This version of this Decision was derived from EUR-Lex on IP completion day (31 December 2020 11:00 p.m.). It has not been amended by the UK since then. Find out more about legislation originating from the EU as published on legislation.gov.uk.![]()
Revised legislation carried on this site may not be fully up to date. At the current time any known changes or effects made by subsequent legislation have been applied to the text of the legislation you are viewing by the editorial team. Please see ‘Frequently Asked Questions’ for details regarding the timescales for which new effects are identified and recorded on this site.
The applicant shall provide all the required information calculated, measured or tested for the period immediately before the application. Measurements shall be representative for the respective series of testing and it should be consistent for all parts of the application as appropriate.
The expression ‘confined waterbed’ identifies an artesian waterbed.
The average flow of the watercourse that interferes with the quarry shall be calculated taking into account the authorised area of the considered quarry. The calculation shall be made multiplying the section of the water body by the velocity of the water. The values shall be representative of at least 12 months.
See A3.
The calculation of I.2 consists of the measurement of the affected area, which includes quarry front and active dump areas, and of the authorised area. These areas should be measured during operating activities.
The calculation of I.3 consists of the evaluation of the usable material and of the total volume extracted yearly. Usable material refers to all the volume which can be used in any process: for example, commercial blocks, aggregate materials, everything else suitable for further processing and use.
This indicator is described in Council Directive 1999/30/EC(1). The calculation of I.4 consists of the measurement, along the border of quarry area, of PM 10 suspended particles based on the specific requirements of the test method and the general provisions of that Directive (PM 10 are defined in Article 2(11)). The test method is defined in EN 12341.
This indicator considers the total emissions of suspended solids after treatment on surface water flowing out of the quarry site. The calculation of I.5 consists of the measurement of total suspended solids using the test method reported in ISO 5667-17.
This indicator considers the noise level recorded along the border of the quarry area. Non-impulsive noises are to be measured. The calculation of I.6 consists in the measurement of the noise using the test method reported in ISO 1996-1.
According to the European Soil Bureau's indication, land is graded on the basis of its potentialities and the severity of its limitations for crop growth into eight capability classes. An indicative description of the classes is as follows:
Class I soils have slight limitations that restrict their use,
Class II soils have moderate limitations that reduce the choice of plants or require moderate conservation practices,
Class III soils have severe limitations that reduce the choice of plants or require special conservation practices, or both,
Class IV soils have very severe limitations that restrict the choice of plants or require very careful management, or both,
Class V soils have little or no hazard of erosion but have other limitations, impractical to remove, that limit their use mainly to pasture, range, forest land, or wildlife food and cover,
Class VI soils have severe limitations that make them generally unsuited to cultivation and that limit their use mainly to pasture, range, forest land, or wildlife food and cover,
Class VII soils have very severe limitations that make them unsuited to cultivation and that restrict their use mainly to grazing, forest land, or wildlife,
Class VIII soils and miscellaneous areas have limitations that preclude their use for commercial plant production and limit their use to recreation, wildlife, or water supply or for aesthetic purposes.
‘Closed loop recycling’ means recycling a waste product into the same kind of product; for ‘secondary material’ arising from a manufacturing process (such as leftovers or remnants), ‘closed loop recycling’ means that the materials are used again in the same process.
The calculation of the water recycling ratio shall be consistent with the following formula based on the flows highlighted in Figure A1.
For waste water is meant only the water used in processing plants, not comprehensive of the fresh water coming from rain and subsoil water.
When providing a calculation of process energy requirement (PER) or energy requirement for firing (ERF), the correct energy carriers shall be taken into account for the entire plant or for the firing stage only. Gross calorific values (high heat value) of fuels shall be used to convert energy units to MJ (Table A1). In case of use of other fuels, the calorific value used for the calculation shall be mentioned. Electricity means net imported electricity coming from the grid and internal generation of electricity measured as electric power.
Evaluation of PER for agglomerated stone production shall consider all energy flows entering the production plant both as fuels and electricity.
Evaluation of PER for terrazzo tiles production must consider all energy flows entering the production plant both as fuels and electricity.
Evaluation of ERF for ceramic tile production shall consider all energy flows entering all the kilns as fuels for the firing stage.
Evaluation of ERF for clay tile production shall consider all energy flows entering all the kilns as fuels for the firing stage.
Evaluation of PER for cement production shall consider all energy flows entering the production system both as fuels and electricity.
Table for calculation of PER or ERF (see text for explanations)
| Production period | Days | From | To | |
|---|---|---|---|---|
| Production (kg) | ||||
| Fuel | Quantity | Units | Conversion factor | Energy (MJ) |
| Natural gas | kg | 54,1 | ||
| Natural gas | Nm3 | 38,8 | ||
| Butane | kg | 49,3 | ||
| Kerosene | kg | 46,5 | ||
| Gasoline | kg | 52,7 | ||
| Diesel | kg | 44,6 | ||
| Gas oil | kg | 45,2 | ||
| Heavy fuel oil | kg | 42,7 | ||
| Dry steam coal | kg | 30,6 | ||
| Anthracite | kg | 29,7 | ||
| Charcoal | kg | 33,7 | ||
| Industrial coke | kg | 27,9 | ||
| Electricity (from net) | kWh | 3,6 | ||
| Total energy | ||||
| Specific energy consumption (MJ/kg of product) | ||||
The fresh water specific consumption shall be calculated as follows:
CWp-a = (Wp + Wa)/Pt
=
fresh water specific consumption. The results are expressed in m3/tonnes, equivalent to l/kg;
=
total stored production in tonnes;
=
water from wells and intended for exclusive industrial use (excluding water form wells for domestic use, irrigation and any other non-industrial use), in m3;
=
water from aqueduct and intended for exclusive industrial use (excluding water form aqueduct for domestic use, irrigation and any other non-industrial use) in m3.
The system boundaries are intended from raw materials to firing operation.
The air pollutant emission factors shall be calculated as follows:
the concentration in the exhaust gas emitted to the environment of each parameter considered in the tables shall be calculated,
the measurements used for the calculation must be made following the testing methods indicated in the tables,
the samplings shall be representative of the considered production.
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As adopted by EU): The original version of the legislation as it stood when it was first adopted in the EU. No changes have been applied to the text.
Geographical Extent: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.
Show Timeline of Changes: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
This timeline shows the different versions taken from EUR-Lex before exit day and during the implementation period as well as any subsequent versions created after the implementation period as a result of changes made by UK legislation.
The dates for the EU versions are taken from the document dates on EUR-Lex and may not always coincide with when the changes came into force for the document.
For any versions created after the implementation period as a result of changes made by UK legislation the date will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. For further information see our guide to revised legislation on Understanding Legislation.
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: