Directive 2014/61/EU of the European Parliament and of the Council of 15 May 2014 on measures to reduce the cost of deploying high-speed electronic communications networks (Text with EEA relevance)
When the UK left the EU, legislation.gov.uk published EU legislation that had been published by the EU up to IP completion day (31 December 2020 11.00 p.m.). On legislation.gov.uk, these items of legislation are kept up-to-date with any amendments made by the UK since then.
Legislation.gov.uk publishes the UK version. EUR-Lex publishes the EU version. The EU Exit Web Archive holds a snapshot of EUR-Lex’s version from IP completion day (31 December 2020 11.00 p.m.).
EU Directives are published on this site to aid cross referencing from UK legislation. Since IP completion day (31 December 2020 11.00 p.m.) no amendments have been applied to this version.
1.Member States shall ensure that every network operator has the right to negotiate agreements concerning the coordination of civil works with undertakings providing or authorised to provide electronic communications networks with a view to deploying elements of high-speed electronic communications networks.
2.Member States shall ensure that every network operator performing directly or indirectly civil works, either fully or partially financed by public means, meets any reasonable request to coordinate civil works on transparent and non-discriminatory terms, made by undertakings providing or authorised to provide public communications networks with a view to deploying elements of high-speed electronic communications networks. Such request shall be met provided that:
(a)this will not entail any additional costs, including because of additional delays, for the initially envisaged civil works;
(b)this will not impede control over the coordination of the works; and
(c)the request to coordinate is filed as soon as possible and in any case at least one month before the submission of the final project to the competent authorities for permit granting.
Member States may provide rules on apportioning the costs associated with the coordination of civil works.
3.Where an agreement on the coordination of civil works pursuant to paragraph 2 is not achieved within one month from the date of receipt of the formal request to negotiate, Member States shall ensure that any party is entitled to refer the issue to the competent national dispute settlement body.
4.Member States shall ensure that the national dispute settlement body referred to in paragraph 3 issues, taking full account of the principle of proportionality, a decision to resolve the dispute initiated pursuant to paragraph 3, including the determination of fair and non-discriminatory terms, conditions and charges where appropriate.
The national dispute settlement body shall resolve the dispute within the shortest possible time frame, and in any case within two months from the date of the receipt of the complete request, except in exceptional circumstances, without prejudice to the possibility for any party to refer the case to a court.
5.Member States may provide for exemptions from the obligations provided for in this Article for civil works of insignificant importance, such as in terms of value, size or duration, or in the case of critical national infrastructure. Such exemptions shall be duly reasoned. The interested parties shall be given the opportunity to comment on the draft exemptions within a reasonable period. Any such exemption shall be notified to the Commission.
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As adopted by EU): The original version of the legislation as it stood when it was first adopted in the EU. No changes have been applied to the text.
Geographical Extent: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.
Show Timeline of Changes: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
This timeline shows the different versions taken from EUR-Lex before exit day and during the implementation period as well as any subsequent versions created after the implementation period as a result of changes made by UK legislation.
The dates for the EU versions are taken from the document dates on EUR-Lex and may not always coincide with when the changes came into force for the document.
For any versions created after the implementation period as a result of changes made by UK legislation the date will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. For further information see our guide to revised legislation on Understanding Legislation.
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: