Commission Regulation (EU) 2017/459 of 16 March 2017 establishing a network code on capacity allocation mechanisms in gas transmission systems and repealing Regulation (EU) No 984/2013 (Text with EEA relevance)
When the UK left the EU, legislation.gov.uk published EU legislation that had been published by the EU up to IP completion day (31 December 2020 11.00 p.m.). On legislation.gov.uk, these items of legislation are kept up-to-date with any amendments made by the UK since then.
Legislation.gov.uk publishes the UK version. EUR-Lex publishes the EU version. The EU Exit Web Archive holds a snapshot of EUR-Lex’s version from IP completion day (31 December 2020 11.00 p.m.).
There are currently no known outstanding effects by UK legislation for Commission Regulation (EU) 2017/459, Article 30.![]()
Revised legislation carried on this site may not be fully up to date. At the current time any known changes or effects made by subsequent legislation have been applied to the text of the legislation you are viewing by the editorial team. Please see ‘Frequently Asked Questions’ for details regarding the timescales for which new effects are identified and recorded on this site.
1.An alternative allocation mechanism covers a maximum of 15 years after the start of operational use. If the economic test could not be passed based on the 15 years' bookings, national regulatory authorities may exceptionally extend the time horizon by up to 5 additional years.
2.An alternative capacity allocation mechanism can be used, subject to national regulatory authorities' approval, where it is reasonable to conclude from the market demand assessment pursuant to Article 26 or the consultation defined in Article 27(3) that the ascending clock auction is not suitable and that the incremental capacity project fulfils both of the following conditions:
(a)it involves more than two entry-exit systems and bids are requested along several interconnection points during the allocation procedure;
(b)bids with a duration of more than 1 year are requested.
3.In an alternative allocation mechanism network users may submit binding conditional bids for contracting capacity subject to one or more of the following conditions specified by the transmission system operators in the approved project proposal pursuant to Article 28(1):
(a)commitments linking or excluding commitments at other interconnection points;
(b)commitments across a number of different yearly standard capacity products at an interconnection point;
(c)commitments conditional on the allocation of a specific or minimum amount of capacity.
4.The alternative allocation mechanism is subject to approvals by the concerned national regulatory authorities according to Article 28(2). The mechanism shall be transparent and non-discriminatory but may allow for the prioritisation of booking duration or bids for higher amounts of capacity for a yearly standard capacity product.
5.If either booking duration or bids for higher amounts of capacity are prioritised, national regulatory authorities shall decide on setting aside an amount of at least 10 % and up to 20 % of the technical capacity at each interconnection point when applying Article 8(8). Capacity set aside in this manner shall be offered in accordance with Article 8(7).
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As adopted by EU): The original version of the legislation as it stood when it was first adopted in the EU. No changes have been applied to the text.
Geographical Extent: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.
Show Timeline of Changes: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
This timeline shows the different versions taken from EUR-Lex before exit day and during the implementation period as well as any subsequent versions created after the implementation period as a result of changes made by UK legislation.
The dates for the EU versions are taken from the document dates on EUR-Lex and may not always coincide with when the changes came into force for the document.
For any versions created after the implementation period as a result of changes made by UK legislation the date will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. For further information see our guide to revised legislation on Understanding Legislation.
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: