Where maintenance of a pipeline or part of a transmission network has an impact on the amount of transmission capacity which can be offered at interconnection points, the transmission system operator(s) shall fully cooperate with their [F1adjacent TSOs] regarding their respective maintenance plans in order to minimise the impact on potential gas flows and capacity at an interconnection point. [F2Where an adjacent TSO is a non-UK TSO, the transmission system operator must endeavour to fully cooperate with the non-UK TSO regarding their respective maintenance plans.]
Textual Amendments
F1Words in Art. 4 substituted (31.12.2020) by The Gas (Security of Supply and Network Codes) (Amendment) (EU Exit) Regulations 2019 (S.I. 2019/531), reg. 1(2), Sch. 4 para. 4(2); 2020 c. 1, Sch. 5 para. 1(1)
F2Words in Art. 4 inserted (31.12.2020) by The Gas (Security of Supply and Network Codes) (Amendment) (EU Exit) Regulations 2019 (S.I. 2019/531), reg. 1(2), Sch. 4 para. 4(3); 2020 c. 1, Sch. 5 para. 1(1)