Search Legislation

Directive 2009/72/EC of the European Parliament and of the CouncilShow full title

Directive 2009/72/EC of the European Parliament and of the Council of 13 July 2009 concerning common rules for the internal market in electricity and repealing Directive 2003/54/EC (Text with EEA relevance)

 Help about what version

What Version

 Help about advanced features

Advanced Features

Close

This is a legislation item that originated from the EU

After exit day there will be three versions of this legislation to consult for different purposes. The legislation.gov.uk version is the version that applies in the UK. The EU Version currently on EUR-lex is the version that currently applies in the EU i.e you may need this if you operate a business in the EU.

The web archive version is the official version of this legislation item as it stood on exit day before being published to legislation.gov.uk and any subsequent UK changes and effects applied. The web archive also captured associated case law and other language formats from EUR-Lex.

Status:

EU Directives are being published on this site to aid cross referencing from UK legislation. After IP completion day (31 December 2020 11pm) no further amendments will be applied to this version.

CHAPTER IU.K.SUBJECT MATTER, SCOPE AND DEFINITIONS

Article 1U.K.Subject matter and scope

This Directive establishes common rules for the generation, transmission, distribution and supply of electricity, together with consumer protection provisions, with a view to improving and integrating competitive electricity markets in the Community. It lays down the rules relating to the organisation and functioning of the electricity sector, open access to the market, the criteria and procedures applicable to calls for tenders and the granting of authorisations and the operation of systems. It also lays down universal service obligations and the rights of electricity consumers and clarifies competition requirements.

Article 2U.K.Definitions

For the purposes of this Directive, the following definitions apply:

1.

‘generation’ means the production of electricity;

2.

‘producer’ means a natural or legal person generating electricity;

3.

‘transmission’ means the transport of electricity on the extra high-voltage and high-voltage interconnected system with a view to its delivery to final customers or to distributors, but does not include supply;

4.

‘transmission system operator’ means a natural or legal person responsible for operating, ensuring the maintenance of and, if necessary, developing the transmission system in a given area and, where applicable, its interconnections with other systems, and for ensuring the long-term ability of the system to meet reasonable demands for the transmission of electricity;

5.

‘distribution’ means the transport of electricity on high-voltage, medium-voltage and low-voltage distribution systems with a view to its delivery to customers, but does not include supply;

6.

‘distribution system operator’ means a natural or legal person responsible for operating, ensuring the maintenance of and, if necessary, developing the distribution system in a given area and, where applicable, its interconnections with other systems and for ensuring the long-term ability of the system to meet reasonable demands for the distribution of electricity;

7.

‘customer’ means a wholesale or final customer of electricity;

8.

‘wholesale customer’ means a natural or legal person purchasing electricity for the purpose of resale inside or outside the system where he is established;

9.

‘final customer’ means a customer purchasing electricity for his own use;

10.

‘household customer’ means a customer purchasing electricity for his own household consumption, excluding commercial or professional activities;

11.

‘non-household customer’ means a natural or legal persons purchasing electricity which is not for their own household use and includes producers and wholesale customers;

12.

‘eligible customer’ means a customer who is free to purchase electricity from the supplier of his choice within the meaning of Article 33;

13.

‘interconnector’ means equipment used to link electricity systems;

14.

‘interconnected system’ means a number of transmission and distribution systems linked together by means of one or more interconnectors;

15.

‘direct line’ means either an electricity line linking an isolated generation site with an isolated customer or an electricity line linking an electricity producer and an electricity supply undertaking to supply directly their own premises, subsidiaries and eligible customers;

16.

‘economic precedence’ means the ranking of sources of electricity supply in accordance with economic criteria;

17.

‘ancillary service’ means a service necessary for the operation of a transmission or distribution system;

18.

‘system user’ means a natural or legal person supplying to, or being supplied by, a transmission or distribution system;

19.

‘supply’ means the sale, including resale, of electricity to customers;

20.

‘integrated electricity undertaking’ means a vertically or horizontally integrated undertaking;

21.

‘vertically integrated undertaking’ means an electricity undertaking or a group of electricity undertakings where the same person or the same persons are entitled, directly or indirectly, to exercise control, and where the undertaking or group of undertakings perform at least one of the functions of transmission or distribution, and at least one of the functions of generation or supply of electricity;

22.

‘related undertaking’ means affiliated undertakings, within the meaning of Article 41 of the Seventh Council Directive 83/349/EEC of 13 June 1983 based on Article 44(2)(g)(1) of the Treaty on consolidated accounts(2), and/or associated undertakings, within the meaning of Article 33(1) of that Directive, and/or undertakings which belong to the same shareholders;

23.

‘horizontally integrated undertaking’ means an undertaking performing at least one of the functions of generation for sale, or transmission, or distribution, or supply of electricity, and another non-electricity activity;

24.

‘tendering procedure’ means the procedure through which planned additional requirements and replacement capacity are covered by supplies from new or existing generating capacity;

25.

‘long-term planning’ means the planning of the need for investment in generation and transmission and distribution capacity on a long-term basis, with a view to meeting the demand of the system for electricity and securing supplies to customers;

26.

‘small isolated system’ means any system with consumption of less than 3 000 GWh in the year 1996, where less than 5 % of annual consumption is obtained through interconnection with other systems;

27.

‘micro isolated system’ means any system with consumption less than 500 GWh in the year 1996, where there is no connection with other systems;

28.

‘security’ means both security of supply and provision of electricity, and technical safety;

29.

‘energy efficiency/demand-side management’ means a global or integrated approach aimed at influencing the amount and timing of electricity consumption in order to reduce primary energy consumption and peak loads by giving precedence to investments in energy efficiency measures, or other measures, such as interruptible supply contracts, over investments to increase generation capacity, if the former are the most effective and economical option, taking into account the positive environmental impact of reduced energy consumption and the security of supply and distribution cost aspects related to it;

30.

‘renewable energy sources’ means renewable non-fossil energy sources (wind, solar, geothermal, wave, tidal, hydropower, biomass, landfill gas, sewage treatment plant gas and biogases);

31.

‘distributed generation’ means generation plants connected to the distribution system;

32.

‘electricity supply contract’ means a contract for the supply of electricity, but does not include an electricity derivative;

33.

‘electricity derivative’ means a financial instrument specified in points 5, 6 or 7 of Section C of Annex I to Directive 2004/39/EC of the European Parliament and of the Council of 21 April 2004 on markets in financial instruments(3), where that instrument relates to electricity;

34.

‘control’ means rights, contracts or any other means which, either separately or in combination and having regard to the considerations of fact or law involved, confer the possibility of exercising decisive influence on an undertaking, in particular by:

(a)

ownership or the right to use all or part of the assets of an undertaking;

(b)

rights or contracts which confer decisive influence on the composition, voting or decisions of the organs of an undertaking;

35.

‘electricity undertaking’ means any natural or legal person carrying out at least one of the following functions: generation, transmission, distribution, supply, or purchase of electricity, which is responsible for the commercial, technical or maintenance tasks related to those functions, but does not include final customers.

(1)

The title of Directive 83/349/EEC has been adjusted to take account of the renumbering of the Articles of the Treaty establishing the European Community in accordance with Article 12 of the Treaty of Amsterdam; the original reference was to Article 54(3)(g).

Back to top

Options/Help

Print Options

Close

Legislation is available in different versions:

Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.

Original (As adopted by EU): The original version of the legislation as it stood when it was first adopted in the EU. No changes have been applied to the text.

Close

See additional information alongside the content

Geographical Extent: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.

Show Timeline of Changes: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.

Close

Opening Options

Different options to open legislation in order to view more content on screen at once

Close

More Resources

Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as adopted version that was used for the EU Official Journal
  • lists of changes made by and/or affecting this legislation item
  • all formats of all associated documents
  • correction slips
  • links to related legislation and further information resources
Close

Timeline of Changes

This timeline shows the different versions taken from EUR-Lex before exit day and during the implementation period as well as any subsequent versions created after the implementation period as a result of changes made by UK legislation.

The dates for the EU versions are taken from the document dates on EUR-Lex and may not always coincide with when the changes came into force for the document.

For any versions created after the implementation period as a result of changes made by UK legislation the date will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. For further information see our guide to revised legislation on Understanding Legislation.

Close

More Resources

Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as adopted version that was used for the print copy
  • correction slips

Click 'View More' or select 'More Resources' tab for additional information including:

  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • links to related legislation and further information resources