Annex I to Regulation (EC) No 715/2009 is amended as follows:
point 2.2 is replaced by the following:
for at least three firm capacity products with a duration of one month or
for at least two firm capacity products with a duration of one quarter or
for at least one firm capacity product with a duration of one year or more or
where no firm capacity product with a duration of one month or more has been offered.
Transmission system operators shall accept any surrender of firm capacity which is contracted by the network user at an interconnection point, with the exception of capacity products with a duration of a day and shorter. The network user shall retain its rights and obligations under the capacity contract until the capacity is reallocated by the transmission system operator and to the extent the capacity is not reallocated by the transmission system operator. Surrendered capacity shall be considered to be reallocated only after all the available capacity has been allocated. The transmission system operator shall notify the network user without delay of any reallocation of its surrendered capacity. Specific terms and conditions for surrendering capacity, in particular for cases where several network users surrender their capacity, shall be approved by the national regulatory authority.
the network user uses less than on average 80 % of its contracted capacity both from 1 April until 30 September and from 1 October until 31 March with an effective contract duration of more than one year for which no proper justification could be provided; or
the network user systematically nominates close to 100 % of its contracted capacity and renominates downwards with a view to circumventing the rules laid down in point 2.2.3(3).
point 3.1.1(1) is amended as follows:
point (e) is replaced by the following:
in a downloadable format that has been agreed between transmission system operators and the national regulatory authorities — on the basis of an opinion on a harmonised format that shall be provided by the Agency — and that allows for quantitative analyses;’;
the following point (h) is added:
all data shall be made available as of 1 October 2013 on one Union-wide central platform, established by ENTSOG on a cost-efficient basis.’;
in point 3.3(1) the following points (h), (i), (j), (k) and (l) are added:
occurrence of unsuccessful, legally valid requests for firm capacity products with a duration of one month or longer including the number and volume of the unsuccessful requests; and
in the case of auctions, where and when firm capacity products with a duration of one month or longer have cleared at prices higher than the reserve price;
where and when no firm capacity product with a duration of one month or longer has been offered in the regular allocation process;
total capacity made available through the application of the congestion-management procedures laid down in points 2.2.2, 2.2.3, 2.2.4 and 2.2.5 per applied congestion-management procedure;
points (h) to (k) shall apply from 1 October 2013.’.