xmlns:atom="http://www.w3.org/2005/Atom" xmlns:atom="http://www.w3.org/2005/Atom"

CHAPTER IV U.K. DISTRIBUTION SYSTEM OPERATION

Article 36U.K.Ownership of energy storage facilities by distribution system operators

1.Distribution system operators shall not own, develop, manage or operate energy storage facilities.

2.By way of derogation from paragraph 1, Member States may allow distribution system operators to own, develop, manage or operate energy storage facilities, where they are fully integrated network components and the regulatory authority has granted its approval, or where all of the following conditions are fulfilled:

(a)other parties, following an open, transparent and non-discriminatory tendering procedure that is subject to review and approval by the regulatory authority, have not been awarded a right to own, develop, manage or operate such facilities, or could not deliver those services at a reasonable cost and in a timely manner;

(b)such facilities are necessary for the distribution system operators to fulfil their obligations under this Directive for the efficient, reliable and secure operation of the distribution system and the facilities are not used to buy or sell electricity in the electricity markets; and

(c)the regulatory authority has assessed the necessity of such a derogation and has carried out an assessment of the tendering procedure, including the conditions of the tendering procedure, and has granted its approval.

The regulatory authority may draw up guidelines or procurement clauses to help distribution system operators ensure a fair tendering procedure.

3.The regulatory authorities shall perform, at regular intervals or at least every five years, a public consultation on the existing energy storage facilities in order to assess the potential availability and interest in investing in such facilities. Where the public consultation, as assessed by the regulatory authority, indicates that third parties are able to own, develop, operate or manage such facilities in a cost-effective manner, the regulatory authority shall ensure that the distribution system operators' activities in this regard are phased out within 18 months. As part of the conditions of that procedure, regulatory authorities may allow the distribution system operators to receive reasonable compensation, in particular to recover the residual value of their investment in the energy storage facilities.

4.Paragraph 3 shall not apply to fully integrated network components or for the usual depreciation period of new battery storage facilities with a final investment decision until 4 July 2019, provided that such battery storage facilities are:

(a)connected to the grid at the latest two years thereafter;

(b)integrated into the distribution system;

(c)used only for the reactive instantaneous restoration of network security in the case of network contingencies where such restoration measure starts immediately and ends when regular re-dispatch can solve the issue; and

(d)not used to buy or sell electricity in the electricity markets, including balancing.