xmlns:atom="http://www.w3.org/2005/Atom"

SCHEDULES

SCHEDULE 10FOR PROTECTION OF ELECTRICITY, GAS, WATER AND SEWERAGE UNDERTAKERS

Removal of apparatus and construction of alternative apparatus by the promoter

16.  Nothing in paragraph 14 authorises the promoter to carry out the actual placing, erection, installation, bedding, packing, removal, connection or disconnection of any apparatus or, where the apparatus is laid in a trench, execute any filling around the apparatus within 600 millimetres (measured in any direction) of the apparatus.