11. 13.No more than the following combinations of B1(b), B1(c), B2...

      3. The authorised works without the related development

        1. 14.(1) In circumstances where the related development is not materially...

      4. Travel Plan

        1. 15.None of the authorised works shall be brought into beneficial...

      5. Noise mitigation measures

        1. 16.Prior to bringing into beneficial use any of the authorised...

        2. 17.(1) The Harbour Authority and the appropriate authority shall agree...

      6. Sustainable handling and transport

        1. 18.Construction of the authorised works shall not be commenced until...

      7. Storage of fluids

        1. 19.Notwithstanding the provisions of the 1995 Order any oil and...

      8. Application of Town and Country Planning legislation

        1. 20.The provisions of this Schedule shall be deemed to be...

    7. SCHEDULE 7

      FOR THE PROTECTION OF NETWORK RAIL

      1. 1.(1) The provisions of this Schedule shall, unless otherwise agreed...

      2. 2.The Harbour Authority shall not, under the powers conferred by...

      3. 3.The provisions of article 32 (extinction of private rights of...

      4. 4.The exercise by the Harbour Authority against Network Rail of...

      5. 5.Where Network Rail is asked to give its consent pursuant...

      6. 6.The Harbour Authority shall before commencing construction of the specified...

      7. 7.The approval of the engineer under paragraph 6 shall not...

      8. 8.If by the end of the period of 56 days...

      9. 9.(1) When signifying his approval of the plans the engineer...

      10. 10.Any specified work and any protective works to be constructed...

      11. 11.The Harbour Authority shall— (a) at all times afford reasonable...

      12. 12.Network Rail shall at all times afford reasonable facilities to...

      13. 13.(1) If any alterations or additions, either permanent or temporary,...

      14. 14.The Harbour Authority shall repay to Network Rail all reasonable...

      15. 15.If at any time after the completion of a specified...

      16. 16.The Harbour Authority shall not provide any illumination or illuminated...

      17. 17.Any additional expenses which Network Rail may reasonably incur in...

      18. 18.The Harbour Authority shall pay to Network Rail all reasonable...

      19. 19.Network Rail shall give to the Harbour Authority reasonable notice...

      20. 20.(1) In this paragraph— “EMI” means, subject to sub-paragraph (2),...

      21. 21.(1) The sums payable by the Harbour Authority under paragraph...

    8. SCHEDULE 8

      FOR THE PROTECTION OF THE PORT OF LONDON AUTHORITY

      1. General

        1. 1.(1) The provisions of this Schedule shall, unless otherwise agreed...

      2. Tidal Works: approval of detailed design

        1. 2.(1) Before— (a) submitting any plans and sections for any...

        2. 3.Subject to paragraph 21, no tidal work shall be subject...

        3. 4.Any operations for the construction of any tidal work approved...

      3. Discharges, etc.

        1. 5.(1) The Harbour Authority shall not without the consent of...

        2. 6.The Harbour Authority shall not, in exercise of the powers...

      4. Obstruction in river

        1. 7.If any pile, stump or other obstruction to navigation becomes...

      5. Removal, etc. of PLA moorings and buoys

        1. 8.If— (a) by reason of the construction of any tidal...

      6. Navigational lights, buoys, etc.

        1. 9.In addition to any requirement under article 18 (lights on...

      7. Removal of temporary works

        1. 10.On completion of the construction of any part of a...

      8. Protective action

        1. 11.(1) If any tidal work— (a) is constructed otherwise than...

      9. Abandoned or decayed works

        1. 12.(1) If any tidal work or any other work of...

      10. Facilities for navigation

        1. 13.(1) The Harbour Authority shall not in the exercise of...

      11. Survey of riverbed

        1. 14.(1) Before the commencement of construction of the first tidal...

      12. Sedimentation, etc.: remedial action

        1. 15.(1) This paragraph applies if any part of the river...

      13. Indemnity

        1. 16.(1) The Harbour Authority shall be responsible for and make...

      14. Dedication of land for conservation, etc.

        1. 17.(1) Before dedicating or designating any land under article 47...

      15. Statutory functions

        1. 18.(1) Subject to article 4(3) and this paragraph, any function...

      16. Vesting of reclaimed river bed

        1. 19.(1) Section 72 of the 1968 Act (vesting of embanked...

      17. Compensation for river bed

        1. 20.Notwithstanding paragraph 3, and unless otherwise agreed in writing between...

      18. Maintenance dredging

        1. 21.For the avoidance of doubt, section 73 of the 1968...

      19. Consideration for dredged material

        1. 22.(1) The Harbour Authority shall pay to the PLA for...

      20. Removal of wrecks and obstructions, etc.

        1. 23.(1) Before exercising any power under section 252 of the...

      21. Disputes

        1. 24.Any dispute arising between the Harbour Authority and the PLA...

    9. SCHEDULE 9

      FOR THE PROTECTION OF THE TRINITY HOUSE LIGHTHOUSE SERVICE

      1. General

        1. 1.The provisions of this Schedule shall, unless otherwise agreed in...

        2. 2.Nothing in this Order shall prejudice or derogate from any...

      2. Indemnity

        1. 3.(1) The Harbour Authority shall be responsible for and reimburse...

    10. SCHEDULE 10

      FOR THE PROTECTION OF THE ENVIRONMENT AGENCY

      1. General

        1. 1.(1) The provisions of this Schedule shall, unless otherwise agreed...

      2. Definitions applying to this Schedule

        1. 2.In this Schedule— “accumulation” means any accumulation of silt or...

      3. Tidal works

        1. 3.(1) At the same time as submitting any plans and...

      4. Pre-conditions to commencing specified work

        1. 4.(1) Before beginning to construct any specified work other than...

      5. Survey of any drainage work liable to be affected by a specified work

        1. 5.Before commencing the construction of a specified work liable to...

      6. Maintenance by Harbour Authority of drainage works within its jurisdiction

        1. 6.(1) Subject to sub-paragraph (2), the Harbour Authority shall, from...

      7. Impairment of efficiency of drainage work for flood defence

        1. 7.If, by reason of the construction of a specified work...

      8. Damage to flood defences managed by the Agency

        1. 8.(1) If, during the construction of a specified work or...

      9. Protection of the fishery

        1. 9.(1) The Harbour Authority shall take all such measures as...

      10. Indemnity as to costs and expenses

        1. 10.(1) The Harbour Authority shall indemnify the Agency in respect...

        2. 11.The fact that any work or thing has been executed...

      11. Approvals deemed and not deemed

        1. 12.(1) For the purposes of section 109 of the Water...

      12. Arbitration in respect of differences arising under this Schedule between the parties

        1. 13.(1) Provided the Harbour Authority and the Agency agree, any...

    11. SCHEDULE 11

      FOR THE PROTECTION OF NATIONAL GRID GAS PLC AND OTHER STATUTORY UNDERTAKERS

      1. Apparatus of statutory undertakers, etc., on land acquired

        1. 1.(1) Subject to the following provisions of this paragraph, sections...

      2. Protection for National Grid Gas plc

        1. 2.(1) For the protection of the undertaker referred to in...

        2. 3.(1) If, in the exercise of any of its powers...

        3. 4.(1) Where, in accordance with the provisions of this Schedule,...

        4. 5.(1) Not less than 56 days before commencing the construction...

        5. 6.(1) Subject to the following provisions of this paragraph, the...

        6. 7.(1) Subject to sub-paragraphs (2) and (3), if by reason...

    12. SCHEDULE 12

      LAND WHICH MAY BE ACQUIRED COMPULSORILY

  11. Explanatory Note

Back to top

Options/Help

Print Options

Close

Legislation is available in different versions:

Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.

Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.

Close

Opening Options

Different options to open legislation in order to view more content on screen at once

Close

More Resources

Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as enacted version that was used for the print copy
  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • correction slips
  • links to related legislation and further information resources
Close

Timeline of Changes

This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.

Close

More Resources

Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as made version that was used for the print copy
  • correction slips

Click 'View More' or select 'More Resources' tab for additional information including:

  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • links to related legislation and further information resources