PART IIOPERATIONAL SECURITY

TITLE 2DATA EXCHANGE

CHAPTER 6Data exchange between TSOs and demand facilities

Article 52Data exchange between TSOs and transmission-connected demand facilities

1.

Unless otherwise provided by the TSO, each transmission-connected demand facility owner shall provide the following structural data to the TSO:

(a)

electrical data of the transformers connected to the transmission system;

(b)

characteristics of the load of the demand facility; and

(c)

characteristics of the reactive power control.

2.

Unless otherwise provided by the TSO, each transmission-connected demand facility owner shall provide the following data to the TSO:

(a)

scheduled active and forecasted reactive power consumption on a day-ahead and intraday basis, including any changes of those schedules or forecast;

(b)

any forecasted restriction in the reactive power control capability;

(c)

in case of participation in demand response, a schedule of its structural minimum and maximum power range to be curtailed F1...

F1(d)

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

3.

Unless otherwise provided by the TSO, each transmission-connected demand facility owner shall provide the following data to the TSO in real-time:

(a)

active and reactive power at the connection point; and

(b)

the minimum and maximum power range to be curtailed.

4.

Each transmission-connected demand facility owner shall describe to its TSO its behaviour at the voltage ranges referred to in Article 27.