- Latest available (Revised)
- Original (As adopted by EU)
Regulation (EU) 2016/1037 of the European Parliament and of the Council of 8 June 2016 on protection against subsidised imports from countries not members of the European Union (codification)
When the UK left the EU, legislation.gov.uk published EU legislation that had been published by the EU up to IP completion day (31 December 2020 11.00 p.m.). On legislation.gov.uk, these items of legislation are kept up-to-date with any amendments made by the UK since then.
Legislation.gov.uk publishes the UK version. EUR-Lex publishes the EU version. The EU Exit Web Archive holds a snapshot of EUR-Lex’s version from IP completion day (31 December 2020 11.00 p.m.).
This version of this Regulation was derived from EUR-Lex on IP completion day (31 December 2020 11:00 p.m.). It has not been amended by the UK since then. Find out more about legislation originating from the EU as published on legislation.gov.uk.![]()
Revised legislation carried on this site may not be fully up to date. At the current time any known changes or effects made by subsequent legislation have been applied to the text of the legislation you are viewing by the editorial team. Please see ‘Frequently Asked Questions’ for details regarding the timescales for which new effects are identified and recorded on this site.
1.The amount of the countervailable subsidies shall be determined per unit of the subsidised product exported to the Union.
In establishing that amount, the following elements may be deducted from the total subsidy:
(a)any application fee or other costs necessarily incurred in order to qualify for, or to obtain, the subsidy;
(b)export taxes, duties or other charges levied on the export of the product to the Union specifically intended to offset the subsidy.
Where an interested party claims a deduction, it must prove that the claim is justified.
2.Where the subsidy is not granted by reference to the quantities manufactured, produced, exported or transported, the amount of countervailable subsidy shall be determined by allocating the value of the total subsidy, as appropriate, over the level of production, sales or exports of the products concerned during the investigation period for subsidisation.
3.Where the subsidy can be linked to the acquisition or future acquisition of fixed assets, the amount of the countervailable subsidy shall be calculated by spreading the subsidy across a period which reflects the normal depreciation of such assets in the industry concerned.
The amount so calculated which is attributable to the investigation period, including that which derives from fixed assets acquired before that period, shall be allocated as described in paragraph 2.
Where the assets are non-depreciating, the subsidy shall be valued as an interest-free loan, and be treated in accordance with Article 6(b).
4.Where a subsidy cannot be linked to the acquisition of fixed assets, the amount of the benefit received during the investigation period shall in principle be attributed to that period, and allocated as described in paragraph 2, unless special circumstances arise justifying attribution over a different period.
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As adopted by EU): The original version of the legislation as it stood when it was first adopted in the EU. No changes have been applied to the text.
Geographical Extent: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.
Show Timeline of Changes: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
This timeline shows the different versions taken from EUR-Lex before exit day and during the implementation period as well as any subsequent versions created after the implementation period as a result of changes made by UK legislation.
The dates for the EU versions are taken from the document dates on EUR-Lex and may not always coincide with when the changes came into force for the document.
For any versions created after the implementation period as a result of changes made by UK legislation the date will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. For further information see our guide to revised legislation on Understanding Legislation.
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: