CHAPTER IIIU.K. RESTORATION PLAN

SECTION 2 U.K. Re-energisation

Article 26U.K.Re-energisation procedure

1.The re-energisation procedure of the restoration plan shall contain a set of measures allowing the TSO to apply:

(a)a top-down re-energisation strategy; and

(b)a bottom-up re-energisation strategy.

2.Regarding the bottom-up re-energisation strategy, the re-energisation procedure shall contain at least measures for:

(a)managing voltage and frequency deviations due to re-energisation;

(b)monitoring and managing island operation; and

(c)resynchronising island operation areas.