TITLE IIIOPERATIONAL NOTIFICATION PROCEDURE FOR CONNECTION

CHAPTER 1 Connection of new power-generating modules

Article 30Operational notification of type A power-generating modules

1.

The operational notification procedure for connection of each new type A power-generating module shall consist of submitting an installation document. The power-generating facility owner shall ensure that the required information is filled in on an installation document obtained from the relevant system operator and is submitted to the system operator. Separate installation documents shall be provided for each power-generating module within the power-generating facility.

The relevant system operator shall ensure that the required information can be submitted by third parties on behalf of the power-generating facility owner.

2.

The relevant system operator shall specify the content of the installation document, which shall have at least the following information:

(a)

the location at which the connection is made;

(b)

the date of the connection;

(c)

the maximum capacity of the installation in kW;

(d)

the type of primary energy source;

(e)

the classification of the power-generating module as an emerging technology according to Title VI of this Regulation;

(f)

reference to equipment certificates issued by an authorised certifier used for equipment that is in the site installation;

(g)

as regards equipment used, for which an equipment certificate has not been received, information shall be provided as directed by the relevant system operator; and

(h)

the contact details of the power-generating facility owner and the installer and their signatures.

3.

The power-generating facility owner shall ensure that the relevant system operator or the F1regulatory authority is notified about the permanent decommissioning of a power-generating module F2....

The relevant system operator shall ensure that such notification can be made by third parties, including aggregators.