1.Each TSO shall be responsible for procuring balancing services from balancing service providers in order to ensure operational security.
2.Each TSO shall apply a self-dispatching model for determining generation schedules and consumption schedules. F1...
Textual Amendments
F1Words in Art. 14(2) omitted (31.12.2020) by virtue of The Electricity Network Codes and Guidelines (Markets and Trading) (Amendment) (EU Exit) Regulations 2019 (S.I. 2019/532), reg. 1(1), Sch. 2 para. 15; 2020 c. 1, Sch. 5 para. 1(1)
1.DSOs, TSOs, balancing service providers and balance responsible parties shall cooperate in order to ensure efficient and effective balancing.
2.Each DSO shall provide, in due time, all necessary information in order to perform the imbalance settlement to the connecting TSO in accordance with the terms and conditions related to balancing pursuant to Article 18.
3.Each TSO may, together with the reserve connecting DSOs within the TSO's control area, jointly elaborate a methodology for allocating costs resulting from actions of DSOs pursuant to paragraphs 4 and 5 of Article 182 of Regulation (EU) 2017/1485. The methodology shall provide for a fair allocation of costs taking into account the responsibilities of the parties involved.
4.DSOs shall report to the connecting TSO any limits defined pursuant to paragraphs 4 and 5 of Article 182 of Regulation (EU) 2017/1485 that could affect the requirements set out in this Regulation.
1.A balancing service provider shall qualify for providing bids for balancing energy or balancing capacity which are activated or procured by the connecting TSO F2.... Successful completion of the prequalification, ensured by the connecting TSO and processed pursuant to Article 159 and Article 162 of Regulation (EU) 2017/1485 shall be considered as a prerequisite for the successful completion of the qualification process to become a balancing service provider pursuant to this Regulation.
2.Each balancing service provider shall submit to the connecting TSO its balancing capacity bids that affect one or more balance responsible parties.
3.Each balancing service provider participating in the procurement process for balancing capacity shall submit and have the right to update its balancing capacity bids before the gate closure time of the procurement process.
4.Each balancing service provider with a contract for balancing capacity shall submit to its connecting TSO the balancing energy bids F3... corresponding to the volume, products, and other requirements set out in the balancing capacity contract.
5.Any balancing service provider shall have the right to submit to its connecting TSO the balancing energy bids F4... for which it has passed the prequalification process pursuant to Article 159 and Article 162 of Regulation (EU) 2017/1485.
6.The price of the balancing energy bids F5... pursuant to paragraph 4 shall not be predetermined in a contract for balancing capacity. A TSO may propose an exemption to this rule in the proposal for the terms and conditions related to balancing set-up pursuant to Article 18. Such an exemption shall F6... be accompanied with a justification demonstrating higher economic efficiency.
7.There shall be no discrimination between balancing energy bids F7... submitted pursuant to paragraph 4 and balancing energy bids F7... submitted pursuant to paragraph 5.
8.For each product for balancing energy or balancing capacity, the reserve providing unit, the reserve providing group, the demand facility or the third party and the associated balance responsible parties pursuant to Article 18(4)(d), shall belong to the same scheduling area.
Textual Amendments
F2Words in Art. 16(1) omitted (31.12.2020) by virtue of The Electricity Network Codes and Guidelines (Markets and Trading) (Amendment) (EU Exit) Regulations 2019 (S.I. 2019/532), reg. 1(1), Sch. 2 para. 16(2); 2020 c. 1, Sch. 5 para. 1(1)
F3Words in Art. 16(4) omitted (31.12.2020) by virtue of The Electricity Network Codes and Guidelines (Markets and Trading) (Amendment) (EU Exit) Regulations 2019 (S.I. 2019/532), reg. 1(1), Sch. 2 para. 16(3); 2020 c. 1, Sch. 5 para. 1(1)
F4Words in Art. 16(5) omitted (31.12.2020) by virtue of The Electricity Network Codes and Guidelines (Markets and Trading) (Amendment) (EU Exit) Regulations 2019 (S.I. 2019/532), reg. 1(1), Sch. 2 para. 16(4); 2020 c. 1, Sch. 5 para. 1(1)
F5Words in Art. 16(6) omitted (31.12.2020) by virtue of The Electricity Network Codes and Guidelines (Markets and Trading) (Amendment) (EU Exit) Regulations 2019 (S.I. 2019/532), reg. 1(1), Sch. 2 para. 16(5)(a); 2020 c. 1, Sch. 5 para. 1(1)
F6Words in Art. 16(6) omitted (31.12.2020) by virtue of The Electricity Network Codes and Guidelines (Markets and Trading) (Amendment) (EU Exit) Regulations 2019 (S.I. 2019/532), reg. 1(1), Sch. 2 para. 16(5)(b); 2020 c. 1, Sch. 5 para. 1(1)
F7Words in Art. 16(7) omitted (31.12.2020) by virtue of The Electricity Network Codes and Guidelines (Markets and Trading) (Amendment) (EU Exit) Regulations 2019 (S.I. 2019/532), reg. 1(1), Sch. 2 para. 16(6); 2020 c. 1, Sch. 5 para. 1(1)
1.In real time, each balance responsible party shall strive to be balanced or help the power system to be balanced. The detailed requirements concerning this obligation shall be defined in the proposal for terms and conditions related to balancing set up pursuant to Article 18.
2.Each balance responsible party shall be financially responsible for the imbalances to be settled with the connecting TSO.
F83.. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
F84.. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Textual Amendments
1.No later than six months after entry into force of this Regulation [F9TSOs] shall develop a proposal regarding:
(a)the terms and conditions for balancing service providers;
(b)the terms and conditions for balance responsible parties.
Where a LFC area consists of two or more TSOs, all TSOs of that LFC area may develop a common proposal subject to the approval by the [F10regulatory authority].
2.The terms and conditions pursuant to paragraph 1 shall also include the rules for suspension and restoration of market activities pursuant to Article 36 of Regulation (EU) 2017/2196 and rules for settlement in case of market suspension pursuant to Article 39 of Regulation (EU) 2017/2196 once approved in accordance with Article 4 of Regulation (EU) 2017/2196.
3.When developing proposals for terms and conditions for balancing service providers and balance responsible parties, each TSO shall:
(a)coordinate with the TSOs and DSOs that may be affected by those terms and conditions;
F11(b). . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
(c)involve other DSOs and other stakeholders throughout the development of the proposal and take into account their views without prejudice to public consultation pursuant to Article 10.
4.The terms and conditions for balancing service providers shall:
(a)define reasonable and justified requirements for the provisions of balancing services;
(b)allow the aggregation of demand facilities, energy storage facilities and power generating facilities in a scheduling area to offer balancing services subject to conditions referred to in paragraph 5 (c);
(c)allow demand facility owners, third parties and owners of power generating facilities from conventional and renewable energy sources as well as owners of energy storage units to become balancing service providers;
(d)require that each balancing energy bid from a balancing service provider is assigned to one or more balance responsible parties to enable the calculation of an imbalance adjustment pursuant to Article 49.
5.The terms and conditions for balancing service providers shall contain:
(a)the rules for the qualification process to become a balancing service provider pursuant to Article 16;
(b)the rules, requirements and timescales for the procurement and transfer of balancing capacity pursuant to Articles 32 F12... and 34;
(c)the rules and conditions for the aggregation of demand facilities, energy storage facilities and power generating facilities in a scheduling area to become a balancing service provider;
(d)the requirements on data and information to be delivered to the connecting TSO and, where relevant, to the reserve connecting DSO during the prequalification process and operation of the balancing market;
(e)the rules and conditions for the assignment of each balancing energy bid from a balancing service provider to one or more balance responsible parties pursuant to paragraph 4 (d);
(f)the requirements on data and information to be delivered to the connecting TSO and, where relevant, to the reserve connecting DSO to evaluate the provisions of balancing services pursuant to Article 154(1), Article 154(8), Article 158(1)(e), Article 158(4)(b), Article 161(1)(f) and Article 161(4)(b) of Regulation (EU) 2017/1485;
(g)the definition of a location for each [F13balancing] product taking into account paragraph 5 (c);
(h)the rules for the determination of the volume of balancing energy to be settled with the balancing service provider pursuant to Article 45;
(i)the rules for the settlement of balancing service providers defined pursuant to Chapters 2 and 5 of Title V;
(j)a maximum period for the finalisation of the settlement of balancing energy with a balancing service provider in accordance with Article 45, for any given imbalance settlement period;
(k)the consequences in case of non-compliance with the terms and conditions applicable to balancing service providers.
6.The terms and conditions for balance responsible parties shall contain:
(a)the definition of balance responsibility for each connection in a way that avoids any gaps or overlaps in the balance responsibility of different market participants providing services to that connection;
(b)the requirements for becoming a balance responsible party;
(c)the requirement that all balance responsible parties shall be financially responsible for their imbalances, and that the imbalances shall be settled with the connecting TSO;
(d)the requirements on data and information to be delivered to the connecting TSO to calculate the imbalances;
(e)the rules for balance responsible parties to change their schedules prior to and after the intraday energy gate closure time pursuant to [F14paragraph 4] of Article 17;
(f)the rules for the settlement of balance responsible parties defined pursuant to Chapter 4 of Title V;
(g)the delineation of an imbalance area pursuant to Article 54(2) and an imbalance price area;
(h)a maximum period for the finalisation of the settlement of imbalances with balance responsible parties for any given imbalance settlement period pursuant to Article 54;
(i)the consequences in case of non-compliance with the terms and conditions applicable to balance responsible parties;
(j)an obligation for balance responsible parties to submit to the connecting TSO any modifications of the position;
(k)the settlement rules pursuant to Articles 52, 53, 54 and 55;
(l)where existing, the provisions for the exclusion of imbalances from the imbalance settlement when they are associated with the introduction of ramping restrictions for the alleviation of deterministic frequency deviations pursuant to Article 137(4) of Regulation (EU) 2017/1485.
7.Each connecting TSO may include the following elements in the proposal for the terms and conditions for balancing service providers or in the terms and conditions for balance responsible parties:
F15(a). . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
(b)where justified, a requirement for balancing service providers to offer the unused generation capacity or other balancing resources through balancing energy bids F16... in the balancing markets after day ahead market gate closure time, without prejudice to the possibility of balancing service providers to change their balancing energy bids prior to the balancing energy gate closure time F17... due to trading within intraday market;
F18(c). . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
(d)specific requirements with regard to the position of balance responsible parties submitted after the day-ahead market timeframe to ensure that the sum of their internal and external commercial trade schedules equals the sum of the physical generation and consumption schedules, taking into account electrical losses compensation, where relevant;
(e)an exemption to publish information on offered prices of balancing energy or balancing capacity bids due to market abuse concerns pursuant to Article 12(4);
(f)an exemption F19... to predetermine the price of the balancing energy bids from a balancing capacity contract pursuant to Article 16(6);
(g)an application for the use of dual pricing for all imbalances [F20containing the information set out in Article 52(2)(d)(i) and (ii)].
F218.. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
9.Each TSO shall monitor the fulfilment by all parties of the requirements set out in the terms and conditions for balancing within its scheduling area or scheduling areas.
Textual Amendments
F9Word in Art. 18(1) substituted (31.12.2020) by The Electricity Network Codes and Guidelines (Markets and Trading) (Amendment) (EU Exit) Regulations 2019 (S.I. 2019/532), reg. 1(1), Sch. 2 para. 18(2)(a); 2020 c. 1, Sch. 5 para. 1(1)
F10Words in Art. 18(1) substituted (31.12.2020) by The Electricity Network Codes and Guidelines (Markets and Trading) (Amendment) (EU Exit) Regulations 2019 (S.I. 2019/532), reg. 1(1), Sch. 2 para. 18(2)(b); 2020 c. 1, Sch. 5 para. 1(1)
F11Art. 18(3)(b) omitted (31.12.2020) by virtue of The Electricity Network Codes and Guidelines (Markets and Trading) (Amendment) (EU Exit) Regulations 2019 (S.I. 2019/532), reg. 1(1), Sch. 2 para. 18(3); 2020 c. 1, Sch. 5 para. 1(1)
F12Word in Art. 18(5)(b) omitted (31.12.2020) by virtue of The Electricity Network Codes and Guidelines (Markets and Trading) (Amendment) (EU Exit) Regulations 2019 (S.I. 2019/532), reg. 1(1), Sch. 2 para. 18(4)(a); 2020 c. 1, Sch. 5 para. 1(1)
F13Word in Art. 18(5)(g) substituted (31.12.2020) by The Electricity Network Codes and Guidelines (Markets and Trading) (Amendment) (EU Exit) Regulations 2019 (S.I. 2019/532), reg. 1(1), Sch. 2 para. 18(4)(b); 2020 c. 1, Sch. 5 para. 1(1)
F14Words in Art. 18(6)(e) substituted (31.12.2020) by The Electricity Network Codes and Guidelines (Markets and Trading) (Amendment) (EU Exit) Regulations 2019 (S.I. 2019/532), reg. 1(1), Sch. 2 para. 18(5); 2020 c. 1, Sch. 5 para. 1(1)
F15Art. 18(7)(a) omitted (31.12.2020) by virtue of The Electricity Network Codes and Guidelines (Markets and Trading) (Amendment) (EU Exit) Regulations 2019 (S.I. 2019/532), reg. 1(1), Sch. 2 para. 18(6)(a); 2020 c. 1, Sch. 5 para. 1(1)
F16Words in Art. 18(7)(b) omitted (31.12.2020) by virtue of The Electricity Network Codes and Guidelines (Markets and Trading) (Amendment) (EU Exit) Regulations 2019 (S.I. 2019/532), reg. 1(1), Sch. 2 para. 18(6)(b)(i); 2020 c. 1, Sch. 5 para. 1(1)
F17Words in Art. 18(7)(b) omitted (31.12.2020) by virtue of The Electricity Network Codes and Guidelines (Markets and Trading) (Amendment) (EU Exit) Regulations 2019 (S.I. 2019/532), reg. 1(1), Sch. 2 para. 18(6)(b)(ii); 2020 c. 1, Sch. 5 para. 1(1)
F18Art. 18(7)(c) omitted (31.12.2020) by virtue of The Electricity Network Codes and Guidelines (Markets and Trading) (Amendment) (EU Exit) Regulations 2019 (S.I. 2019/532), reg. 1(1), Sch. 2 para. 18(6)(c); 2020 c. 1, Sch. 5 para. 1(1)
F19Words in Art. 18(7)(f) omitted (31.12.2020) by virtue of The Electricity Network Codes and Guidelines (Markets and Trading) (Amendment) (EU Exit) Regulations 2019 (S.I. 2019/532), reg. 1(1), Sch. 2 para. 18(6)(d); 2020 c. 1, Sch. 5 para. 1(1)
F20Words in Art. 18(7)(g) substituted (31.12.2020) by The Electricity Network Codes and Guidelines (Markets and Trading) (Amendment) (EU Exit) Regulations 2019 (S.I. 2019/532), reg. 1(1), Sch. 2 para. 18(6)(e); 2020 c. 1, Sch. 5 para. 1(1)
F21Art. 18(8) omitted (31.12.2020) by virtue of The Electricity Network Codes and Guidelines (Markets and Trading) (Amendment) (EU Exit) Regulations 2019 (S.I. 2019/532), reg. 1(1), Sch. 2 para. 18(7); 2020 c. 1, Sch. 5 para. 1(1)
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Textual Amendments
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Textual Amendments
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Textual Amendments
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Textual Amendments
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Textual Amendments
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Textual Amendments
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Textual Amendments
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Textual Amendments
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Textual Amendments
1.Each TSO shall ensure that fall-back solutions are in place in case [F24the procedure referred to in paragraph 2 fails].
2.Where the procurement of balancing services fails, the concerned TSOs shall repeat the procurement process. TSOs shall inform market participants that fall-back procedures will be used as soon as possible.
F253.. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Textual Amendments
Textual Amendments