Article 41U.K.Prior involvement of candidates or tenderers

Where a candidate or tenderer or an undertaking related to a candidate or tenderer has advised the contracting authority, whether in the context of Article 40 or not, or has otherwise been involved in the preparation of the procurement procedure, the contracting authority shall take appropriate measures to ensure that competition is not distorted by the participation of that candidate or tenderer.

Such measures shall include the communication to the other candidates and tenderers of relevant information exchanged in the context of or resulting from the involvement of the candidate or tenderer in the preparation of the procurement procedure and the fixing of adequate time limits for the receipt of tenders. The candidate or tenderer concerned shall only be excluded from the procedure where there are no other means to ensure compliance with the duty to observe the principle of equal treatment.

Prior to any such exclusion, candidates or tenderers shall be given the opportunity to prove that their involvement in preparing the procurement procedure is not capable of distorting competition. The measures taken shall be documented in the individual report required by Article 84.