- Latest available (Revised)
- Original (As adopted by EU)
When the UK left the EU, legislation.gov.uk published EU legislation that had been published by the EU up to IP completion day (31 December 2020 11.00 p.m.). On legislation.gov.uk, these items of legislation are kept up-to-date with any amendments made by the UK since then.
Legislation.gov.uk publishes the UK version. EUR-Lex publishes the EU version. The EU Exit Web Archive holds a snapshot of EUR-Lex’s version from IP completion day (31 December 2020 11.00 p.m.).
This is the original version as it was originally adopted in the EU.
This legislation may since have been updated - see the latest available (revised) version
1.For the purposes of the determination of start-up and shut-down periods in the permit of the installation comprising the combustion plant, the measures referred to in Article 14(1)(f) of Directive 2010/75/EU shall include:
(a)at least one of the following:
the end point of the start-up period and the start point of the shut-down period expressed as load thresholds, in accordance with Articles 6, 7 and 8 and considering that the minimum shut-down load for stable generation may be lower than the minimum start-up load for stable generation as the combustion plant may be able to operate stably at a lower load once it has reached a sufficient temperature following a period of operation;
discrete processes or thresholds for operational parameters, which are associated with the end of the start-up period, and with the start of the shut-down period, and which are clear, easily monitored and applicable to the technology used, as set out in Article 9;
(b)measures ensuring that the start-up and shut-down periods are minimised as far as practicable;
(c)measures ensuring that all abatement equipment is brought into operation as soon as is technically practicable.
For the purposes of the first subparagraph, account shall be taken of the technical and operational characteristics of the combustion plant and its units, and the technical requirements for operating the abatement techniques installed.
2.If any aspects relating to the plant that affect start-up and shut-down periods change, including the installed equipment, fuel type, plant role in the system and installed abatement techniques, the permit conditions related to start-up and shut-down periods shall be reconsidered and, if necessary, updated by the competent authority.
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As adopted by EU): The original version of the legislation as it stood when it was first adopted in the EU. No changes have been applied to the text.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: