PART IIU.K.OPERATIONAL SECURITY

TITLE 2U.K.DATA EXCHANGE

CHAPTER 6U.K.Data exchange between TSOs and demand facilities

Article 52U.K.Data exchange between TSOs and transmission-connected demand facilities

1.Unless otherwise provided by the TSO, each transmission-connected demand facility owner shall provide the following structural data to the TSO:

(a)electrical data of the transformers connected to the transmission system;

(b)characteristics of the load of the demand facility; and

(c)characteristics of the reactive power control.

2.Unless otherwise provided by the TSO, each transmission-connected demand facility owner shall provide the following data to the TSO:

(a)scheduled active and forecasted reactive power consumption on a day-ahead and intraday basis, including any changes of those schedules or forecast;

(b)any forecasted restriction in the reactive power control capability;

(c)in case of participation in demand response, a schedule of its structural minimum and maximum power range to be curtailed F1...

F1(d). . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

3.Unless otherwise provided by the TSO, each transmission-connected demand facility owner shall provide the following data to the TSO in real-time:

(a)active and reactive power at the connection point; and

(b)the minimum and maximum power range to be curtailed.

4.Each transmission-connected demand facility owner shall describe to its TSO its behaviour at the voltage ranges referred to in Article 27.