Revised legislation carried on this site may not be fully up to date. At the current time any known changes or effects made by subsequent legislation have been applied to the text of the legislation you are viewing by the editorial team. Please see ‘Frequently Asked Questions’ for details regarding the timescales for which new effects are identified and recorded on this site.
14. Conformity to type based on internal production control plus supervised vessel checks at random intervals is a conformity assessment procedure whereby the manufacturer fulfills the obligations laid down in paragraphs 15 to 17, and it is the manufacturer's sole responsibility to ensure and declare that the vessels concerned are in conformity with the type described in the [F1Type] examination certificate and satisfy the applicable requirements of these Regulations.
Extent Information
E1This version of this provision extends to England and Wales and Scotland only; a separate version has been created for Northern Ireland only
Textual Amendments
F1Word in Sch. 2 substituted (E.W.S.) (31.12.2020) by The Product Safety and Metrology etc. (Amendment etc.) (EU Exit) Regulations 2019 (S.I. 2019/696), reg. 1, Sch. 21 para. 40(e) (with Sch. 21 para. 37) (as amended by S.I. 2020/676, regs. 1(1), 2); 2020 c. 1, Sch. 5 para. 1(1)
14. Conformity to type based on internal production control plus supervised vessel checks at random intervals is a conformity assessment procedure whereby the manufacturer fulfills the obligations laid down in paragraphs 15 to 17, and it is the manufacturer's sole responsibility to ensure and declare that the vessels concerned are in conformity with the type described in the EU-type examination certificate and satisfy the applicable requirements of these Regulations.
Extent Information
E5This version of this provision extends to Northern Ireland only; a separate version has been created for England and Wales and Scotland only
15.—(1) The manufacturer must take all measures necessary so that the manufacturing process and its monitoring ensure conformity of the manufactured vessels with the type described in the [F1Type] examination certificate and with the applicable requirements of these Regulations.
(2) Before commencing manufacture, the manufacturer must provide [F2an approved] body of his choice with all necessary information, and in particular—
(a)the technical documentation referred to in paragraph 2(2)(c), together with —
(i)the certificates relating to the suitable qualification of the welding operations and of the welders or welding operators;
(ii)the inspection slip for the materials used in the manufacture of parts and components contributing to the strength of the vessel; and
(iii)a report on the examination and tests performed;
(b)the [F1Type] examination certificate;
(c)a document describing the manufacturing processes and all of the predetermined systematic measures taken to ensure conformity of the vessels with the type described in the [F1Type] examination certificate, which document must include—
(i)a description of the means of manufacture and checking appropriate to the construction of the vessels;
(ii)an inspection document describing the appropriate examinations and tests to be carried out during manufacture, together with the procedures in respect thereof and the frequency with which they are to be performed;
(iii)an undertaking to carry out the examinations and tests in accordance with the inspection document and to ensure that a hydrostatic test or, subject to the agreement of the relevant authorities, a pneumatic test is carried out on each vessel manufactured at a test pressure equal to 1.5 times the design pressure; and
(iv)the addresses of the places of manufacture and storage and the date on which manufacture is to commence.
(3) The examinations and tests referred to in paragraph 15(2)(c)(iii) must be—
(i)carried out under the responsibility of qualified staff who are independent of production personnel; and
(ii)the subject of a report.
(4) The [F3approved] body must, before the date on which any manufacture begins, examine the documents referred to in paragraphs 15(2)(a) and (c) in order to certify their conformity with the [F1Type] examination certificate.
Extent Information
E2This version of this provision extends to England and Wales and Scotland only; a separate version has been created for Northern Ireland only
Textual Amendments
F1Word in Sch. 2 substituted (E.W.S.) (31.12.2020) by The Product Safety and Metrology etc. (Amendment etc.) (EU Exit) Regulations 2019 (S.I. 2019/696), reg. 1, Sch. 21 para. 40(e) (with Sch. 21 para. 37) (as amended by S.I. 2020/676, regs. 1(1), 2); 2020 c. 1, Sch. 5 para. 1(1)
F2Words in Sch. 2 para. 15(2) substituted (E.W.S.) (31.12.2020) by The Product Safety and Metrology etc. (Amendment etc.) (EU Exit) Regulations 2019 (S.I. 2019/696), reg. 1, Sch. 21 para. 40(b) (with Sch. 21 para. 37) (as amended by S.I. 2020/676, regs. 1(1), 2); 2020 c. 1, Sch. 5 para. 1(1)
F3Words in Sch. 2 substituted (E.W.S.) (31.12.2020) by The Product Safety and Metrology etc. (Amendment etc.) (EU Exit) Regulations 2019 (S.I. 2019/696), reg. 1, Sch. 21 para. 40(c) (with Sch. 21 para. 37) (as amended by S.I. 2020/676, regs. 1(1), 2); 2020 c. 1, Sch. 5 para. 1(1)
15.—(1) The manufacturer must take all measures necessary so that the manufacturing process and its monitoring ensure conformity of the manufactured vessels with the type described in the EU-type examination certificate and with the applicable requirements of these Regulations.
(2) Before commencing manufacture, the manufacturer must provide a notified body of his choice with all necessary information, and in particular—
(a)the technical documentation referred to in paragraph 2(2)(c), together with —
(i)the certificates relating to the suitable qualification of the welding operations and of the welders or welding operators;
(ii)the inspection slip for the materials used in the manufacture of parts and components contributing to the strength of the vessel; and
(iii)a report on the examination and tests performed;
(b)the EU-type examination certificate;
(c)a document describing the manufacturing processes and all of the predetermined systematic measures taken to ensure conformity of the vessels with the type described in the EU-type examination certificate, which document must include—
(i)a description of the means of manufacture and checking appropriate to the construction of the vessels;
(ii)an inspection document describing the appropriate examinations and tests to be carried out during manufacture, together with the procedures in respect thereof and the frequency with which they are to be performed;
(iii)an undertaking to carry out the examinations and tests in accordance with the inspection document and to ensure that a hydrostatic test or, subject to the agreement of the relevant authorities, a pneumatic test is carried out on each vessel manufactured at a test pressure equal to 1.5 times the design pressure; and
(iv)the addresses of the places of manufacture and storage and the date on which manufacture is to commence.
(3) The examinations and tests referred to in paragraph 15(2)(c)(iii) must be—
(i)carried out under the responsibility of qualified staff who are independent of production personnel; and
(ii)the subject of a report.
(4) The notified body must, before the date on which any manufacture begins, examine the documents referred to in paragraphs 15(2)(a) and (c) in order to certify their conformity with the EU-type examination certificate.
Extent Information
E6This version of this provision extends to Northern Ireland only; a separate version has been created for England and Wales and Scotland only
16.—(1) The [F3approved] body must carry out vessel checks, or ensure that vessel checks are carried out, on random samples at random intervals determined by the body, in order to verify the quality of the internal checks on the vessel, taking into account, inter alia, the technological complexity of the vessels and the quantity of production.
(2) An adequate sample of the final vessels, taken on site by the [F3approved] body before their placing on the market, must be examined and appropriate tests as identified by the relevant parts of the [F4designated] standards, or equivalent tests set out in other relevant technical specifications, must be carried out to check the conformity of the vessel with the type described in the [F1Type] examination certificate and with the relevant requirements of these Regulations.
(3) The [F3approved] body must also ensure that the manufacturer checks series-produced vessels in accordance with paragraph 15(2)(c)(iii).
(4) Where a sample does not conform to the acceptable quality level, the [F3approved]body must take appropriate measures.
(5) The acceptance sampling procedure to be applied is intended to determine whether the manufacturing process of the vessel performs within acceptable limits, with a view to ensuring conformity of the vessel.
(6) The [F3approved] body must supply the Secretary of State and, on request, other [F3approved] bodies, F5... with a copy of the inspection report issued by it.
(7) The manufacturer must, under the responsibility of the [F3approved] body, affix the [F3approved] body's identification number during the manufacturing process.
Extent Information
E3This version of this provision extends to England and Wales and Scotland only; a separate version has been created for Northern Ireland only
Textual Amendments
F1Word in Sch. 2 substituted (E.W.S.) (31.12.2020) by The Product Safety and Metrology etc. (Amendment etc.) (EU Exit) Regulations 2019 (S.I. 2019/696), reg. 1, Sch. 21 para. 40(e) (with Sch. 21 para. 37) (as amended by S.I. 2020/676, regs. 1(1), 2); 2020 c. 1, Sch. 5 para. 1(1)
F3Words in Sch. 2 substituted (E.W.S.) (31.12.2020) by The Product Safety and Metrology etc. (Amendment etc.) (EU Exit) Regulations 2019 (S.I. 2019/696), reg. 1, Sch. 21 para. 40(c) (with Sch. 21 para. 37) (as amended by S.I. 2020/676, regs. 1(1), 2); 2020 c. 1, Sch. 5 para. 1(1)
F4Word in Sch. 2 para. 16(2) substituted (E.W.S.) (31.12.2020) by The Product Safety and Metrology etc. (Amendment etc.) (EU Exit) Regulations 2019 (S.I. 2019/696), reg. 1, Sch. 21 para. 40(f) (with Sch. 21 para. 37) (as amended by S.I. 2020/676, regs. 1(1), 2); 2020 c. 1, Sch. 5 para. 1(1)
F5Words in Sch. 2 para. 16(6) omitted (E.W.S.) (31.12.2020) by virtue of The Product Safety and Metrology etc. (Amendment etc.) (EU Exit) Regulations 2019 (S.I. 2019/696), reg. 1, Sch. 21 para. 40(k) (with Sch. 21 para. 37) (as amended by S.I. 2020/676, regs. 1(1), 2); 2020 c. 1, Sch. 5 para. 1(1)
16.—(1) The notified body must carry out vessel checks, or ensure that vessel checks are carried out, on random samples at random intervals determined by the body, in order to verify the quality of the internal checks on the vessel, taking into account, inter alia, the technological complexity of the vessels and the quantity of production.
(2) An adequate sample of the final vessels, taken on site by the notified body before their placing on the market, must be examined and appropriate tests as identified by the relevant parts of the harmonised standards, or equivalent tests set out in other relevant technical specifications, must be carried out to check the conformity of the vessel with the type described in the EU-type examination certificate and with the relevant requirements of these Regulations.
(3) The notified body must also ensure that the manufacturer checks series-produced vessels in accordance with paragraph 15(2)(c)(iii).
(4) Where a sample does not conform to the acceptable quality level, the notified body must take appropriate measures.
(5) The acceptance sampling procedure to be applied is intended to determine whether the manufacturing process of the vessel performs within acceptable limits, with a view to ensuring conformity of the vessel.
(6) The notified body must supply the Secretary of State and, on request, other notified bodies, other [F9relevant states] and the Commission, with a copy of the inspection report issued by it.
(7) The manufacturer must, under the responsibility of the notified body, affix the notified body's identification number during the manufacturing process.
Extent Information
E7This version of this provision extends to Northern Ireland only; a separate version has been created for England and Wales and Scotland only
Textual Amendments
F9Words in Sch. 2 para. 16(6) substituted (N.I.) (31.12.2020) by The Pressure Vessels (Amendment) (Northern Ireland) (EU Exit) Regulations 2020 (S.I. 2020/678), reg. 1(b), Sch. 1 para. 8(1)(c)
17.—(1) The manufacturer must affix the [F7UK] marking to each individual vessel that is in conformity with the type described in the [F1Type] examination certificate and satisfies the applicable requirements of these Regulations.
(2) The manufacturer must draw up a written [F8declaration] of conformity for each vessel model and keep it at the disposal of the enforcing authority for a period of 10 years beginning on the day on which the vessel has been placed on the market. The [F8declaration] of conformity must identify the vessel model for which it has been drawn up.
(3) A copy of the [F8declaration] of conformity must be made available to the enforcing authority upon request.
Extent Information
E4This version of this provision extends to England and Wales and Scotland only; a separate version has been created for Northern Ireland only
Textual Amendments
F1Word in Sch. 2 substituted (E.W.S.) (31.12.2020) by The Product Safety and Metrology etc. (Amendment etc.) (EU Exit) Regulations 2019 (S.I. 2019/696), reg. 1, Sch. 21 para. 40(e) (with Sch. 21 para. 37) (as amended by S.I. 2020/676, regs. 1(1), 2); 2020 c. 1, Sch. 5 para. 1(1)
F6Sch. 2 para. 17 heading substituted (E.W.S.) (31.12.2020) by The Product Safety and Metrology etc. (Amendment etc.) (EU Exit) Regulations 2019 (S.I. 2019/696), reg. 1, Sch. 21 para. 40(l) (with Sch. 21 para. 37) (as amended by S.I. 2020/676, regs. 1(1), 2); 2020 c. 1, Sch. 5 para. 1(1)
F7Word in Sch. 2 para. 17 substituted (E.W.S.) (31.12.2020) by The Product Safety and Metrology etc. (Amendment etc.) (EU Exit) Regulations 2019 (S.I. 2019/696), reg. 1, Sch. 21 para. 40(m)(i) (with Sch. 21 para. 37) (as amended by S.I. 2020/676, regs. 1(1), 2); 2020 c. 1, Sch. 5 para. 1(1)
F8Word in Sch. 2 para. 17 substituted (E.W.S.) (31.12.2020) by The Product Safety and Metrology etc. (Amendment etc.) (EU Exit) Regulations 2019 (S.I. 2019/696), reg. 1, Sch. 21 para. 40(m)(ii) (with Sch. 21 para. 37) (as amended by S.I. 2020/676, regs. 1(1), 2); 2020 c. 1, Sch. 5 para. 1(1)
17.—(1) The manufacturer must affix the CE marking to each individual vessel that is in conformity with the type described in the EU-type examination certificate and satisfies the applicable requirements of these Regulations.
(2) The manufacturer must draw up a written EU declaration of conformity for each vessel model and keep it at the disposal of the enforcing authority for a period of 10 years beginning on the day on which the vessel has been placed on the market. The EU declaration of conformity must identify the vessel model for which it has been drawn up.
(3) A copy of the EU declaration of conformity must be made available to the enforcing authority upon request.
Extent Information
E8This version of this provision extends to Northern Ireland only; a separate version has been created for England and Wales and Scotland only
The Whole Instrument you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Whole Instrument you have selected contains over 200 provisions and might take some time to download.
Would you like to continue?
Y Diweddaraf sydd Ar Gael (diwygiedig):Y fersiwn ddiweddaraf sydd ar gael o’r ddeddfwriaeth yn cynnwys newidiadau a wnaed gan ddeddfwriaeth ddilynol ac wedi eu gweithredu gan ein tîm golygyddol. Gellir gweld y newidiadau nad ydym wedi eu gweithredu i’r testun eto yn yr ardal ‘Newidiadau i Ddeddfwriaeth’.
Gwreiddiol (Fel y’i Deddfwyd neu y’i Gwnaed): Mae'r wreiddiol fersiwn y ddeddfwriaeth fel ag yr oedd pan gafodd ei deddfu neu eu gwneud. Ni wnaed unrhyw newidiadau i’r testun.
Rhychwant ddaearyddol: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.
Dangos Llinell Amser Newidiadau: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.
Mae Memoranda Esboniadol yn nodi datganiad byr o ddiben Offeryn Statudol ac yn rhoi gwybodaeth am ei amcan polisi a goblygiadau polisi. Maent yn ceisio gwneud yr Offeryn Statudol yn hygyrch i ddarllenwyr nad oes ganddynt gymhwyster cyfreithiol, ac maent yn cyd-fynd ag unrhyw Offeryn Statudol neu Offeryn Statudol Drafft a gyflwynwyd ger bron y Senedd o Fehefin 2004 ymlaen.
Gallwch wneud defnydd o ddogfennau atodol hanfodol a gwybodaeth ar gyfer yr eitem ddeddfwriaeth o’r tab hwn. Yn ddibynnol ar yr eitem ddeddfwriaeth sydd i’w gweld, gallai hyn gynnwys:
Impact Assessments generally accompany all UK Government interventions of a regulatory nature that affect the private sector, civil society organisations and public services. They apply regardless of whether the regulation originates from a domestic or international source and can accompany primary (Acts etc) and secondary legislation (SIs). An Impact Assessment allows those with an interest in the policy area to understand:
This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.
Defnyddiwch y ddewislen hon i agor dogfennau hanfodol sy’n cyd-fynd â’r ddeddfwriaeth a gwybodaeth am yr eitem hon o ddeddfwriaeth. Gan ddibynnu ar yr eitem o ddeddfwriaeth sy’n cael ei gweld gall hyn gynnwys:
liciwch ‘Gweld Mwy’ neu ddewis ‘Rhagor o Adnoddau’ am wybodaeth ychwanegol gan gynnwys