The Infrastructure Planning (Model Provisions) (England and Wales) Order 2009

Fencing and other means of enclosure

This adran has no associated Memorandwm Esboniadol

13.—(1) No [stage of the] authorised development shall commence until written details of all proposed permanent and temporary fences, walls or other means of enclosure [for that stage] have, after consultation with the relevant planning authority, been submitted to and approved by the Commission.

(2) The [insert description], and any construction sites, must remain securely fenced at all times during construction of the authorised development.

(3) Any temporary fencing must be removed on completion of the authorised development.

(4) Any approved permanent fencing of the new [insert description] must be completed before the [insert description] is brought into use.