Commission Decision
of 23 January 2013
on State aid SA.24123 (2012/C) (ex 2011/NN) implemented by the Netherlands Alleged sale of land below market price by the Municipality of Leidschendam-Voorburg
(notified under document C(2013) 87)
(Only the Dutch text is authentic)
(Text with EEA relevance)
(2013/247/EU)
THE EUROPEAN COMMISSION,
Having regard to the Treaty on the Functioning of the European Union, and in particular the first subparagraph of Article 108(2) thereof,
Having regard to the Agreement on the European Economic Area, and in particular Article 62(1)(a) thereof,
Whereas:
By letter of 10 September 2007, the Stichting Behoud Damplein Leidschendam (hereinafter “the Stichting”), a foundation set up in 2006 to defend the interests of residents located in the vicinity of the Damplein in Leidschendam-Voorburg (the Netherlands), submitted a complaint to the Commission concerning the alleged grant of State aid in the context of a real estate project initiated by the municipality of Leidschendam-Voorburg in co-operation with a number of private parties.
By letter of 12 October 2007, the Commission forwarded the complaint to the Dutch authorities for their consideration, along with a request to reply to a number of questions. The Dutch authorities submitted their reply by letter of 7 December 2007. The Commission sent further requests for information to the Dutch authorities by letters of 25 April 2008, 12 September 2008, 14 August 2009, 12 February 2010 and 2 August 2011. The Dutch authorities replied to these requests by letters of 30 May 2008, 7 November 2008, 30 October 2009, 12 April 2010, 29 September 2011 and 3 October 2011, respectively. On 12 March 2010, a meeting took place between the Commission services and the Dutch authorities and, as a result, additional information was submitted to the Commission by letter of 30 August 2010.
By letter of 18 April 2012, the Dutch authorities submitted their observations on the opening decision, after having received two extensions of the deadline to comment and after a meeting with the Commission services on 12 March 2012 in the presence of the beneficiary of the measure.
By letter of 16 April 2012, the Stichting submitted its comments to the Commission on the opening decision. The non-confidential version of these comments was forwarded to the Dutch authorities by letter of 16 May 2012. By letter of 14 June 2012, the Dutch authorities submitted their reaction to the Stichting’s comments.
The beneficiary of the measures is the partnership Schouten-de Jong Bouwfonds (hereinafter “SJB”). This partnership was set up by Schouten & De Jong Projectontwikkeling BV (hereinafter "Schouten de Jong") and Bouwfonds Ontwikkeling BV (hereinafter "Bouwfonds") for the purposes of the contested real estate project and does not have legal personality under Dutch law.
Schouten de Jong, established in Voorburg, the Netherlands, is active in real estate project development in the Netherlands, in particular in the Leidschendam area. Its turnover amounted to EUR 60 million in 2011.
Bouwfonds, established in Delft, the Netherlands, and a subsidiary of Rabo Vastgoed, is the largest real estate developer in the Netherlands and among the top three largest players on the European real estate market. Bouwfonds is active, in particular, in the Netherlands, Germany and France. It had a turnover of EUR 1,6 billion in 2011.
The municipality of Leidschendam-Voorburg (hereinafter: “the Municipality”) is located in the province of South Holland, close to The Hague, in the Netherlands.
On the basis of the Leidschendam Centrum Project, the Municipality concluded a co-operation agreement with a number of private project developers, including with SJB, on 9 September 2004 (hereinafter: the “2004 Co-operation Agreement”). The 2004 Co-operation Agreement stipulates that the private project developers would, for each of the specific sub-parts of the Leidschendam Centrum Project assigned to them, construct and sell, for their own risk and expense, the envisaged real estate.
According to the 2004 Co-operation Agreement, the construction works would begin once the land had been made ready for construction (see recital (22) below) and the necessary building permits had been obtained. However, as regards the construction of the free sector housing units, the private developers were allowed to postpone construction until 70 % of these units, whether or not in combination with social housing units, in the sub-project area concerned had been pre-sold (Article 7.5 of the 2004 Co-operation Agreement, hereinafter: the “70 % clause”). This 70 % clause is commonly found in construction contracts in the Netherlands and seeks to limit the risks for project developers of constructing real estate which might not be sold. The agreement did not, however, provide for any possibility to postpone construction as regards the commercial premises and the underground parking garage.
The Municipality, as also explicitly emphasised by the Dutch authorities in its submissions, was not involved in the construction phase of the project and bore no risks in relation to the sale of the housing units and commercial premises. Profits from these sales, if any, would accrue directly to the private developers. The construction phase of the project should be distinguished from the so-called ground exploitation phase of the project, where the Municipality was involved through the PPP with SJB and bore 50 % of the risks (see recital 18 below).
Besides making the land ready for construction, the ground exploitation phase also covered the construction, temporary exploitation and reselling of the public part of the underground parking garage and the building of the school (Article 4 of the GREX). To this end, the PPP agreed with SJB that SJB would construct the underground public garage, which was considered to be intrinsically linked to the private section of the parking garage (article 9 of the GREX), for which SJB would receive a maximum amount of approximately EUR 4,6 million (value on 1 January 2003) from the PPP (Article 6 of the SJB Project Agreement). The construction of the private section of the parking garage would be financed by SJB itself. The PPP intended to sell the entire parking garage to a third party and the revenues from that sale were to flow to the PPP, which would share them between the Municipality and SJB.
Finally, the PPP would also contribute 50 % of the costs for the construction of a school in another plan area of the Leidschendam Centrum Project. The remaining 50 % would be financed directly by the Municipality (Article 8 of the GREX).
As follows from recitals 17 to 20 above, the costs of the ground exploitation phase of the project consisted essentially in the costs of the acquisition of the land insofar as it was not already owned by the Municipality, the costs of making the land ready for construction, the costs for the public section of the underground parking garage and 50 % of the construction costs for the school.
The PPP would generate revenues from the ground exploitation phase, first and foremost, through the sale of the land to private project developers, including SJB, after the PPP had made the land ready for construction. Each project developer was to purchase the part of the land assigned to it to construct housing units and commercial premises. The prices for the land were laid down in Article 10 and Annex 3a of the 2004 Co-operation Agreement. The 2004 Co-operation Agreement explicitly stated that these prices were minimum prices, which could be increased if more than the planned floor space was constructed. These prices were based on an independent expert valuation report, dated 11 March 2003, which considered the prices to be market-conform. Payment of the land price was due at the moment the private developer concerned obtained the necessary building permits and would take place, at the latest, at the moment of the legal transfer of the land (Article 10.5 of the 2004 Co-operation Agreement).
The price of the land sold by the PPP to SJB for the overall Leidschendam Centrum Project was determined at minimum EUR 18,5 million (value on 1 January 2003). The land in the Damplein area sold by the PPP to SJB was determined at minimum EUR 7,2 million (value on 1 January 2003), yearly indexed with 2,5 % until payment.
As regards SJB, the total ground exploitation fee was determined at approximately EUR 1,1 million and the quality fee at approximately EUR 0,9 million (value on 1 January 2003), indexed yearly by 2,5 % until payment, for all the housing units it planned to build in the Leidschendam centrum area. The final ground exploitation fee and quality fee due would depend on the number of housing units actually built.
According to the timeline which was set up in March 2004, construction works on the Damplein were initially planned to start in November 2005. However, due to several national court proceedings, the building permits SJB needed to commence construction were delayed and eventually only obtained in November 2008.
SJB started with the pre-sale of housing units in February 2007, but experienced difficulties selling these and eventually managed to pre-sell only 20 of the 67 planned units. Because of the delays encountered in obtaining the necessary building permits, these pre-sale contracts were annulled in September 2008 so that, when SJB finally obtained the permits to start construction works in November of that year, none of the housing units SJB was required to build on the Damplein had been pre-sold. In the meantime, the financial crisis had started and affected the Dutch real-estate market in particular.
In this context, SJB informed the Municipality that it would not start any of the construction works, notwithstanding the fact that the 2004 Co-operation Agreement only allowed it to postpone construction of the housing units if less than 70 % of these units had been sold. As explained in recital 14 above, the 70 % clause did not cover the construction of the commercial premises or the underground parking garage.
In the Autumn of 2008, SJB made a proposal to the PPP to pay EUR 4 million for the land on the Damplein, instead of the EUR 7,2 million (value on 1 January 2003) originally agreed, whereby SJB would start the construction works in April 2009 regardless of whether the housing units had been pre-sold. In return for this decrease in price, SJB was therefore willing to waive its right to invoke the 70 % clause contained in the 2004 Co-operation Agreement. SJB further proposed to contact an investor who would guarantee to buy the unsold housing units. According to the Dutch authorities this resulted in a price lower than that expected from a direct sale to private persons.
On 18 December 2008, the PPP and SJB decided in principle to the price decrease, but before seeking approval from the Municipality’s Council, the Municipality contacted an independent expert to determine whether the price calculated by SJB was a market-conform price. In its report of 11 February 2009, the expert concluded that EUR 4 million (value on 1 January 2010) could, on the basis of the residual value method, be considered a market-conform price for the land on the Damplein in 2010, taking into account the fact that SJB committed to sell the unsold housing units to an investor and had agreed to lower its initially foreseen profit and risk margin from 5 % to 2 %. The report did not take into account the lowering of the ground exploitation fee and quality fee.
On the basis of this report and because, according to the Dutch authorities, the Municipality feared further delays and considered it of general interest that the construction phase was started as soon as possible, the Municipality's Council, in its meeting of 10 March 2009, decided that the PPP would agree to lower the price and fees originally agreed in 2004 with SJB for the land located on the Damplein. A proposal of 18 February 2009 from the Municipality, which was sent to the members of its Council, refers to a decrease in price for the land and a decrease in the ground exploitation and quality fees. The proposal further states that this decrease would turn the ground exploitation phase, which was budgeted to be break-even, into a loss-making project. The proposal also requested the Municipality to foresee the necessary provision for 50 % of the losses. The proposal further mentions that due to the financial crisis SJB was not able to obtain the necessary financing for the development of the Damplein.
The Supplementary Agreement also states that SJB started the construction works on the Damplein on 7 July 2009 and that it had to undertake those works without interruption. The works should be finished by December 2011. In case of late delivery, SJB was to reimburse part of the decreased price. Delivery of the land would take place at the latest in mid-March 2010 and payment would take place at the latest on the day of delivery.
On 15 January 2010, SJB and Wooninvest Projecten BV, a company related to one of the project developers who signed the 2004 Co-operation Agreement, signed a purchase/construction agreement (“koop/aannemingsovereenkomst”) for the purchase of 43 housing units, which would be rented out to private persons by Wooninvest. In the case that SJB found a private purchaser for some of these housing units before 29 January 2010, the parties agreed that these units would not be sold to Wooninvest. The agreement also foresees a period between 29 January 2010 until the delivery of the units to Wooninvest during which SJB can repurchase the units sold to Wooninvest under the same conditions as they were sold to Wooninvest, plus compensation of the costs borne by Wooninvest and an interest of 6 % per year for the period between payment by Wooninvest to SJB and the redelivery of the units from Wooninvest to SJB (article 24).
By way of the opening decision, the Commission initiated the formal investigation procedure laid down in Article 108(2) TFEU in respect of the retroactive price decrease of the land and the waiver of the ground exploitation and quality fees by the PPP in favour of SJB (hereafter: the “contested measures”) on the grounds that these measures could entail State aid within the meaning of Article 107(1) TFEU and the Commission had doubts as to their compatibility with the internal market.
In particular, the Commission considered it unlikely that a hypothetical private vendor in a situation similar to that of the Municipality would have agreed to the same price reduction and waiver of fees as required by the market economy investor test (hereinafter: “MEIT”). By retroactively decreasing the sales price of the land it sold to SJB, the PPP and, therefore, the Municipality decided to carry the risk of a declining housing market. This behaviour is contrary to the Dutch authorities’ own assertion that the construction phase of the project was to be entirely at the risk and the expense of the private project developers, including SJB. Since the PPP, as the seller of the land, had no financial involvement in this phase of the project, there was no reason to believe that a hypothetical private seller in a similar situation as the Municipality would agree to retroactively lower an agreed sales price for a plot of land because the intended buyer had problems selling housing units it planned to build on that land. Nor did the waivers granted for the ground exploitation and quality fees seem to conform with the MEIT, as it was unlikely that a private investor would retroactively waive an agreed contribution to its costs without any consideration in return.
Finally, the Commission expressed its doubts as to whether the contested measures could fall within the scope of any of the exceptions laid down in Article 107 TFEU.
By letter dated 18 April 2012, the Dutch authorities submitted their comments to the Commission's opening decision.
The Dutch authorities specified that, contrary to what was suggested by the wording of Article 2.1.2 of the Supplementary Agreement, the Municipality had not waived the full amounts of the initially agreed ground exploitation fee and quality fee under the 2004 Co-operation Agreement, but rather only those fees that were due by SJB for the housing units to be built on the Damplein. According to the Dutch authorities, those fees amounted together to EUR 551 544 (value on1 January 2003, which would represent a total value of EUR 719 400 on 1 January 2010). To substantiate its position, the Dutch authorities referred to a proposal concerning the price decrease sent by the Municipality to its Council on 18 February 2009 and to a building programme annexed to the 2004 Co-operation Agreement which allocates a ground exploitation and quality fee of EUR 551 554 to the Damplein.
Decrease Damplein | value 1.1.2010 |
|---|---|
Value land | 8 622 480 |
Ground exploitation fee and quality fee | 719 400 |
Total land and fees | 9 341 880 |
Decreases agreed in 2006 and 2008 | -1 734 245 |
Reduced value | 7 607 635 |
Value supplementary agreement March 2010 | -4 000 000 |
Total decrease | 3 607 635 |
The Dutch authorities disagree that the contested measures qualify as State aid within the meaning of Article 107(1) TFEU. In essence, the Dutch authorities hold the view that the contested measures did not confer an advantage on SJB that it would not have obtained under normal market conditions.
Instead, the Dutch authorities are of the opinion that the Municipality acted in accordance with the MEIT, as the non-realisation of the Damplein Project would have had an effect on the entire Leidschendam Centrum Project and would have caused direct and indirect damages to the Municipality.
Direct damages during 2 years | PPP | municipality(50 %) |
|---|---|---|
Interest cost over a credit facility (5 % during 2 years outstanding amount on 01.01.2009 EUR 17 million) | 1 800 000 | 900 000 |
Temporary provision of fences, road signs and maintenance | 60 000 | 30 000 |
Provisions cost increase (indexation of 2.5 %) | 385 000 | 192 500 |
Extra planning costs i.e. costs related to the project office such as financial administration, insurance, etc. | 600 000 | 300 000 |
Maintenance deteriorated area | 50 000 | |
Total | 2 845 000 | 1 472 500 |
In addition, the Dutch authorities claim that the Municipality would have suffered indirect damage from such a delay consisting in the further deterioration of the public space, loss of confidence in the area by its inhabitants and future purchasers of real estate, costs for the re-destination of shops, damage claims from enterprises, maintenance costs, and changes of plans for the other sub-projects. Such delay could also mean the end of shopping facilities in the development area whose presence contributes to the habitability of the entire area. Already before the start of the project, around 23 % of the shops were vacant and, by 2010, 27 % were out of business. Without the necessary revitalisation, the entire area would further deteriorate.
The Dutch authorities are therefore of the opinion that the Municipality acted as a market economy private investor would, by taking into account the financial forecasts and trying to limit, in its own interest, the direct and indirect damages resulting from a further delay of the project. At the same time, it obtained a guarantee that construction works on the Damplein would be undertaken.
Second, the Dutch authorities submitted that the Municipality had acted as a private investor would by granting the contested measures in return for a commitment from SJB that it would waive its right to invoke the 70 % clause. The fact that SJB could no longer invoke the 70 % clause had an implication on the assumptions made in the initial valuation of the land in 2003 and the price agreed in the 2004 Co-operation Agreement. According to the Dutch authorities, the decrease in the sales price for the land and the waiver of the fees was the consideration which the Municipality had to pay so that SJB would agree to waive its right to invoke the 70 % clause. Without the Supplementary Agreement, SJB would not have started construction on the Damplein.
Should the Commission concludes that the contested measures qualify as State aid, the Dutch authorities contend that this aid would be compatible with the internal market, in accordance with Article 107(3)(c) TFEU.
The Dutch authorities claim that the Municipality had a public interest in the realisation of this project. As a large part of the land on the Damplein lay fallow and the area was deteriorating, the Municipality considered starting the constructions works on the Damplein as crucial not only for the development of the Damplein, but for the entire Leidschendam city centre. In particular, delaying the construction of the underground parking garage could jeopardise the realisation of the other sub-projects.
According to the Dutch authorities, the revitalisation of Leidschendam city centre contributes to the objective of economic and social cohesion, as laid down in Articles 3 and 174 TFEU. The revitalisation of the city centre makes efficient use of the scarce space available for new housing units, commercial facilities and underground parking in Leidschendam, while the amelioration of the public infrastructure contributes to the cohesion of the entire city centre.
The Dutch authorities contend that SJB could not be forced to start construction works on the Damplein due to the 70 % clause in the 2004 Co-operation Agreement. By the time SJB received a valid building permit, the credit crisis had had its effect on the Dutch real estate market, which made it even more unlikely that SJB would swiftly pre-sell 70 % of the free sector housing units. The 2004 Co-operation Agreement was therefore re-negotiated, since the Municipality considered it of the utmost importance to start the construction works on the Damplein. The Supplementary Agreement was therefore appropriate and necessary for the Municipality to achieve its goal of revitalising the Damplein.
In order for the Municipality to obtain an immediate start of the construction works, SJB had to give up it right to invoke the 70 % clause and had to start the construction works with the risk that the housing units might not be sold. Therefore, the previously agreed price was recalculated by SJB. Subsequently, this calculation was verified by an independent expert who declared the agreed price as market-conform.
According to the Dutch authorities, the fact that the price is declared market-conform by an independent expert indicates that the price decrease is proportionate. This would also imply that no overcompensation of SJB has taken place. The decrease in the price was the consideration which the Municipality had to pay so that SJB would agree to waive its right to invoke the 70 % clause. Without the Supplementary Agreement, SJB would not have started construction on the Damplein.
Furthermore, through its participation in the PPP, SJB will itself bear 50 % of the risks and the costs of the ground exploitation, thereby participating in the agreed decrease of the sales price. In order to arrive at break-even for the ground exploitation, it was decided that SJB should contribute EUR 2,6 million to the PPP (point 5.2.1 Ground Exploitation Masterplan Damcentrum) and, as the PPP bore 50 % of the costs of the school, 25 % of those costs is at the expense of SJB (EUR 0,7 million).
Finally, he Dutch authorities claim that the retroactive price decrease concerns the building of 67 housing units and 14 commercial premises which will be sold at market-conform prices valued by an independent expert. Therefore, the distortion of competition would be of a very local nature and would not outweigh the positive effects of the completion of the project.
Only the Stichting provided comments in response to the opening decision. The Stichting welcomes the opening decision, but is of the opinion that the contested measures described in this decision are part of a much wider aid operation and refers to its complaint and additional submissions. In particular, the Stichting refers to the alleged free transfer of land by the Municipality to the PPP.
The Stichting is of the opinion that the delay in the project was not due to the national court proceedings initiated by them, nor that the financial crisis delayed the sales of the housing units on the Damplein. According to the Stichting, there has been no market demand for the kind of housing units proposed for the Damplein ever since the beginning of the project in 2004.
According to the Stichting, the land was not valued by an independent expert, neither in 2003, nor in 2009.
The Dutch authorities stated that the set-up of the project by the Municipality has been transparent and described in the “Concept Masterplan Damcentrum”, approved on 6 April 2004. Only financially sensitive agreements or parts thereof were kept confidential.
Concerning the free transfer of land by the Municipality to the PPP, the Municipality explained that this is not part of the opening decision and referred to its submissions to the Commission in 2009, in which it explained that that transfer was not free of charge since the PPP provided services in return for it. In its earlier submissions, the Municipality stressed that the works carried out by the PPP should normally have been borne by the Municipality.
According to the Dutch authorities, both the different legal procedures initiated by the Stichting, which generated a lot of negative publicity for the project, and the credit crisis had a negative effect on the sales of housing units on the Damplein. However, when initial sales started in 2007, almost a third of the housing units were sold. These sales agreements were later cancelled due to the late delivery of the necessary building permits. It can therefore be concluded that there was a demand for these units at the beginning of the project.
The Dutch authorities further note that the independent experts were selected by the Municipality, which had no interest in obtaining a low value for the land.
Article 107(1) TFEU provides that: “any aid granted by a Member State or through State resources in any form whatsoever which distorts or threatens to distort competition by favouring certain undertakings or the production of certain goods shall, in so far as it affects trade between Member States, be incompatible with the internal market”.
First, it has not been challenged that SJB as well as Schouten de Jong and Bouwfonds, the members of this partnership, qualify as undertakings for the purpose of this provisions, since they pursue economic activities offering goods and services on the market, as indicated in the opening decision.
Second, the contested measures were granted by the PPP, which means with the necessary agreement of the Municipality, which holds a 50 % stake in the PPP. Since the decision-making of the PPP is by unanimity and these measures could not have been agreed to without the express approval of the Municipality’s Council, the decision to grant the contested measures by the PPP are imputable to the State. Furthermore, had the Municipality not agreed to grant the contested measures, the extent of its financial exposure resulting from the PPP would have been proportionally lower. Therefore, the price decrease and waived fees agreed to by the PPP imply a loss of State resources.
Third, since the measures benefit only SJB and, ultimately, Schouten de Jong and Bouwfonds, the members of this partnership, they must be considered as selective in nature.
However, the Dutch authorities have challenged the contention that the Municipality, by agreeing to a reduction in the initially agreed sales price for the land sold to SJB and a waiver of fees, conferred an economic advantage on SJB which it would not have otherwise obtained under normal market conditions. It also challenges the contention that the contested measures distort competition and affect intra-Union trade.
For the reasons set out in recitals 69 to 89 below, the Commission disagrees with the Dutch authorities on these points.
In the present case, no unconditional bidding procedure was organised. While an expert valuation was made in March 2003 to establish the sales prices laid down in the 2004 Co-operation Agreement, the price agreed with SJB for the purchase of the land on the Damplein was subsequently decreased and the fees earlier agreed were waived in 2010 as a result of the Supplementary Agreement.
As regards the expert valuation of February 2009 referred to in recital (30) above, the Commission considers the residual value method used in that ex post assessment inappropriate to calculate the market value of the land sold to SJB, since the expected decrease in revenues from the sale of the housing units would be entirely absorbed by the price of the land. To calculate the value of land, the residual value method starts from the sales price of the housing units. From this price, the construction costs and a profit and risk provision are deducted. What is left is the residual value of the land. It is clear that in a declining housing market such as that in casu the residual value method shifts the deceasing value of real estate entirely to the value of the land. In theory, this could even result in a negative value for the land.
Finally, the Dutch authorities claim that the Municipality, by agreeing to the contested measures, acted in accordance with the MEIT; that is, that a hypothetical private vendor in the same situation as the Municipality would have agreed to the same price reduction and fee waivers, so as to preclude the existence of an advantage as a result of the contested measures. First, according to the Dutch authorities, the Municipality had an important financial and social interest in starting the construction works on the Damplein as soon as possible, since further delays would lead to direct and indirect damages for the Municipality and these damages would be higher than the costs for the Municipality to agree to the contested measures. Second, the Dutch authorities contend that the Municipality behaved as a private investor by accepting a commitment from SJB to waive its right to invoke the 70 % clause of the 2004 Co-operation Agreement in return for the contested measures.
The Commission does not accept this reasoning. As a preliminary matter, the Commission recalls that the Municipality was only involved in the ground exploitation phase of the real estate project, while the construction phase of the project was at the risk and the expense of the private developers concerned, including SJB (see recitals 13 and 16 above). It is unlikely that a private investor, operating in normal competitive conditions, would have decided to take on the risk of a declining housing market from SJB, which it was previously not exposed to, by agreeing to a reduction in the initially agreed sales price for that land and a waiver of fees, without a clear financial compensation that would outweigh the losses stemming from that decision. As explained in recitals 75 to 86 below, neither the fact that the Municipality would suffer damages as a result of further delays, nor the fact that SJB decided to waive its right to invoke the 70 % clause, leads the Commission to a different conclusion in its application of the MEIT to the Municipality’s actions.
As regards the direct damages the Municipality would allegedly suffer from further delays to the Damplein Project, the Commission notes that the costs estimated by the Dutch authorities in Table 2 above all relate to the ground exploitation phase of the entire Leidschendam Centrum Project. Assuming it would take at least another two years for SJB to start construction, the Dutch authorities estimated the reduced revenues for the PPP from the sale of the land to SJB, as well as assumed similar delays for the rest of the Leidschendam Centrum Project, to result in interest costs of approximately EUR 1,8 million on an outstanding loan of the PPP for the ground exploitation phase of the entire Leidschendam Centrum Project. A two year delay would also lead to extra planning and other costs of approximately EUR 1 million for the entire Leidschendam Centrum Project.
In any event, even if the alleged direct costs referred to by the Dutch authorities could be taken into account to support the Municipality’s decision to grant the contested measure, which the Commission contests, its calculations of these costs are nevertheless flawed. First, the interest costs are calculated in relation to a credit facility granted to the PPP covering the entire Leidschendam Centrum Project and not just the Damplein Project, which is but one of eight sub-projects. Similarly, the extra planning costs are calculated for the entire Leidschendam Centrum Project. It can therefore not be assumed that in the case that the Damplein Project would have been realised, all the other sub-projects would also have been realised, and thus that none of these interest costs would have been incurred.
Third, the outstanding credit facility, and therefore the interest costs, would have been much lower in the case that payment would have been made on the date and for the amount as foreseen in the 2004 Co-operation Agreement.
Fourth, it is clear that, even in the calculations submitted by the Dutch authorities, the financial consequences of granting the contested measures for the PPP, estimated at approximately EUR 3,6 million, outweigh the alleged direct costs of further delaying construction of the real estate on the Damplein by SJB, estimated by the Dutch authorities at approximately EUR 2,8 million.
Finally, as regards the alleged indirect costs of delaying the project by a further two years, the Dutch authorities have not quantified these damages so that it is impossible for the Commission to verify them.
As regards SJB’s commitment to waive its right to invoke the 70 % clause, the Commission notes at the outset that this clause, which also applied to the other private developers involved in the Leidschendam Centrum Project, is not uncommon in the Netherlands. By agreeing to this clause, the Municipality accepted that the start of the actual construction of the free sector housing units would be determined by the success of the private project developers, including SJB, in pre-selling the housing units. This follows from the fact that the Municipality was only involved in the ground exploitation phase of the project, whereas the construction phase was carried out at the risk and the expense of the private developers. If the Municipality had indeed had an interest in a prompt start of the construction works, it was free, when negotiating the sale agreements with private developers in 2004, either not to agree to the 70 % clause in the contract or to incorporate penalties in case the construction phase would not be started and/or finished at a defined date.
It should also be noted that the 70 % clause in the 2004 Co-operation Agreement was limited to the free sector housing units and did not include the construction of the commercial premises or the underground parking garage, whereas SJB refused to start any construction on the Damplein. In those circumstances, it is quite likely that a private investor, operating in normal competitive conditions and having an interest in the completion of the entire real estate project, would have requested SJB to fulfil its contractual obligations as regards the construction of the commercial premises and the underground parking garage. Even if the claim of SJB that these works could not be started because the different components of the real estate project would be technically linked was correct, this risk would be for SJB to bear, since it was solely responsible for the construction phase of the project. There is therefore no reason to believe that a private investor, operating in normal competitive conditions, would take over this risk from SJB.
In this regard, it should further be recalled that, as regards the construction of the public part of the underground parking garage, the PPP had already decided to grant these works to SJB in 2004 for the lump sum of maximum EUR 4,6 million (value on 1 January 2003), without organising a public tender. There were therefore no financial reasons for SJB to refuse to start construction works on the parking garage and therefore no reasons for a private investor, operating in normal competitive conditions, to accept any further delays by making the construction of the parking garage dependent on the sale of the free sector housing units by SJB.
It is therefore unlikely that a private investor, operating in normal competitive conditions, would have agreed to the contested measures in the manner the Municipality did without having first explored other commercially more attractive options, such as annulling the 2004 Co-operation Agreement, and claiming damages for the delay from SJB and putting out a call for tender. The Dutch authorities have provided no evidence that the PPP made any such assessment of its options.
It can therefore be concluded that the contested measures confer an advantage on SJB and that they are not in line with the MEIT, as the Dutch authorities have not established that a hypothetical private seller, operating under normal market conditions, would have agreed to these measures.
Since the contested measures meet all the criteria of Article 107(1) TFEU, the Commission concludes that these measures constitute State aid within the meaning of that provision. Moreover, since this aid was granted to the beneficiaries without the prior notification to and authorisation from the Commission as required by Article 108(3) TFEU, the contested measures constitute unlawful aid.
Having established that the contested measures constitute State aid within the meaning of Article 107(1) TFEU, it is necessary to examine the Dutch authorities’ claim that these measures are compatible with the internal market on the basis of Article 107(3)(c) TFEU.
Article 107(3)(c) TFEU provides that aid may be considered compatible with the internal market where it facilitates the development of certain economic activities or of certain economic areas, so long as it does not adversely affect trading conditions to an extent contrary to the common interest.
When examining whether aid is compatible under Article 107(3)(c) TFEU, the Commission thus takes into account whether the aid is aimed at a well-defined objective of common interest, as well as whether it is appropriate and proportionate to achieve that objective, and whether it causes undue distortions of competition.
According to the Dutch authorities, the revitalisation of Leidschendam city centre contributes to economic and social cohesion, as laid down in Articles 3 and 174 TFEU, and without the contested measures SJB would not have started the construction works on the Damplein and the entire Leidschendam Centrum Project would have been jeopardised.
The Commission, however, is not convinced by this line of reasoning. On the one hand, the Dutch authorities have not established that the Damplein is a deprived urban area which suffers from market failure and that the market alone would not have decided to undertake the envisaged reconstruction of the Damplein. On the contrary, when the project was launched, several private developers, including SJB, were apparently willing to participate in the construction phase of the project at their own commercial risk and expense, as laid down in the 2004 Co-operation Agreement.
On the other hand, by concluding the 70 % clause in the 2004 Co-operation Agreement, the Municipality subordinated its interest in achieving the alleged objective of revitalising Leidschendam city centre to the commercial interest of SJB in case it would not be able to pre-sell 70 % of the planned housing units in advance of construction. The Municipality is therefore no longer in a position to argue that the contested measures, agreed to in 2010 on the condition that SJB committed to waive its right to invoke this clause, sought to attain a common interest objective.
Even if it could be accepted that the contested measures sought to achieve the revitalisation of Leidschendam city centre, the Dutch authorities have not shown that those measures were an appropriate means to achieve that objective.
Indeed, it appears from the information provided that the other private developers involved in the Leidschendam Centrum Project also asked the PPP to decrease the initial sales price agreed for the land because of the difficulties they faced on the declining real estate market, but that the Municipality, rather than agreeing to such a decrease or a waiver of fees, considered amendments in the initial planning and development provisions to adapt to the changed demand on the market.
This demonstrates that other, more appropriate measures, which are better suited and less distortive of competition, were available to the Municipality to achieve the intended objective of revitalising Leidschendam city centre in light of the changed economic circumstances.
The Dutch authorities consider the contested measures proportionate to the intended objective of revitalising Leidschendam city centre since, in return for a price decrease and waiver of the fees, SJB agreed to waive its right to rely on the 70 % clause. Furthermore, the Dutch authorities consider the contested measures proportionate since SJB contributed financially to the ground exploitation phase. In particular, SJB paid a financial contribution of around EUR 2,6 million to the PPP and bore, via the PPP, 25 % of the costs for the school to be built in another sub area of the Leidschendam Centrum Project.
The Commission cannot follow this reasoning. Article 107(3)(c) requires that the aid measures must be proportionate to the intended objectives, not that there must be adequate trade-off between the aid that is granted and any concessions made by the beneficiaries to acquire that aid. Thus, the fact that SJB agreed to waive its right to rely on the 70 % clause in return for the price decrease and the fee waivers is of no relevance for the assessment into the proportionality of the contested measures. The same goes for any financial contributions SJB might have made to the ground exploitation phase.
The Dutch authorities have therefore failed to demonstrate that the contested measures were proportionate to the intended objective of common interest.
Finally, the Dutch authorities contest that the contested measures unduly distorts competition, arguing that the positive effects of promptly completing the project outweigh the negative effects of the contested measures.
The Dutch authorities have, however, not substantiated this argument. On the contrary, as stated in recital 80 above, according to the Dutch authorities, a further delay in the contested real estate project would result in a cost of EUR 2,8 million for the PPP, while the agreed price decreases would amount to EUR 3,6 million. The Commission therefore concludes that the Dutch authorities have not demonstrated that the positive effects of completing the contested real estate project outweigh the negative effects of granting the contested measures.
Based on the considerations set out in recitals 93 to 103 above, the Commission concludes that the aid granted by the Municipality in favour of SJB by way of the contested measures is not compatible with the internal market on the basis of Article 107(3)(c) TFEU.
As explained in the section above, the contested measures constitute State aid within the meaning of Article 107(1) TFEU and cannot be considered compatible with the internal market. Moreover, since this aid was granted to the beneficiaries without the prior notification to and authorisation from the Commission as required by Article 108(3) TFEU, the contested measures constitute unlawful aid.
As a result of the contested measures, SJB paid a lower price for the land on the Damplein than it had initially agreed under the 2004 Co-operation Agreement and was no longer required to pay the ground exploitation and quality fees it had also agreed to. Thus, to quantify the amount of illegal aid received by SJB, it is necessary to determine the amount of the price decrease and the value of the fees waived.
The advantage accruing to SJB as a result of the reduction in sales price for the land on the Damplein therefore corresponds to approximately EUR 4,6 million.
The claim of the Dutch authorities that the decrease of the sales price was less than EUR 4,6 million because the PPP had already decreased the initially agreed sales price of EUR 7,2 million in 2006 and in 2008 (see Table 1 above) cannot be accepted, as no evidence has been provided that these reductions were formalised by way of an agreement or that they led to an amendment of the initial sales price in the 2004 Co-operation Agreement.
The Commission further notes that the alleged 2006 reduction would run counter to the 2004 Co-operation Agreement, which clearly lays down minimum land prices and only foresees in an additional payment where more floor space could be achieved.
Finally, the Commission notes that both the alleged reduction in 2006, which was said to be due to the fact that less commercial space could be realised than initially foreseen, and the alleged reduction in 2008, which apparently related to delays in the construction permit for SJB, were granted under the condition that SJB would receive a building permit by 1 October 2008. This condition was apparently not fulfilled since, according to the Dutch authorities, SJB received the building permit only in November 2008.
The Commission therefore concludes that the amount of the aid granted to SJB by the PPP as a result of the decrease in the sales price originally agreed in the 2004 Co-operation Agreement amounts to approximately EUR 4,6 million (see amount in Table 3 below).
As a result of the Supplementary Agreement, the fees as agreed under the 2004 Co-operation Agreement were no longer due as regards SJB. Thus, the amount of aid granted to SJB as a result of the waiver by the PPP of these fees amounts to approximately EUR 2,3 million (see Table 3 below).
The Dutch authorities contend that, in spite of the wording of the Supplementary Agreement, the PPP had only waived the fees related to the Damplein Project, representing a total amount of approximately EUR 0,6 million (value on 1 January 2003). To substantiate their position, the Dutch authorities refer to the building programme annexed to the 2004 Co-operation Agreement which allocates a ground exploitation fee and a quality fee of approximately EUR 0,6 million (value on 1 January 2003) to the Damplein and mentions a total ground exploitation fee and quality fee of approximately EUR 2 million (value on 1 January 2003) to be paid by SJB for the entire Leidschendam Centrum Project. Reference was also made to a proposal from the Municipality sent to its Council on 18 February 2009, which mentioned that the lowering of the fees would have a negative effect, at that moment in time, of approximately EUR 0,7 million on the result of the ground exploitation project.
The Commission does not consider it possible, however, to conclude on the basis of the building programme or on the basis of the proposal sent to the Council that the waiver of the fees related exclusively to the Damplein Project. In any event the wording of the Supplementary Agreement does not limit the waiver of the fees to the Damplein Project. The Dutch authorities have also not been able to provide any evidence that SJB actually paid all fees due for all housing units of the Leidschendam Centrum Project on 1 July 2004, as it was obliged to do under Article 10.3 of the 2004 Co-operation Agreement.
Co-operation agreement 2004 | Supplementary agreement March 2010 | Decrease | ||
|---|---|---|---|---|
Value 1.1.2003 | value 1.1.2010 | value 1.1.2010 | value 1.1.2010 | |
Land price | 7 253 793 | 8 622 480 | 4 000 000 | 4 622 480 |
Ground exploitation fee | 1 077 941 | 1 281 333 | 0 | 1 281 333 |
Quality fee | 856 667 | 1 018 308 | 0 | 1 018 308 |
Total | 9 188 401 | 10 922 121 | 4 000 000 | 6 922 121 |
As explained in Table 3 above, the incompatible aid element of the measures should be calculated as EUR 6 922 121, consisting of the retroactive decrease of the sales price of the land (EUR 4 622 480), and the waiver of the ground exploitation fee (EUR 1 281 333) and the quality fee (EUR 1 018 308).
The aid was granted to SJB on 1 March 2010. The aid to be recovered shall bear recovery interest for the period between 1 March 2010 until the date at which it will be effectively repaid.
HAS ADOPTED THIS DECISION:
Article 1
The State aid amounting to EUR 6 922 121, unlawfully granted by the Netherlands on 1 March 2010, in breach of Article 108(3) of the Treaty on the Functioning of the European Union, in favour of Schouten-de Jong Bouwfonds, a partnership consisting of Schouten & De Jong Projectontwikkeling BV and Bouwfonds Ontwikkeling BV, in the form of a retroactive decrease of the sales price of land and a retroactive decrease of the agreed ground exploitation fee and quality fee agreed by the municipality of Leidschendam-Voorburg, is incompatible with the internal market.
Article 2
1.
The Netherlands shall recover the incompatible aid referred to in Article 1 from Schouten-de Jong Bouwfonds and/or Schouten & De Jong Projectontwikkeling BV and/or Bouwfonds Ontwikkeling BV.
2.
The sums to be recovered shall bear interest from the date on which they were put at the disposal of Schouten-de Jong Bouwfonds and/or Schouten & De Jong Projectontwikkeling BV and/or Bouwfonds Ontwikkeling BV, namely 1 March 2010 until their actual recovery.
3.
Article 3
1.
Recovery of the aid referred to in Article 1 shall be immediate and effective.
2.
The Netherlands shall ensure that this Decision is implemented within four months following the date of notification of this Decision.
Article 4
1.
Within two months following the date of notification of this Decision, the Netherlands shall submit the following information:
(a)
the total amount (principal and recovery interests) to be recovered from the beneficiaries;
(b)
a detailed description of the measures already taken and planned to comply with this Decision;
(c)
documents demonstrating that the beneficiaries have been ordered to repay the aid.
2.
The Netherlands shall keep the Commission informed of the progress of the national measures taken to implement this Decision until recovery of the aid referred to in Article 1 has been completed. It shall immediately submit, on simple request by the Commission, information on the measures already taken and planned to comply with this Decision. It shall also provide detailed information concerning the amounts of aid and recovery interest already recovered from the beneficiaries referred to in Article 1.
Article 5
This Decision is addressed to the Kingdom of the Netherlands.
Done at Brussels, 23 January 2013.
For the Commission
Joaquín Almunia
Vice-president