1.Where for technical reasons it is temporarily not feasible to apply the monitoring methodology plan as approved by the [F1regulator], the operator shall apply a method based on alternative data sources listed in the monitoring methodology plan for the purpose of performing corroborative checks in accordance with Article 10(5), or, if such an alternative is not contained in the monitoring methodology plan, an alternative method which provides the highest achievable accuracy according to the generic data sources and their hierarchy laid down in section 4 of Annex VII, or a conservative estimation approach, until the conditions for application of the approved monitoring methodology plan have been restored.
The operator shall take all necessary measures to achieve a prompt application of the approved monitoring methodology plan.
2.Where data relevant for the baseline data report are missing, for which the monitoring methodology plan does not list alternative monitoring methods or alternative data sources for corroborating data or for closing the data gap, the operator shall use an appropriate estimation method for determining conservative surrogate data for the respective time period and missing parameter, in particular, based on best industry practice, recent scientific and technical knowledge, and shall provide due justification for the data gap and the use of those methods in an annex to the baseline data report.
3.Where a temporary deviation from the approved monitoring methodology plan occurs in accordance with paragraph 1, or where data relevant for the report referred to in Article 4(2)(a) or [F2Article 5(5)(a)] are found to be missing, the operator shall without undue delay develop a written procedure for avoiding this type of data gap in the future and modify the monitoring methodology plan in accordance with Article 9(3). Furthermore, the operator shall assess whether and how the control activities referred to in Article 11(3) need to be updated and shall modify those control activities and the relevant written procedures, as appropriate.
Textual Amendments
F1Words in Regulation substituted (31.12.2020) by The Greenhouse Gas Emissions Trading Scheme (Amendment) Order 2020 (S.I. 2020/1557), art. 2(2), Sch. 1 para. 2
F2Words in Art. 12(3) substituted (31.12.2020) by The Greenhouse Gas Emissions Trading Scheme (Amendment) Order 2020 (S.I. 2020/1557), art. 2(2), Sch. 1 para. 15(2)