Commission Regulation (EU) 2017/2196 of 24 November 2017 establishing a network code on electricity emergency and restoration (Text with EEA relevance)

 Help about what version

What Version

 Help about advanced features

Advanced Features

 Help about UK-EU Regulation

Legislation originating from the EU

When the UK left the EU, legislation.gov.uk published EU legislation that had been published by the EU up to IP completion day (31 December 2020 11.00 p.m.). On legislation.gov.uk, these items of legislation are kept up-to-date with any amendments made by the UK since then.

Close

This item of legislation originated from the EU

Legislation.gov.uk publishes the UK version. EUR-Lex publishes the EU version. The EU Exit Web Archive holds a snapshot of EUR-Lex’s version from IP completion day (31 December 2020 11.00 p.m.).

Changes to legislation:

There are currently no known outstanding effects by UK legislation for Commission Regulation (EU) 2017/2196, CHAPTER I. Help about Changes to Legislation

Close

Changes to Legislation

Revised legislation carried on this site may not be fully up to date. At the current time any known changes or effects made by subsequent legislation have been applied to the text of the legislation you are viewing by the editorial team. Please see ‘Frequently Asked Questions’ for details regarding the timescales for which new effects are identified and recorded on this site.

CHAPTER IU.K. GENERAL PROVISIONS

Article 1U.K.Subject matter

For the purposes of safeguarding operational security, preventing the propagation or deterioration of an incident to avoid a widespread disturbance and the blackout state as well to allow for the efficient and rapid restoration of the electricity system from the emergency or blackout states, this Regulation establishes a network code which lays down the requirements on:

(a)

the management by TSOs of the emergency, blackout and restoration states;

(b)

the coordination of system operation F1... in the emergency, blackout and restoration states;

(c)

the simulations and tests to guarantee a reliable, efficient and fast restoration of the interconnected transmission systems to the normal state from the emergency or blackout states;

(d)

the tools and facilities needed to guarantee a reliable, efficient and fast restoration of the interconnected transmission systems to the normal state from the emergency or blackout states.

Article 2U.K.Scope

1.This Regulation shall apply to TSOs, DSOs, SGUs, defence service providers, restoration service providers, balance responsible parties, [F2and] balancing service providers F3...

2.In particular, this Regulation shall apply to the following SGUs:

(a)existing and new power generating modules classified as type C and D in accordance with the criteria set out in Article 5 of Commission Regulation (EU) 2016/631(1);

(b)existing and new power generating modules classified as type B in accordance with the criteria set out in Article 5 of Regulation (EU) 2016/631, where they are identified as SGUs in accordance with Article 11(4) and Article 23(4);

(c)existing and new transmission-connected demand facilities;

(d)existing and new transmission connected closed distribution systems;

(e)providers of redispatching of power generating modules or demand facilities by means of aggregation and providers of active power reserve in accordance with Title 8 of Regulation (EU) 2017/1485; and

(f)existing and new high voltage direct current (‘HVDC’) systems and direct current-connected power park modules in accordance with the criteria set out in Article 4(1) of Commission Regulation (EU) 2016/1447(2).

3.This Regulation shall apply to existing and new type A power generating modules, in accordance with the criteria set out in Article 5 of Regulation (EU) 2016/631, to existing and new type B power generating modules other than those referred to in paragraph 2(b), as well as to existing and new demand facilities, closed distribution systems and third parties providing demand response where they qualify as defence service providers or restoration service providers pursuant to Article 4(4).

4.Type A and type B power generating modules referred to in paragraph 3, demand facilities and closed distribution systems providing demand response may fulfil the requirements of this Regulation either directly or indirectly through a third party, under the terms and conditions set in accordance with Article 4(4).

5.This Regulation shall apply to energy storage units of a SGU, a defence service provider or a restoration service provider, which can be used to balance the system, provided that they are identified as such in the system defence plans, restoration plans or in the relevant service contract.

6.[F4Except for Article 10,] this Regulation shall apply to all transmission systems, distribution systems and interconnections [F5within the jurisdiction of Great Britain.]

7.[F6Except for Article 10, this Regulation shall apply to all transmission system operators within Great Britain.] Where a transmission system operator does not have a function relevant to one or more obligations under this Regulation, [F7the regulatory authority] may provide that the responsibility for complying with those obligations is assigned to one or more different, specific transmission system operators.

F88.. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

Textual Amendments

Article 3U.K.Definitions

[F9Except where stated in this Article,] for the purposes of this Regulation, the definitions provided for in F10... Article 2 of [F11Regulation (EU) 2019/943 of the European Parliament and of the Council of 5 June 2019 on the internal market for electricity (recast)], Article 2 of Commission Regulation (EU) No 543/2013(3), F12... Article 2 of Regulation (EU) 2016/631, Article 2 of Commission Regulation (EU) 2016/1388(4), Article 2 of Regulation (EU) 2016/1447 F13... and Article 2 of Regulation (EU) 2017/1485 shall apply.

In addition, the following definitions shall apply:

(1)

‘defence service provider’ means a legal entity with a legal or contractual obligation to provide a service contributing to one or several measures of the system defence plan;

(2)

‘restoration service provider’ means a legal entity with a legal or contractual obligation to provide a service contributing to one or several measures of the restoration plan;

(3)

‘high priority significant grid user’ means the significant grid user for which special conditions apply for disconnection and re-energisation;

(4)

‘netted demand’ means the netted value of active power seen from a given point of the system, computed as (load — generation), generally expressed in kilowatts (kW) or megawatts (MW), at a given instant or averaged over any designated interval of time;

(5)

‘restoration plan’ means all technical and organisational measures necessary for the restoration of the system back to normal state;

(6)

‘re-energisation’ means reconnecting generation and load to energise the parts of the system that have been disconnected;

(7)

‘top-down re-energisation strategy’ means a strategy that requires the assistance of other TSOs to re-energise parts of the system of a TSO;

(8)

‘bottom-up re-energisation strategy’ means a strategy where part of the system of a TSO can be re-energised without the assistance from other TSOs;

(9)

‘resynchronisation’ means synchronising and connecting again two synchronised regions at the resynchronisation point;

(10)

‘frequency leader’ means the TSO appointed and responsible for managing the system frequency within a synchronised region or a synchronous area in order to restore system frequency back to the nominal frequency;

(11)

‘synchronised region’ means the fraction of a synchronous area covered by interconnected TSOs with a common system frequency and which is not synchronised with the rest of the synchronous area;

(12)

‘resynchronisation leader’ means the TSO appointed and responsible for the resynchronisation of two synchronised regions;

(13)

‘resynchronisation point’ means the device used to connect two synchronised regions, usually a circuit breaker.

(15)

[F14“SGU” or “significant grid user” means an electricity grid user of a kind specified in Article 2(1) of Commission Regulation (EU) 2017/1485.]

Textual Amendments

Article 4U.K.Regulatory aspects

1.When applying this Regulation, [F15the Secretary of State], [F16the regulatory authority] F17... and system operators shall:

(a)apply the principles of proportionality and non-discrimination;

(b)ensure transparency;

(c)apply the principle of optimisation between the highest overall efficiency and lowest total costs for all parties involved;

(d)ensure that TSOs make use of market-based mechanisms as far as is possible to ensure network security and stability;

(e)respect technical, legal, personal safety and security constraints;

(f)respect the responsibility assigned to the relevant TSO in order to ensure system security, including as required by national legislation;

(g)consult with relevant DSOs and take account of potential impacts on their system; and

(h)take into consideration agreed F18... standards and technical specifications.

2.Each TSO shall submit the following proposals to [F19the regulatory authority] for approval:

(a)the terms and conditions to act as defence service providers on a contractual basis in accordance with paragraph 4;

(b)the terms and conditions to act as restoration service providers on a contractual basis in accordance with paragraph 4;

(c)the list of SGUs responsible for implementing on their installations the measures that result from mandatory requirements set out in Regulations (EU) 2016/631, (EU) 2016/1388 and (EU) 2016/1447 and/or from national legislation and the list of the measures to be implemented by these SGUs, identified by the TSOs under Art. 11(4)(c) and 23(4)(c);

(d)the list of high priority significant grid users referred to in Articles 11(4)(d) and 23(4)(d) or the principles applied to define those and the terms and conditions for disconnecting and re-energising the high priority grid users F20...

(e)the rules for suspension and restoration of market activities in accordance with Article 36(1);

(f)specific rules for imbalance settlement and settlement of balancing energy in case of suspension of market activities, in accordance with Article 39(1);

(g)the test plan in accordance with Article 43(2).

F213.. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

4.The terms and conditions to act as defence service provider and as restoration service provider shall be established either in the national legal framework or on a contractual basis. If established on a contractual basis, each TSO shall develop by 18 December 2018 a proposal for the relevant terms and conditions, which shall define at least:

(a)the characteristics of the service to be provided;

(b)the possibility of and conditions for aggregation; and

(c)for restoration service providers, the target geographical distribution of power sources with black start and island operation capabilities.

5.By 18 December 2018, each TSO shall notify the regulatory authority F22... the system defence plan designed pursuant to Article 11 and the restoration plan designed pursuant to Article 23, or at least the following elements of those plans:

(a)the objectives of the system defence plan and the restoration plan, including the phenomena to be managed or the situations to be solved;

(b)the conditions triggering the activation of the measures of the system defence plan and the restoration plan;

(c)the rationale of each measure, explaining how it contributes to the objectives of the system defence plan and the restoration plan, and the party responsible for implementing those measures; and

(d)the deadlines set out pursuant to Articles 11 and 23 for the implementation of the measures.

6.Where a TSO is required or permitted under this Regulation to specify, establish or agree on requirements, terms and conditions or methodologies that are not subject to approval in accordance with paragraph 2, [F23the Secretary of State may require prior approval by the regulatory authority] of these requirements, terms and conditions or methodologies.

7.If a TSO deems an amendment to the documents, approved in accordance with paragraph 3, to be necessary, the requirements provided for in paragraphs 2 to 5 shall apply to the proposed amendment. TSOs proposing an amendment shall take into account the legitimate expectations, where necessary, of power generating facility owners, demand facility owners and other stakeholders based on the initially specified or agreed requirements or methodologies.

8.Any party can complain against a relevant system operator or TSO in relation to that relevant system operator's or TSO's obligations or decisions under this Regulation and may refer the complaint to the regulatory authority which, acting as dispute settlement authority, shall issue a decision within two months after receipt of the complaint. That period may be extended by a further two months where additional information is sought by the regulatory authority. That extended period may be further extended with the agreement of the complainant. The regulatory authority's decision shall be binding unless and until overruled on appeal.

Textual Amendments

Article 5U.K.Consultation and coordination

1.Where this Regulation provides that a TSO shall consult concerned parties for actions it defines before real-time or in real-time, the following procedure shall apply:

(a)the TSO shall liaise with at least the parties identified in the Articles of this Regulation requiring consultation;

(b)the TSO shall explain the rationale and objective of the consultation and of the decision that it has to take;

(c)the TSO shall collect from the parties referred to in point (a) any relevant information and their assessment;

(d)the TSO shall duly take into account the views, situations and constraints of the parties consulted;

(e)before taking a decision, the TSO shall provide an explanation to the parties consulted of the reasons for following or not their views.

2.Where this Regulation provides that a TSO shall coordinate the execution of a set of actions in real-time with several parties, the following procedure shall apply:

(a)the TSO shall liaise at least with the parties identified in the Articles of this Regulation requiring real time coordination;

(b)the TSO shall explain the rationale and objective of the coordination and of the actions to be taken;

(c)the TSO shall make an initial proposal on actions to be taken by each party;

(d)the TSO shall collect from the parties referred to in point (a) any relevant information and their assessment;

(e)the TSO shall make a final proposal on actions to be taken by each party, duly taking into account the views, situations and constraints of the concerned parties and setting a deadline for parties to express their opposition to the actions proposed by the TSO;

(f)where the concerned parties do not oppose executing the actions proposed by the TSO, each party, including the TSO, shall execute the actions in line with the proposal;

(g)where one or more of the parties refuse the action proposed by the TSO within the set deadline, the TSO shall refer the action proposed to the relevant authority for decision, together with a justification of the rationale and objectives of the action proposed by the TSO and of the assessment and position of the parties;

(h)if real-time referral to the relevant authority is not possible, the TSO shall initiate an equivalent action that has the least or no impact on the parties that refused to execute the action proposed.

3.A party may refuse to execute real time actions proposed by the TSO under the coordination procedure described in paragraph 2 if it justifies that the proposed action would lead to the violation of one or more technical, legal, personal safety or security constraint(s).

F24Article 6U.K.Regional coordination

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

Article 7U.K.Public consultation

1.The relevant TSOs shall consult stakeholders, including the [F25regulatory authority], on proposals subject to approval in accordance with points (a), (b), (e), (f) and (g) of Article 4(2). The consultation shall last for a period of not less than one month.

2.The relevant TSOs shall duly take into account the views of the stakeholders resulting from the consultations prior to the submission of the draft proposal. In all cases, a sound justification for including or not including the views of the stakeholders shall be provided and published in a timely manner before, or simultaneously with, the publication of the proposal.

Article 8U.K.Recovery of costs

1.The costs borne by system operators subject to network tariff regulation and stemming from the obligations laid down in this Regulation shall be assessed by the [F26regulatory authority]. Costs assessed as reasonable, efficient and proportionate shall be recovered through network tariffs or other appropriate mechanisms.

2.If requested by the [F27regulatory authority], system operators referred to in paragraph 1 shall, within three months of the request, provide the information necessary to facilitate assessment of the costs incurred.

Article 9U.K.Confidentiality obligations

1.Any confidential information received, exchanged or transmitted pursuant to this Regulation shall be subject to the conditions of professional secrecy laid down in paragraphs 2, 3 and 4.

2.The obligation of professional secrecy shall apply to any persons subject to the provisions of this Regulation.

3.Confidential information received by the persons referred to in paragraph 2 in the course of their duties may not be divulged to any other person or authority, without prejudice to cases covered by [F28the other provisions of this Regulation or any other enactment].

4.Without prejudice to cases covered by [F29any enactment], regulatory authorities, bodies or persons who receive confidential information pursuant to this Regulation may use it only for the purpose of carrying out their duties under this Regulation.

F30Article 10U.K.Agreement with TSOs not bound by this Regulation

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

(1)

Commission Regulation (EU) 2016/631 of 14 April 2016 establishing a network code on requirements for grid connection of generators (OJ L 112, 27.4.2016, p. 1).

(2)

Commission Regulation (EU) 2016/1447 of 26 August 2016 establishing a network code on requirements for grid connection of high voltage direct current systems and direct current-connected power park modules (OJ L 241, 8.9.2016, p. 1).

(3)

Commission Regulation (EU) No 543/2013 of 14 June 2013 on submission and publication of data in electricity markets and amending Annex I to Regulation (EC) No 714/2009 of the European Parliament and of the Council (OJ L 163, 15.6.2013, p. 1).

(4)

Commission Regulation (EU) 2016/1388 of 17 August 2016 establishing a network code on demand connection (OJ L 223, 18.8.2016, p. 10).

Back to top

Options/Help

Print Options

Close

Legislation is available in different versions:

Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.

Original (As adopted by EU): The original version of the legislation as it stood when it was first adopted in the EU. No changes have been applied to the text.

Close

See additional information alongside the content

Geographical Extent: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.

Show Timeline of Changes: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.

Close

Opening Options

Different options to open legislation in order to view more content on screen at once

Close

More Resources

Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as adopted version that was used for the EU Official Journal
  • lists of changes made by and/or affecting this legislation item
  • all formats of all associated documents
  • correction slips
  • links to related legislation and further information resources
Close

Timeline of Changes

This timeline shows the different versions taken from EUR-Lex before exit day and during the implementation period as well as any subsequent versions created after the implementation period as a result of changes made by UK legislation.

The dates for the EU versions are taken from the document dates on EUR-Lex and may not always coincide with when the changes came into force for the document.

For any versions created after the implementation period as a result of changes made by UK legislation the date will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. For further information see our guide to revised legislation on Understanding Legislation.

Close

More Resources

Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as adopted version that was used for the print copy
  • correction slips

Click 'View More' or select 'More Resources' tab for additional information including:

  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • links to related legislation and further information resources