- Latest available (Revised)
- Original (As adopted by EU)
Commission Regulation (EU) 2017/2196 of 24 November 2017 establishing a network code on electricity emergency and restoration (Text with EEA relevance)
When the UK left the EU, legislation.gov.uk published EU legislation that had been published by the EU up to IP completion day (31 December 2020 11.00 p.m.). On legislation.gov.uk, these items of legislation are kept up-to-date with any amendments made by the UK since then.
Legislation.gov.uk publishes the UK version. EUR-Lex publishes the EU version. The EU Exit Web Archive holds a snapshot of EUR-Lex’s version from IP completion day (31 December 2020 11.00 p.m.).
There are currently no known outstanding effects by UK legislation for Commission Regulation (EU) 2017/2196, Article 40.![]()
Revised legislation carried on this site may not be fully up to date. At the current time any known changes or effects made by subsequent legislation have been applied to the text of the legislation you are viewing by the editorial team. Please see ‘Frequently Asked Questions’ for details regarding the timescales for which new effects are identified and recorded on this site.
1.In addition to the provisions of Articles 40 to 53 of Regulation (EU) 2017/1485, each TSO, when in the emergency, blackout or restoration states, shall be entitled to gather the following information:
(a)from DSOs identified in accordance with Article 23(4), the necessary information about at least:
the part of their network that is in island operation;
the ability to synchronise parts of their network that is in island operation; and
the capability to start island operation.
(b)from SGUs identified in accordance with Article 23(4) and restoration service providers, information about at least the following conditions:
the current status of the installation;
the operational limits;
the full activation time and the time to increase generation; and
the time critical processes.
2.During the emergency, blackout or restoration states, each TSO shall provide in due time and for the purposes of system defence plan procedures and restoration plan procedures, the following information, where available to the TSO:
F1(a). . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
(b)to the frequency leader of its synchronised region, information about at least:
the restrictions to maintain island operation;
the available additional load and generation; and
the availability of operational reserves;
(c)to transmission connected DSOs identified in accordance with Article 11(4) and 23(4), information about at least:
the system state of its transmission system;
the limits of active and reactive power, block loading, tap and circuit breaker position at the connection points;
the information on the current and planned status of power generating modules connected to the DSO, if not available to the DSO directly; and
all necessary information leading to further coordination with distribution connected parties;
(d)to defence service providers, information about at least:
the system state of its transmission system; and
the scheduled measures that require participation of the defence service providers;
(e)to DSOs and SGUs identified pursuant to Article 23(4) and to restoration service providers, information about at least:
the system state of its transmission system;
the ability and plans to re-energise couplings; and
the scheduled measures that require their participation.
3.TSOs in emergency, blackout or restoration state shall exchange among themselves information concerning, at least:
(a)the circumstances that led to the current system state of its transmission system, to the extent that they are known; and
(b)the potential problems making assistance for active power necessary.
4.A TSO in emergency, blackout or restoration state shall provide, in due time, information about the system state of its transmission system and, where available, additional information explaining the situation on the transmission system:
F2(a). . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
[F3(b)to the regulatory authority;] and
(c)to any other relevant party, as appropriate.
5.TSOs shall inform each affected party about the test plan developed pursuant to Article 43(2) and (3).
Textual Amendments
F1Art. 40(2)(a) omitted (E.W.S.) (31.12.2020) by virtue of The Electricity Network Codes and Guidelines (System Operation and Connection) (Amendment etc.) (EU Exit) Regulations 2019 (S.I. 2019/533), reg. 1(2), Sch. 2 para. 25(2) (as amended by S.I. 2020/1016, regs. 1(2), 6(2)); 2020 c. 1, Sch. 5 para. 1(1)
F2Art. 40(4)(a) omitted (E.W.S.) (31.12.2020) by virtue of The Electricity Network Codes and Guidelines (System Operation and Connection) (Amendment etc.) (EU Exit) Regulations 2019 (S.I. 2019/533), reg. 1(2), Sch. 2 para. 25(3)(a) (as amended by S.I. 2020/1016, regs. 1(2), 6(2)); 2020 c. 1, Sch. 5 para. 1(1)
F3Art. 40(4)(b) substituted (E.W.S.) (31.12.2020) by The Electricity Network Codes and Guidelines (System Operation and Connection) (Amendment etc.) (EU Exit) Regulations 2019 (S.I. 2019/533), reg. 1(2), Sch. 2 para. 25(3)(b) (as amended by S.I. 2020/1016, regs. 1(2), 6(2)); 2020 c. 1, Sch. 5 para. 1(1)
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As adopted by EU): The original version of the legislation as it stood when it was first adopted in the EU. No changes have been applied to the text.
Geographical Extent: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.
Show Timeline of Changes: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
This timeline shows the different versions taken from EUR-Lex before exit day and during the implementation period as well as any subsequent versions created after the implementation period as a result of changes made by UK legislation.
The dates for the EU versions are taken from the document dates on EUR-Lex and may not always coincide with when the changes came into force for the document.
For any versions created after the implementation period as a result of changes made by UK legislation the date will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. For further information see our guide to revised legislation on Understanding Legislation.
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: