1.Immediately after the start of the annual yearly capacity auction at least in each odd-numbered year, transmission system operators [F1must cooperate with adjacent TSOs] in the processes of assessing market demand for incremental capacity and of conducting technical studies for incremental capacity projects for their joint interconnection points. [F2Where an adjacent TSO is a non-UK TSO, transmission system operators must endeavour to cooperate in these processes.]
2.No later than 8 weeks after the start of the annual yearly capacity auction at least in each odd-numbered year, the concerned transmission system operators on each side of an entry-exit system border shall produce common market demand assessment reports, each covering all interconnection points of at least one entry-exit system border. The market assessment report shall evaluate the prospective demand for incremental capacity of all network users pursuant to paragraph 8 and shall state whether an incremental capacity project is initiated. [F3Where the market demand report concerns any non-UK TSOs, the concerned transmission system operators must endeavour to produce that report in common with the non-UK TSOs.]
3.The market demand assessment report shall be published F4... on the websites of the concerned transmission system operators no later than 16 weeks after the start of the annual yearly capacity auction at least in each odd-numbered year.
F54.. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
5.If demand for incremental capacity is expressed by network users no later than 8 weeks after the start of the annual yearly auction in even-numbered years, the concerned transmission system operators may agree to conduct a market demand assessment also in an even-numbered year, provided that:
(a)the process set out in Articles 26-30 can be concluded before the start of the next demand assessment cycle referred to in paragraph 1; and
(b)the auction calendar is respected.
6.Transmission system operators shall consider non-binding demand indications submitted no later than 8 weeks after the start of the annual yearly auction in the ongoing market demand assessment.
7.Transmission system operators may consider non-binding demand indications submitted after the deadline set out in paragraph 6 in the ongoing market demand assessment, or introduce them into the next market demand assessment.
8.The non-binding demand indications referred to in paragraphs 6 and 7 shall contain at least the following information:
(a)the two or more adjacent entry-exit systems between which demand for incremental capacity — on one or both sides of an interconnection point — is expressed and the requested direction;
(b)the gas year(s) for which a demand for incremental capacity is expressed;
(c)the amount of capacity demanded between the respective entry-exit systems;
(d)information on non-binding demand indications which were or will be submitted to other transmission system operators, in case such indications are linked to each other, such as demand for capacities at several related interconnection points;
9.Network users shall indicate whether their demand is subject to any conditions in relation to points (a) to (d) of paragraph 8.
10.Transmission system operators shall respond to non-binding demand indications within 16 weeks after the start of the annual yearly auctions, or within 8 weeks of receipt of demand indications in accordance with paragraph 7. The response shall provide at least the following:
(a)whether the demand indicated can be considered by the transmission system operator in the ongoing process; or
(b)whether, in the case of demand indications in accordance with paragraph 7, they are sufficient to consider the initiation of an incremental capacity process according to paragraph 5; or
(c)in which market demand assessment report, according to paragraph 3, the indicated demand will be assessed, provided that the demand indicated cannot be considered under points (a) or (b), which is to be justified.
11.A transmission system operator may charge fees for activities resulting from the submission of non-binding demand indications. Such fees shall reflect the administrative costs for submitting demand indications, and shall be subject to approval by the relevant national regulatory authority and published on the transmission system operator's website. Such fees shall be reimbursed to the respective network user if the economic test for at least one offer level that includes incremental capacity at the respective interconnection point is positive.
12.The market demand assessment report shall take into account all of the following criteria:
[F6(a)the obligation on any concerned non-UK TSOs to take into account whether the Union-wide 10-year network development plan identifies a physical capacity gap whereby a specific region is undersupplied in a reasonable peak scenario and where offering incremental capacity at the interconnection point in question could close the gap; or any UK network development plan or national network development plan relevant to a concerned non-UK TSO identifies a concrete and sustained physical transport requirement;]
(b)whether no yearly standard capacity product linking two adjacent entry-exit systems is available in the annual yearly capacity auction for the year in which incremental capacity could be offered for the first time and in the 3 subsequent years, because all the capacity has been contracted;
(c)whether network users submitted non-binding demand indications requesting incremental capacity for a sustained number of years and all other economically efficient means for maximising the availability of existing capacity are exhausted.
13.The market demand assessment report shall include at least the following:
(a)a conclusion on whether to initiate an incremental capacity project;
(b)the aggregated non-binding demand indications received no later than 8 weeks after the start of the annual yearly capacity auction in the year of the publication of the respective demand assessment report;
(c)the aggregated non-binding demand indications submitted after the deadline referred to in paragraph 6 during the previous incremental capacity process in case these demand indications were not considered for the previous demand assessment;
(d)the aggregated non-binding demand indications submitted in accordance with paragraph 7 where the transmission system operators has decide to consider them in the ongoing market demand assessment;
(e)an assessment of the expected amount, direction and duration of demand for incremental capacity at the interconnection points with each adjacent entry-exit system or interconnectors;
(f)a conclusion on whether technical studies for incremental capacity projects will be conducted, specifying for which interconnection points and for which expected demand level;
(g)provisional timelines for the incremental capacity project, technical studies and the consultation referred to in Article 27(3);
(h)a conclusion on what fees, if any, will be introduced, according to paragraph 10;
(i)the types and, where available the aggregated size of conditional demand indications according to point paragraph 9;
(j)how transmission system operators intend to apply Article 11(3) with regards to limitation of the number of years being offered in the annual yearly capacity auctions during the incremental process.
14.Transmission system operators and the relevant national regulatory authorities shall publish respective points of contact for incremental capacity projects initiated at the publication of the market demand assessment report and update this information on a regular basis throughout the project.
Textual Amendments
F1Words in Art. 26(1) substituted (31.12.2020) by The Gas (Security of Supply and Network Codes) (Amendment) (EU Exit) Regulations 2019 (S.I. 2019/531), reg. 1(2), Sch. 4 para. 18(2)(a); 2020 c. 1, Sch. 5 para. 1(1)
F2Words in Art. 26(1) substituted (31.12.2020) by The Gas (Security of Supply and Network Codes) (Amendment) (EU Exit) Regulations 2019 (S.I. 2019/531), reg. 1(2), Sch. 4 para. 18(2)(b); 2020 c. 1, Sch. 5 para. 1(1)
F3Words in Art. 26(2) inserted (31.12.2020) by The Gas (Security of Supply and Network Codes) (Amendment) (EU Exit) Regulations 2019 (S.I. 2019/531), reg. 1(2), Sch. 4 para. 18(3); 2020 c. 1, Sch. 5 para. 1(1)
F4Words in Art. 26(3) omitted (31.12.2020) by virtue of The Gas (Security of Supply and Network Codes) (Amendment) (EU Exit) Regulations 2019 (S.I. 2019/531), reg. 1(2), Sch. 4 para. 18(4); 2020 c. 1, Sch. 5 para. 1(1)
F5Art. 26(4) omitted (31.12.2020) by virtue of The Gas (Security of Supply and Network Codes) (Amendment) (EU Exit) Regulations 2019 (S.I. 2019/531), reg. 1(2), Sch. 4 para. 18(5); 2020 c. 1, Sch. 5 para. 1(1)