Search Legislation

Commission Regulation (EU) 2017/459Show full title

Commission Regulation (EU) 2017/459 of 16 March 2017 establishing a network code on capacity allocation mechanisms in gas transmission systems and repealing Regulation (EU) No 984/2013 (Text with EEA relevance)

 Help about what version

What Version

 Help about advanced features

Advanced Features

 Help about opening options

Opening Options

 Help about UK-EU Regulation

Legislation originating from the EU

When the UK left the EU, legislation.gov.uk published EU legislation that had been published by the EU up to IP completion day (31 December 2020 11.00 p.m.). On legislation.gov.uk, these items of legislation are kept up-to-date with any amendments made by the UK since then.

Close

This item of legislation originated from the EU

Legislation.gov.uk publishes the UK version. EUR-Lex publishes the EU version. The EU Exit Web Archive holds a snapshot of EUR-Lex’s version from IP completion day (31 December 2020 11.00 p.m.).

Changes to legislation:

There are currently no known outstanding effects by UK legislation for Commission Regulation (EU) 2017/459, Article 17. Help about Changes to Legislation

Close

Changes to Legislation

Revised legislation carried on this site may not be fully up to date. At the current time any known changes or effects made by subsequent legislation have been applied to the text of the legislation you are viewing by the editorial team. Please see ‘Frequently Asked Questions’ for details regarding the timescales for which new effects are identified and recorded on this site.

Article 17U.K.Ascending clock auction algorithm

1.Ascending clock auctions shall enable network users to place volume bids against escalating prices announced in consecutive bidding rounds, starting at the reserve price P0.

2.The first bidding round, with an associated price equal to the reserve price P0, shall have a duration of 3 hours. Subsequent bidding rounds shall have a duration of 1 hour. There shall be a period of 1 hour between bidding rounds.

3.A bid shall specify:

(a)the identity of the network user applying;

(b)the concerned interconnection point and direction of the flow;

(c)the standard capacity product for which the capacity is applied for;

(d)per price step, the amount of capacity for the respective standard capacity product applied for;

(e)where incremental capacity is offered, the concerned offer level.

4.A bid shall be considered valid if it is submitted by a network user and complies with all provisions of this Article.

5.In order for network users to participate in an auction, it shall be mandatory for network users to place a volume bid in the first bidding round.

6.Transmission system operators shall provide network users with the option to enter bids automatically against any price step.

7.Once the relevant bidding round closes, no modification, withdrawal or variation to valid bids shall be accepted. All valid bids shall become binding commitments of a network user to book capacity to the amount requested per announced price, provided the clearing price of the auction is that which is announced in the relevant bidding round.

8.The volume bid in any bidding round per network user shall be equal or smaller to the capacity offered in a specific auction. The volume bid per network user at a specific price shall be equal to or less than the volume bid placed by this network user in the previous round, except where paragraph 16 applies.

9.Bids may be freely entered, modified and withdrawn during a bidding round, providing all bids comply with paragraph 8. Valid bids shall remain valid until modified or withdrawn.

10.A large price step and a small price step shall be defined per interconnection point and per standard capacity product and shall be published in advance of the relevant auction. The small price step shall be set such that an increase by an integer number of small price steps is equal to an increase by a large price step.

11.The determination of the large price step shall seek to minimise, as far as reasonably possible, the length of the auction process. The determination of the small price step shall seek to minimise, as far as reasonably possible, the level of unsold capacity where the auction closes at a price higher than the reserve price.

12.If the aggregate demand across all network users is less than or equal to the capacity offered at the end of the first bidding round, the auction shall close.

13.If the aggregate demand across all network users is greater than the capacity offered at the end of the first bidding round or a subsequent bidding round, a further bidding round shall be opened with a price equal to the price in the previous bidding round, plus the large price step.

14.If the aggregate demand across all network users is equal to the capacity offered at the end of the second bidding round or a subsequent bidding round, the auction shall close.

15.If a first-time undersell occurs, a price reduction shall take place and a further bidding round shall be opened. The further bidding round will have a price equal to the price applicable in the bidding round preceding the first-time undersell, plus the small price step. Further bidding rounds with increments of the small price step shall then be opened until the aggregate demand across all network users is less than or equal to the capacity offered, at which point the auction shall close.

16.The volume bid per network user in all bidding rounds where small price steps are applied shall be equal to or less than the volume bid placed by this network user in the bidding round which preceded the first-time undersell. The volume bid per network user for a specific small price step shall be equal to or smaller than the volume bid placed by this network user in the previous bidding round of small price steps. The volume bid per network user in all bidding rounds where small price steps are applied shall be equal to or greater than the volume bid placed by this network user during the bidding round in which the first-time undersell occurred.

17.If the aggregate demand across all network users is greater than the capacity offered in the bidding round with a price equal to that which led to the first-time undersell, minus one small price step, the auction shall close. The clearing price shall be the price that led to the first-time undersell and the successful bids shall be those submitted during the original bidding round in which the first-time undersell occurred.

18.After each bidding round, the demand of all network users in a specific auction shall be published as soon as reasonably possible in an aggregated form.

19.The price announced for the last bidding round in which the auction closes shall be considered as the clearing price of the specific auction, except cases where paragraph 17 applies.

20.All network users who have placed valid volume bids at the clearing price shall be allocated the capacity according to their volume bids at the clearing price. Where incremental capacity is offered, the allocation of incremental capacity shall be subject to the outcome of the economic test according to Article 22. Successful network users shall pay the clearing price of the specific auction, which may be a fixed or a floating payable price approach set out in Article 24 of Regulation (EU) 2017/460, and any other possible charges applicable at the time when the capacity allocated to them can be used.

21.Following every closed auction, the final auction result including the aggregation of allocated capacities and the clearing price shall be published. Successful network users shall be informed about the amount of capacities they are allocated, individual information shall be communicated only to concerned parties. Where incremental capacity is allocated, this paragraph shall only apply to the auction results of the offer level offering the largest amount of capacity that resulted in a positive economic test according to Article 22(3).

22.If an ascending clock auction has not ended by the scheduled starting point (according to the auction calendar) of the next auction for capacity covering the same period, the first auction shall close and no capacity shall be allocated. The capacity shall be offered in the next relevant auction.

Back to top

Options/Help

Print Options

Close

Legislation is available in different versions:

Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.

Original (As adopted by EU): The original version of the legislation as it stood when it was first adopted in the EU. No changes have been applied to the text.

Close

See additional information alongside the content

Geographical Extent: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.

Show Timeline of Changes: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.

Close

Opening Options

Different options to open legislation in order to view more content on screen at once

Close

More Resources

Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as adopted version that was used for the EU Official Journal
  • lists of changes made by and/or affecting this legislation item
  • all formats of all associated documents
  • correction slips
  • links to related legislation and further information resources
Close

Timeline of Changes

This timeline shows the different versions taken from EUR-Lex before exit day and during the implementation period as well as any subsequent versions created after the implementation period as a result of changes made by UK legislation.

The dates for the EU versions are taken from the document dates on EUR-Lex and may not always coincide with when the changes came into force for the document.

For any versions created after the implementation period as a result of changes made by UK legislation the date will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. For further information see our guide to revised legislation on Understanding Legislation.

Close

More Resources

Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as adopted version that was used for the print copy
  • correction slips

Click 'View More' or select 'More Resources' tab for additional information including:

  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • links to related legislation and further information resources