xmlns:atom="http://www.w3.org/2005/Atom" xmlns:atom="http://www.w3.org/2005/Atom"

ANNEX IIU.K.MINIMUM TECHNICAL REQUIREMENTS APPLICABLE TO VESSELS ON INLAND WATERWAYS OF ZONES 1, 2, 3 AND 4

PART IIU.K.

CHAPTER 10U.K.EQUIPMENT

Article 10.03aU.K. [F1Permanently installed firefighting systems for protecting accommodation spaces, wheelhouses and passenger spaces]

1.Fire protection in accommodation spaces, wheelhouses and passenger spaces is to be provided only by suitable automatic pressurised water sprinklers as permanently installed fire-fighting systems.

2.Installation or conversion of the systems shall be carried out only by specialised firms.

3.The systems shall be made of steel or equivalent non-combustible materials.

4.The systems shall be able to spray water at a rate of at least 5 l/m2 per minute over the area of the largest room to be protected.

[F25. Systems spraying smaller quantities of water shall have a type-approval pursuant to IMO Resolution A 800(19) or another recognised standard. Such recognitions, when designed to amend non-essential elements of this Directive, shall be adopted in accordance with the regulatory procedure with scrutiny referred to in Article 19(3) of this Directive. Type-approval shall be carried out by an approved classification society or an accredited testing institution. The accredited testing institution shall comply with the European standard for general requirements for the competence of testing and calibrating laboratories (EN ISO/IEC 17025: 2000).]

[F36. The systems shall be checked by an expert:

(a) before being put into service for the first time,

(b) before being put back into service after they have been triggered,

(c) before being put back into service after any major modification or repair,

(d) regularly, at least every two years.

Inspections as referred to in point (d) may also be carried out by a competent person from a competent firm specialising in fire extinguishing systems.

7. When carrying out the check in accordance with paragraph 6, the expert or competent person shall verify whether the systems meet the requirements of this paragraph.

The check shall at least include:

(a) external inspection of the entire system;

(b) functional testing of the safety systems and nozzles;

(c) functional testing of the pressure tanks and pumping system.

8. An inspection certificate, signed by the expert or competent person, shall be issued, showing the date of inspection.]

9.The number of installed systems shall be entered in the Community certificate.

F410.. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .