CHAPTER IIU.K. PRINCIPLES OF COOPERATION

Article 4U.K.Coordination of maintenance

Where maintenance of a pipeline or part of a transmission network has an impact on the amount of transmission capacity which can be offered at interconnection points, the transmission system operator(s) shall fully cooperate with their [F1adjacent TSOs] regarding their respective maintenance plans in order to minimise the impact on potential gas flows and capacity at an interconnection point. [F2Where an adjacent TSO is a non-UK TSO, the transmission system operator must endeavour to fully cooperate with the non-UK TSO regarding their respective maintenance plans.]