Article 3U.K.
1.Spain shall recover the incompatible aid granted under the scheme referred to in Article 1 from TelecomCLM and Abertis.
2.The sums to be recovered shall bear interest from the date on which they were put at the disposal of the beneficiaries until their actual recovery.
3.The interest shall be calculated on a compound basis in accordance with Chapter V of Commission Regulation (EC) No 794/2004(1).
4.Spain shall cancel all outstanding payments of aid under the scheme referred to in Article 1 with effect from the date of notification of this decision.
Commission Regulation (EC) No 794/2004 of 21 April 2004 implementing Council Regulation (EU) 2015/1589 laying down detailed rules for the application of Article 108 of the Treaty on the Functioning of the European Union (OJ L 140 30.4.2004, p. 1).