Commission Regulation (EU) No 543/2013 of 14 June 2013 on submission and publication of data in electricity markets and amending Annex I to Regulation (EC) No 714/2009 of the European Parliament and of the Council (Text with EEA relevance)
When the UK left the EU, legislation.gov.uk published EU legislation that had been published by the EU up to IP completion day (31 December 2020 11.00 p.m.). On legislation.gov.uk, these items of legislation are kept up-to-date with any amendments made by the UK since then.
Legislation.gov.uk publishes the UK version. EUR-Lex publishes the EU version. The EU Exit Web Archive holds a snapshot of EUR-Lex’s version from IP completion day (31 December 2020 11.00 p.m.).
There are currently no known outstanding effects by UK legislation for Commission Regulation (EU) No 543/2013, Article 17.
Revised legislation carried on this site may not be fully up to date. At the current time any known changes or effects made by subsequent legislation have been applied to the text of the legislation you are viewing by the editorial team. Please see ‘Frequently Asked Questions’ for details regarding the timescales for which new effects are identified and recorded on this site.
1.For their control areas, TSOs or where applicable operators of balancing markets, where such markets exist shall [F1publish] the following information F2...:
(a)rules on balancing including:
(a)processes for the procurement of different types of balancing reserves and of balancing energy,
the methodology of remuneration for both the provision of reserves and activated energy for balancing,
the methodology for calculating imbalance charges,
if applicable, a description on how cross-border balancing between two or more control areas is carried out and the conditions for generators and load to participate;
(b)the amount of balancing reserves under contract (MW) by the TSO, specifying:
(b)the source of reserve (generation or load),
the type of reserve (e.g. Frequency Containment Reserve, Frequency Restoration Reserve, Replacement Reserve),
the time period for which the reserves are contracted (e.g. hour, day, week, month, year, etc.);
(c)prices paid by the TSO per type of procured balancing reserve and per procurement period (Currency/MW/period);
(d)accepted aggregated offers per balancing time unit, separately for each type of balancing reserve;
(e)the amount of activated balancing energy (MW) per balancing time unit and per type of reserve;
(f)prices paid by the TSO for activated balancing energy per balancing time unit and per type of reserve; price information shall be provided separately for up and down regulation;
(g)imbalance prices per balancing time unit;
(h)total imbalance volume per balancing time unit;
(i)monthly financial balance of the control area, specifying:
(i)the expenses incurred to the TSO for procuring reserves and activating balancing energy,
the net income to the TSO after settling the imbalance accounts with balance responsible parties;
(j)if applicable, information regarding Cross Control Area Balancing per balancing time unit, specifying:
(j)the volumes of exchanged bids and offers per procurement time unit,
maximum and minimum prices of exchanged bids and offers per procurement time unit,
volume of balancing energy activated in the control areas concerned.
Operators of balancing markets shall be considered as primary owners of the information they provide.
2.The information laid down:
(a)in point (b) of paragraph 1 shall be published as soon as possible but no later than two hours before the next procurement process takes place;
(b)in point (c) of paragraph 1 shall be published as soon as possible but no later than one hour after the procurement process ends;
(c)in point (d) of paragraph 1 shall be published as soon as possible but no later than one hour after the operating period;
(d)in point (e) of paragraph 1 shall be published as soon as possible but no later than 30 minutes after the operating period. In case the data are preliminary, the figures shall be updated when the data become available;
(e)in point (f) of paragraph 1 shall be published as soon as possible but no later than one hour after the operating period;
(f)in point (g) of paragraph 1 shall be published as soon as possible;
(g)in point (h) of paragraph 1 shall be published as soon as possible but no later than 30 minutes after the operating period. In case the data are preliminary, the figures shall be updated when the data become available;
(h)in point (i) of paragraph 1 shall be published no later than three months after the operational month. In case the settlement is preliminary, the figures shall be updated after the final settlement;
(i)in point (j) of paragraph 1 shall be published no later than one hour after the operating period.
Textual Amendments
F1Word in Art. 17(1) substituted (31.12.2020) by The Electricity and Gas (Market Integrity and Transparency) (Amendment) (EU Exit) Regulations 2019 (S.I. 2019/534), reg. 1(2), Sch. 3 para. 16(a); 2020 c. 1, Sch. 5 para. 1(1)
F2Words in Art. 17(1) omitted (31.12.2020) by virtue of The Electricity and Gas (Market Integrity and Transparency) (Amendment) (EU Exit) Regulations 2019 (S.I. 2019/534), reg. 1(2), Sch. 3 para. 16(b); 2020 c. 1, Sch. 5 para. 1(1)
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As adopted by EU): The original version of the legislation as it stood when it was first adopted in the EU. No changes have been applied to the text.
Geographical Extent: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.
Show Timeline of Changes: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
This timeline shows the different versions taken from EUR-Lex before exit day and during the implementation period as well as any subsequent versions created after the implementation period as a result of changes made by UK legislation.
The dates for the EU versions are taken from the document dates on EUR-Lex and may not always coincide with when the changes came into force for the document.
For any versions created after the implementation period as a result of changes made by UK legislation the date will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. For further information see our guide to revised legislation on Understanding Legislation.
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: