Search Legislation

Commission Regulation (EU) 2017/460Show full title

Commission Regulation (EU) 2017/460 of 16 March 2017 establishing a network code on harmonised transmission tariff structures for gas (Text with EEA relevance)

 Help about what version

What Version

 Help about advanced features

Advanced Features

 Help about opening options

Opening Options

 Help about UK-EU Regulation

Legislation originating from the EU

When the UK left the EU, legislation.gov.uk published EU legislation that had been published by the EU up to IP completion day (31 December 2020 11.00 p.m.). On legislation.gov.uk, these items of legislation are kept up-to-date with any amendments made by the UK since then.

Close

This item of legislation originated from the EU

Legislation.gov.uk publishes the UK version. EUR-Lex publishes the EU version. The EU Exit Web Archive holds a snapshot of EUR-Lex’s version from IP completion day (31 December 2020 11.00 p.m.).

Changes to legislation:

There are currently no known outstanding effects by UK legislation for Commission Regulation (EU) 2017/460, CHAPTER VII. Help about Changes to Legislation

Close

Changes to Legislation

Revised legislation carried on this site may not be fully up to date. At the current time any known changes or effects made by subsequent legislation have been applied to the text of the legislation you are viewing by the editorial team. Please see ‘Frequently Asked Questions’ for details regarding the timescales for which new effects are identified and recorded on this site.

CHAPTER VIIU.K. CONSULTATION REQUIREMENTS

Article 26U.K.Periodic consultation

1.One or more consultations shall be carried out by the national regulatory authority or the transmission system operator(s), as decided by the national regulatory authority. F1... The final consultation prior to the decision referred to in Article 27(4) shall comply with the requirements set out in this Article and Article 27, and shall include the following information:

(a)the description of the proposed reference price methodology as well as the following items:

(i)

the indicative information set out in Article 30(1)(a), including:

(1)

the justification of the parameters used that are related to the technical characteristics of the system;

(2)

the corresponding information on the respective values of such parameters and the assumptions applied.

(ii)

the value of the proposed adjustments for capacity-based transmission tariffs pursuant to Article 9;

(iii)

the indicative reference prices subject to consultation;

(iv)

the results, the components and the details of these components for the cost allocation assessments set out in Article 5;

(v)

the assessment of the proposed reference price methodology in accordance with Article 7;

(vi)

where the proposed reference price methodology is other than the capacity weighted distance reference price methodology detailed in Article 8, its comparison against the latter accompanied by the information set out in point (iii);

(b)the indicative information set out in Article 30(1)(b)(i), (iv), (v);

(c)the following information on transmission and non-transmission tariffs:

(i)

where commodity-based transmission tariffs referred to in Article 4(3) are proposed:

(1)

the manner in which they are set;

(2)

the share of the allowed or target revenue forecasted to be recovered from such tariffs;

(3)

the indicative commodity-based transmission tariffs;

(ii)

where non-transmission services provided to network users are proposed:

(1)

the non-transmission service tariff methodology therefor;

(2)

the share of the allowed or target revenue forecasted to be recovered from such tariffs;

(3)

the manner in which the associated non-transmission services revenue is reconciled as referred to in Article 17(3);

(4)

the indicative non-transmission tariffs for non-transmission services provided to network users;

(d)the indicative information set out in Article 30(2);

(e)where the fixed payable price approach referred to in Article 24(b) is considered to be offered under a price cap regime for existing capacity:

(i)

the proposed index;

(ii)

the proposed calculation and how the revenue derived from the risk premium is used;

(iii)

at which interconnection point(s) and for which tariff period(s) such approach is proposed;

(iv)

the process of offering capacity at an interconnection point where both fixed and floating payable price approaches referred to in Article 24 are proposed.

2.The final consultation prior to the decision referred to in Article 27(4) shall be open for at least two months. Consultation documents for any of the consultations referred to in paragraph 1 may require that replies submitted in response to the consultation shall include a non-confidential version suitable for publication.

3.Within one month following the end of the consultation, the transmission system operator(s) or the national regulatory authority, depending on the entity that publishes the consultation document referred to in paragraph 1, shall publish the consultation responses received and their summary. F2...

4.The subsequent periodic consultations shall be conducted in accordance with Article 27(5).

F35.. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

Article 27U.K.Periodic national regulatory authority decision-making

F41.. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

F52.. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

F63.. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

4.Within five months following the end of the final consultation [F7pursuant to Article 26], the national regulatory authority F8... shall take and publish a motivated decision on all items set out in Article 26(1). F9...

5.The procedure consisting of the final consultation on the reference price methodology in accordance with Article 26, the decision by the national regulatory authority in accordance with paragraph 4, the calculation of tariffs on the basis of this decision, and the publication of the tariffs in accordance with Chapter VIII may be initiated as from the entry into force of this Regulation and shall be concluded no later than 31 May 2019. The requirements set out in Chapters II, III and IV shall be taken into account in this procedure. The tariffs applicable for the prevailing tariff period at 31 May 2019 will be applicable until the end thereof. This procedure shall be repeated at least every five years starting from 31 May 2019.

Article 28U.K.Consultation on discounts, multipliers and seasonal factors

1.At the same time as the final consultation carried out in accordance with Article 26(1), the national regulatory authority shall conduct a consultation with the [F10non-UK] regulatory authorities of all directly connected [F11countries or territories, the other national regulatory authority] and the relevant stakeholders on the following:

(a)the level of multipliers;

(b)if applicable, the level of seasonal factors and the calculations set out in Article 15;

(c)the levels of discounts set out in Articles 9(2) and 16.

After the end of the consultation a motivated decision shall be taken [F12by the national regulatory authority] on the aspects referred to in points (a) to (c) of this paragraph. [F13The] national regulatory authority shall consider the positions of [F14non-UK] regulatory authorities of directly connected [F15countries or territories and the other national regulatory authority].

2.The subsequent consultations shall be conducted every tariff period as from the date of the decision referred to in paragraph 1. After each consultation and as set out in Article 32(a), the national regulatory authority shall take and publish a motivated decision on the aspects referred to in paragraph 1(a), (b) and (c).

3.When adopting the decision referred to in paragraphs 1 and 2, the national regulatory authority shall take into account the consultation responses received and the following aspects:

(a)for multipliers:

(i)

the balance between facilitating short-term gas trade and providing long-term signals for efficient investment in the transmission system;

(ii)

the impact on the transmission services revenue and its recovery;

(iii)

the need to avoid cross-subsidisation between network users and to enhance cost-reflectivity of reserve prices;

(iv)

situations of physical and contractual congestion;

(v)

the impact on cross-border flows;

(b)for seasonal factors:

(i)

the impact on facilitating the economic and efficient utilisation of the infrastructure;

(ii)

the need to improve the cost-reflectivity of reserve prices.

Back to top

Options/Help

Print Options

Close

Legislation is available in different versions:

Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.

Original (As adopted by EU): The original version of the legislation as it stood when it was first adopted in the EU. No changes have been applied to the text.

Close

See additional information alongside the content

Geographical Extent: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.

Show Timeline of Changes: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.

Close

Opening Options

Different options to open legislation in order to view more content on screen at once

Close

More Resources

Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as adopted version that was used for the EU Official Journal
  • lists of changes made by and/or affecting this legislation item
  • all formats of all associated documents
  • correction slips
  • links to related legislation and further information resources
Close

Timeline of Changes

This timeline shows the different versions taken from EUR-Lex before exit day and during the implementation period as well as any subsequent versions created after the implementation period as a result of changes made by UK legislation.

The dates for the EU versions are taken from the document dates on EUR-Lex and may not always coincide with when the changes came into force for the document.

For any versions created after the implementation period as a result of changes made by UK legislation the date will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. For further information see our guide to revised legislation on Understanding Legislation.

Close

More Resources

Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as adopted version that was used for the print copy
  • correction slips

Click 'View More' or select 'More Resources' tab for additional information including:

  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • links to related legislation and further information resources